ND-21-0614, Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.6.03.04i (Index Number 609)

From kanterella
(Redirected from ML21216A337)
Jump to navigation Jump to search
Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.6.03.04i (Index Number 609)
ML21216A337
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 08/04/2021
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
ND-21-0614
Download: ML21216A337 (9)


Text

Michael J. Vox 7825 River Road Stk. Southern Nuclear Regulatory Affairs Director Waynesboro, GA 30830 Vogtle 3 & 4 706-848-6459 tel AU6 0 k 2021 Docket No.;52-025 52-026 ND-21-0614 10 CFR 52.99(c)(3)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 and Unit 4 Resubmittai of Notice of Uncompleted ITAAC 225-davs Prior to initial Fuel Load item 2.6.03.041 [index Number 6091 Ladies and Gentlemen:

Pursuant to 10 CFR 52.99(c)(3), Southern Nuclear Operating Company hereby notifies the NRC that as of August 4, 2021, Vogtle Electric Generating Plant(VEGP) Unit 3 and Unit 4 Uncompleted Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 2.6.03.04i

[Index Number 609] has not been completed greater than 225-days prior to initial fuel load for Unit 4. The Enclosure describes the plan for completing this ITAAC. Southern Nuclear Operating Company will, at a later date, provide additional notifications for Unit 4 ITAAC that have not been completed 225-days prior to initial fuel load.

Southern Nuclear Operating Company previously submitted Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load for Item 2.6.03.041 [Index Number 609] ND-19-0949

[ML19234A217], dated August 22, 2019. This resubmittai supersedes ND-19-0949 in its entirety and clarifies scope in Attachment A.

This notification is informed by the guidance described in NEI-08-01, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215. In accordance with NEI 08-01, this notification includes ITAAC for which required inspections, tests, or analyses have not been performed or have been only partially completed.

All ITAAC will be fully completed and all Section 52.99(c)(1) ITAAC Closure Notifications will be submitted to NRC to support the Commission finding that all acceptance criteria are met prior to plant operation, as required by 10 CFR 52.103(g).

This letter contains no new NRC regulatory commitments.

If there are any questions, please contact Kelli Roberts at 706-848-6991.

Respectfully submitted.

VJU Michael J. Ydx<

Regulatory Affairs irector Vogtle 3 & 4

Enclosure:

Vogtle Electric Generating Plant(VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 2.6.03.041 [Index Number 609]

MJY/RLB/sfr

U.S. Nuclear Regulatory Commission ND-21-0614 Page 2 of 3 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. Peter P. Sena III Mr. D. L. McKinney Mr. M. D. Meier Mr. G. Chick Mr. S. Stimac Mr. P. Martino Mr. M. J. Yox Mr. A. S. Parton Ms. K. A. Roberts Mr. C. T. Defnall Mr. C. E. Morrow Mr. J. M. Fisher Mr. R. L. Beiike Mr. S. Leighty Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:

Nuclear Requlatorv Commission Ms. M. Bailey Mr. M. King Mr. G. Bowman Ms. A. Veil M . C. P. Patel M . G. J. Khouri M . C. J. Even M B. J. Kemker Ms. N. C. Coovert M C. Welch M . J. Gaslevic M . O. Lopez-Santiago M G. Armstrong M M. Webb M T. Fredette M C. Santos M B. Davis M J. Vasquez M J. Eargle M E. Davidson M T. Fanelli Ms. K. McCurry Mr. J. Parent Mr. B. Griman

U.S. Nuclear Regulatory Commission ND-21-0614 Page 3 of 3 Oqiethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. 8. M. Jackson Daiton Utilities Mr. T. Bundros Westinqhouse Electric Company. LLC Dr. L. Oriani Mr. D. 0. Durham Mr. M. M. CorlettI Mr. Z. 8. Harper Mr. J. L. Coward Other Mr. 8. W. Kline, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, Inc.

Mr. 8. Roetger, Georgia Public Service Commission Mr. R. L. Trokey, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Balch Bingham

U.S. Nuclear Regulatory Commission ND-21-0614 Enclosure Page 1 of 6 Southern Nuclear Operating Company ND-21-0614 Enclosure Vogtle Electric Generating Plant(VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 2.6.03.041 [Index Number 609]

U.S. Nuclear Regulatory Commission ND-21-0614 Enclosure Page 2 of 6 ITAAC Statement Design Commitment 4.1) The IDS supplies an operating voltage at the terminals of the Class 1E motor operated valves identified in subsections 2.1.2, 2.2.1, 2.2.2, 2.2.3, 2.2.4, 2.3.2, 2.3.6, and 2.7.1 that is greater than or equal to the minimum design voltage.

