Letter Sequence Response to RAI |
---|
EPID:L-2020-LLE-0204, Request for Exemption from the Annual Force on Force Training Requirements of 10 CFR 73, Appendix B, Section VI, Due to the COVID-19 Public Health Emergency (Approved, Closed) |
|
MONTHYEARNRC-20-0071, Request for Exemption from the Annual Force on Force Training Requirements of 10 CFR 73, Appendix B, Section VI, Due to the COVID-19 Public Health Emergency2020-11-13013 November 2020 Request for Exemption from the Annual Force on Force Training Requirements of 10 CFR 73, Appendix B, Section VI, Due to the COVID-19 Public Health Emergency Project stage: Request ML20329A3802020-11-23023 November 2020 NRR E-mail Capture - Fermi 2 (COVID-19) Part 73 Exemption Request Project stage: Other NRC-20-0077, Response to Request for Additional Information Regarding Exemption from the Annual Force on Force Training Requirements of 10 CFR 73, Appendix B, Section VI, Due to the COVID-19 Public Health Emergency2020-12-0303 December 2020 Response to Request for Additional Information Regarding Exemption from the Annual Force on Force Training Requirements of 10 CFR 73, Appendix B, Section VI, Due to the COVID-19 Public Health Emergency Project stage: Response to RAI ML20343A3502020-12-18018 December 2020 Exemption from Annual Force-on-Force Exercise Requirement of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel, Subsection VI.C.3(l)(1) (EPID L-2020-LLE-0204 (COVID-19)) Project stage: Approval 2020-11-23
[Table View] |
Similar Documents at Fermi |
---|
Category:Letter type:NRC
MONTHYEARNRC-24-0057, Update to NRC 24-0041: Technical Specification (TS) 5.6.7 – Post Accident Monitoring Report2024-09-0303 September 2024 Update to NRC 24-0041: Technical Specification (TS) 5.6.7 – Post Accident Monitoring Report NRC-24-0053, Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30, 20242024-08-30030 August 2024 Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30, 2024 NRC-24-0050, Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval2024-08-12012 August 2024 Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval NRC-24-0048, Submittal of Inservice Inspection Summary Report2024-08-0606 August 2024 Submittal of Inservice Inspection Summary Report NRC-24-0046, Fenni 2 Power Plant - Approval of the National Pollutant Discharge Elimination System Permit Application for Reissuance2024-07-25025 July 2024 Fenni 2 Power Plant - Approval of the National Pollutant Discharge Elimination System Permit Application for Reissuance NRC-24-0020, Submittal of Revision 51 to the Fermi 2 Radiological Emergency Response Preparedness Plan2024-07-24024 July 2024 Submittal of Revision 51 to the Fermi 2 Radiological Emergency Response Preparedness Plan NRC-24-0044, Enrico Fermi 1 License Expiration - 10 CFR 50.51 (Continuation of License)2024-07-10010 July 2024 Enrico Fermi 1 License Expiration - 10 CFR 50.51 (Continuation of License) NRC-24-0041, Technical Specification (TS) 5.6.7 - Post Accident Monitoring Report2024-06-21021 June 2024 Technical Specification (TS) 5.6.7 - Post Accident Monitoring Report NRC-24-0042, Regulat01y Issues Summaty (RIS) 24-01 Preparation and Scheduling of Operator Licensing Examinations to Submit Fonn 536, Operator Licensing Examination Data2024-06-18018 June 2024 Regulat01y Issues Summaty (RIS) 24-01 Preparation and Scheduling of Operator Licensing Examinations to Submit Fonn 536, Operator Licensing Examination Data NRC-24-0040, Verification of No Significant Hazards Considerations for License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance Supplement Provided in NRC-24-00332024-06-0606 June 2024 Verification of No Significant Hazards Considerations for License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance Supplement Provided in NRC-24-0033 NRC-24-0033, DTE Electric Company - Final Response to Request for Additional Information for License Amendment Request Regarding Risk Informed Approach to Performance ECCS Strainer Performance2024-05-30030 May 2024 DTE Electric Company - Final Response to Request for Additional Information for License Amendment Request Regarding Risk Informed Approach to Performance ECCS Strainer Performance NRC-24-0035, Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications2024-05-16016 May 2024 Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications NRC-24-0025, Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-222024-05-15015 May 2024 Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-22 NRC-24-0017, 2023 Annual Radioactive Effluent Release Report and 2023 Radiological Environmental Operating Report2024-04-29029 April 2024 2023 Annual Radioactive Effluent Release Report and 2023 Radiological Environmental Operating Report NRC-24-0032, Transmittal of the Core Operating Limits Report for Cycle 232024-04-25025 April 2024 Transmittal of the Core Operating Limits Report for Cycle 23 NRC-24-0027, Partial Response to Request for Additional Information for License Amendment Request Regarding Risk Informed Approach to Performance ECCS Strainer Performance2024-04-24024 April 2024 Partial Response to Request for Additional Information for License Amendment Request Regarding Risk Informed Approach to Performance ECCS Strainer Performance NRC-24-0031, Retake Exam Outline Submittal Letter2024-04-22022 April 2024 Retake Exam Outline Submittal Letter NRC-24-0018, 2023 Annual Non-Radiological Environmental Operating Report2024-04-0909 April 2024 2023 Annual Non-Radiological Environmental Operating Report NRC-24-0015, Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report2024-03-31031 March 2024 Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report NRC-24-0001, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Rev. 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, TSTF-439, Rev. 2, Eliminate Second Completion2024-03-21021 March 2024 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Rev. 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, TSTF-439, Rev. 2, Eliminate Second Completion NRC-24-0019, Submittal of 2023 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report2024-03-14014 March 2024 Submittal of 2023 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report NRC-24-0023, NRC-24-0023, Post Exam Package Submittal Letter to NRC2024-03-0707 March 2024 NRC-24-0023, Post Exam Package Submittal Letter to NRC NRC-24-0008, Levels and Sources of Property Insurance Coverage2024-02-15015 February 2024 Levels and Sources of Property Insurance Coverage NRC-24-0009, Request for NRC to Suspend Regulatory Audit of License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance for Fermi Unit 22024-02-0606 February 2024 Request for NRC to Suspend Regulatory Audit of License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance for Fermi Unit 2 NRC-24-0002, Clarification for Request for Additional Information Responses for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122024-01-12012 January 2024 Clarification for Request for Additional Information Responses for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 NRC-24-0007, Report of Changes to Quality Assurance Program for Radioactive