Inspections. Tests. Analvses Testing will be performed by measuring the voltage during motor starting at both the IDS battery and motor-operated valve motor terminals while each motor-operated valve is stroked. Analyses will be performed to verify that the voltage at the motor-operated valve motor terminals is greater than or equal to the minimum design voltage of each motor-operated valve with an IDS battery terminal voltage of 210 Vdc.

Acceptance Criteria A report exists and concludes that IDS can provide a voltage greater than or equal to each valve's minimum design voltage to the motor terminals of each motor-operated valve when power is supplied under design conditions from IDS batteries with battery terminal voltage at 210 Vdc while each motor-operated valve is stroked.

ITAAC Completlon Description Testing is performed by measuring the voltage during motor starting at both the Class 1E dc and uninterruptible power supply system (IDS) battery and motor-operated valve(MOV) motor terminals while each MOV is stroked. Analyses are performed to verify that the voltage at the MOV motor terminals is greater than or equal to the minimum design voltage of each MOV with an IDS battery terminal voltage of 210 Vdc.

Analyses are performed in accordance with SV3-IDS-E0C-004 and SV4-IDS-E0C-004 (References 1 and 2)to determine the voltage drop on each power circuit at a battery voltage of 210 Vdc and the resulting voltage at the MOV terminals during normal operating conditions, and accident conditions. References 1 and 2 are the basis of analyses performed in accordance with SV3-IDS-E0C-018 and SV4-IDS-E0C-018 (References 3 and 4). The analyses determine the expected voltage at the MOV terminals and define the method for the determination of the minimum acceptance voltage for each MOV during preoperational testing.

Each MOV identified in Combined License (COL) Appendix C subsections 2.1.2, 2.2.1,2.2.2, 2.2.3, 2.2.4, 2.3.2, 2.3.6, and 2.7.1 (Attachment A)is stroked individually in accordance with References 5 and 6. The voltage at the battery terminals and at the MOV terminals is recorded during MOV operation using installed maintenance and test equipment. The recorded voltage at the MOV terminals is analyzed in accordance with the method described in References 3 and 4, to compare proportional values when the tested battery voltage is higher or lower than the nominal voltage assumed in the analyses of References 3 and 4, to determine the minimum acceptance voltage for each MOV. A resulting proportional voltage that is greater than or equal to the minimum design voltage of each MOV confirms the tested voltage is bounded by the analyses in References 3 and 4.

The analyses and preoperational test results (References 1 through 6)confirm that IDS can provide a voltage greater than or equal to each MOV's minimum design voltage to the terminals

U.S. Nuclear Regulatory Commission ND-21-0614 Enclosure Page 3 of 6 of each MOV,as specified in References 3 and 4, when power is supplied under design conditions from IDS batteries with battery terminal voltage at 210 Vdc while each MOV is stroked.

References 1 through 6 are available for NRG inspection as part of Unit 3 and Unit 4 ITAAC Completion Packages(Reference 7 and 8).

List of ITAAC Findings In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company(SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC.

References favaiiabie for NRG inspection)

1. SV3-IDS-E0C-004,"IDS Power Cable Sizing and Voltage Drop Analysis"
2. SV4-IDS-E0C-004,"IDS Power Cable Sizing and Voltage Drop Analysis"
3. SV3-IDS-E0C-018,"MOV Acceptance Voltage During Safety Related DC MOV Field Testing"
4. SV4-IDS-E0C-018,"MOV Acceptance Voltage During Safety Related DC MOV Field Testing"
5. 3-IDS-ITPP-503,"Class 1E DC and UPS System MOV Voltage Test"
6. 4-IDS-ITPP-503, "Class 1E DC and UPS System MOV Voltage Test"
7. 2.6.03.04i-U3-CP-Rev0, ITAAC Completion Package
8. 2.6.03.04i-U4-CP-Rev0, ITAAC Completion Package
9. NEI 08-01, "Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52"

U.S. Nuclear Regulatory Commission MD-21-0614 Enclosure Page 4 of 6 Attachment A Table 2.1.2-1*

Equipment Name* Tag No.*

First-stage ADS Motor-operated Valve(MOV) RCS-PL-V001A First-stage ADS MOV RCS-PL-V001B Second-stage ADS MOV RCS-PL-V002A Second-stage ADS MOV RCS-PL-V002B Third-stage ADS MOV RCS-PL-V003A Third-stage ADS MOV RCS-PL-V003B First-stage ADS Isolation MOV RCS-PL-V011A First-stage ADS Isolation MOV RCS-PL-V011B Second-stage ADS Isolation MOV RCS-PL-V012A Second-stage ADS Isolation MOV RCS-PL-V012B Third-stage ADS Isolation MOV RCS-PL-V013A Third-stage ADS Isolation MOV RCS-PL-V013B Fourth-stage ADS MOV RCS-PL-V014A Fourth-stage ADS MOV RCS-PL-V014B Fourth-stage ADS MOV RCS-PL-V014C Fourth-stage ADS MOV RCS-PL-V014D Table 2.2.1-1*

Equipment Name* Tag No.*

Component Cooling Water System (CCS) Containment Isolation Motor- CCS-PL-V200 operated Valve(MOV)- Inlet Line Outside Reactor Containment(ORC)

CCS Containment Isolation MOV - Outlet Line IRC CCS-PL-V207 CCS Containment Isolation MOV - Outlet Line ORC CCS-PL-V208 SFS Discharge Line Containment Isolation MOV - ORC SFS-PL-V038 SFS Suction Line Containment Isolation MOV - IRC SFS-PL-V034 SFS Suction Line Containment Isolation MOV - ORC SFS-PL-V035 Vacuum Relief Containment Isolation A MOV - ORC VFS-PL-V800A Vacuum Relief Containment Isolation B MOV - ORC VFS-PL-V800B Table 2.2.2-1*

Component Name* Tag No.*

PCCWST Isolation Valve MOV PCS-PL-V001C PCCWST Isolation Block MOV PCS-PL-V002A PCCWST Isolation Block MOV PCS-PL-V002B PCCWST Isolation Block MOV PCS-PL-V002C Excerpts from COL Tables 2.1.2-1, 2.2.1-1, and 2.2.2-1.

U.S. Nuclear Regulatory Commission ND-21-0614 Enclosure Page 5 of 6 Attachment A (Cont.)

Table 2.2.3-1*

Equipment Name* Tag No.*

CMT A Inlet Isolation Motor-operated Valve PXS-PL-V002A CMT B Inlet Isolation Motor-operated Valve PXS-PL-V002B PRHR HX Inlet Isolation Motor-operated Valve PXS-PL-V101 Containment Recirculation A Isolation Motor-operated Valve PXS-PL-V117A Containment Recirculation B Isolation Motor-operated Valve PXS-PL-V117B Table 2.2.4-1*

Equipment Name* Tag No.*

Power-operated Relief Valve Block Motor-operated Valve Steam SGS-PL-V027A Generator 01 Power-operated Relief Valve Block Motor-operated Valve Steam SGS-PL-V027B Generator 02 Startup Feedwater Isolation Motor-operated Valve SGS-PL-V067A Startup Feedwater Isolation Motor-operated Valve SGS-PL-V067B Table 2.3.2-1*

Equipment Name* Tag No.*

RCS Purification Motor-operated Isolation Valve CVS-PL-V001 RCS Purification Motor-operated Isolation Valve CVS-PL-V002 RCS Purification Motor-operated Isolation Valve CVS-PL-V003 CVS Makeup Line Containment Isolation Motor-operated Valve CVS-PL-V090 CVS Makeup Line Containment Isolation Motor-operated Valve CVS-PL-V091 Table 2.3.6-1*

Equipment Name* Tag No.*

RCS Inner Hot Leg Suction Motor-operated Isolation Valve RNS-PL-V001A RCS Inner Hot Leg Suction Motor-operated Isolation Valve RNS-PL-V001B RCS Outer Hot Leg Suction Motor-operated Isolation Valve RNS-PL-V002A RCS Outer Hot Leg Suction Motor-operated Isolation Valve RNS-PL-V002B RNS Discharge Motor-operated Containment Isolation Valve RNS-PL-V011 RNS Suction Header Motor-operated Containment Isolation Valve RNS-PL-V022 RNS Suction from IRWST Motor-operated Isolation Valve RNS-PL-V023 Excerpts from COL Tables 2.2.3-1, 2.2.4-1,2.3.2-1, and 2.3.6-1.

U.S. Nuclear Regulatory Commission ND-21-0614 Enclosure Page 6 of 6 Attachment A (Cent.)

Table 2.7.1-1*

Equipment Name* Tag No.*

MCR Supply Air Isolation Valve VBS-PL-V186 MCR Supply Air Isolation Valve VBS-PL-V187 MCR Return Air Isolation Valve VBS-PL-V188 MCR Return Air Isolation Valve VBS-PL-V189 MCR Exhaust Air Isolation Valve VBS-PL-V190 MCR Exhaust Air Isolation Valve VBS-PL-V191 MCR SDS (Vent) Isolation Valve SDS-PL-V001 MCR SDS(Vent) Isolation Valve SDS-PL-V002 Excerpt from COL Table 2.7.1-1.