Material Packages2024-01-12012 January 2024 Report of Changes to Quality Assurance Program for Radioactive Material Packages NRC-23-0079, Transmittal of Revision 1 of the Core Operating Limits Report for Cycle 222023-12-14014 December 2023 Transmittal of Revision 1 of the Core Operating Limits Report for Cycle 22 NRC-23-0077, Submittal of Revision 50 to the Fermi 2 Radiological Emergency Response Preparedness Plan2023-12-0404 December 2023 Submittal of Revision 50 to the Fermi 2 Radiological Emergency Response Preparedness Plan NRC-23-0075, Request for Exemption from Enhanced Weapons, Firearms Background Checks and Security Event Notification Implementation2023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks and Security Event Notification Implementation NRC-23-0073, Guarantee of Payment of Deferred Premiums2023-11-29029 November 2023 Guarantee of Payment of Deferred Premiums NRC-23-0071, Response to Request for Additional Information (RAI) for Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating2023-10-13013 October 2023 Response to Request for Additional Information (RAI) for Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating NRC-23-0062, Response to Request for Additional Information for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122023-10-12012 October 2023 Response to Request for Additional Information for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 NRC-23-0068, Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating2023-09-28028 September 2023 Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating NRC-23-0064, Additional Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-09-11011 September 2023 Additional Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0057, Independent Spent Fuel Storage Installation Cask Registration2023-08-31031 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0054, Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30 20232023-08-31031 August 2023 Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30 2023 NRC-23-0056, Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval2023-08-31031 August 2023 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval NRC-23-0061, Clarification for NRC-23-0059, Response to Request for Additional Information for Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water..2023-08-30030 August 2023 Clarification for NRC-23-0059, Response to Request for Additional Information for Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water.. NRC-23-0059, Response to Request for Additional Information Exigent License Amendment Request for Technical Specification 3.7.2,Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-25025 August 2023 Response to Request for Additional Information Exigent License Amendment Request for Technical Specification 3.7.2,Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0060, Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-25025 August 2023 Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0053, Independent Spent Fuel Storage Installation Cask Registration2023-08-23023 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0050, Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-10010 August 2023 Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0048, Independent Spent Fuel Storage Installation Cask Registration2023-08-0101 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0049, Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-07-24024 July 2023 Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0043, Independent Spent Fuel Storage Installation, Cask Registration2023-06-27027 June 2023 Independent Spent Fuel Storage Installation, Cask Registration NRC-23-0020, License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance2023-06-13013 June 2023 License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance NRC-23-0039, Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-06-0606 June 2023 Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0030, Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval2023-06-0505 June 2023 Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval NRC-23-0029, Snubber Program for the Fourth 10-Year Testing Interval2023-06-0505 June 2023 Snubber Program for the Fourth 10-Year Testing Interval NRC-23-0037, 56542-EN 56542 - Fermi2023-05-26026 May 2023 56542-EN 56542 - Fermi 2024-09-03
[Table view] Category:Response to Request for Additional Information (RAI)
MONTHYEARNRC-24-0033, DTE Electric Company - Final Response to Request for Additional Information for License Amendment Request Regarding Risk Informed Approach to Performance ECCS Strainer Performance2024-05-30030 May 2024 DTE Electric Company - Final Response to Request for Additional Information for License Amendment Request Regarding Risk Informed Approach to Performance ECCS Strainer Performance NRC-24-0027, Partial Response to Request for Additional Information for License Amendment Request Regarding Risk Informed Approach to Performance ECCS Strainer Performance2024-04-24024 April 2024 Partial Response to Request for Additional Information for License Amendment Request Regarding Risk Informed Approach to Performance ECCS Strainer Performance NRC-24-0002, Clarification for Request for Additional Information Responses for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122024-01-12012 January 2024 Clarification for Request for Additional Information Responses for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 NRC-23-0071, Response to Request for Additional Information (RAI) for Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating2023-10-13013 October 2023 Response to Request for Additional Information (RAI) for Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating NRC-23-0062, Response to Request for Additional Information for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122023-10-12012 October 2023 Response to Request for Additional Information for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 NRC-23-0061, Clarification for NRC-23-0059, Response to Request for Additional Information for Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water..2023-08-30030 August 2023 Clarification for NRC-23-0059, Response to Request for Additional Information for Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water.. NRC-23-0059, Response to Request for Additional Information Exigent License Amendment Request for Technical Specification 3.7.2,Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-25025 August 2023 Response to Request for Additional Information Exigent License Amendment Request for Technical Specification 3.7.2,Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0031, Response to NRC Request from Audit of License Amendment Request to Revise Technical Specification 3.8.1, AC Sources -Operating,' Emergency Diesel Generator Voltage and Frequency Surveillance Requirements2023-05-16016 May 2023 Response to NRC Request from Audit of License Amendment Request to Revise Technical Specification 3.8.1, AC Sources -Operating,' Emergency Diesel Generator Voltage and Frequency Surveillance Requirements NRC-21-0045, Response to Request for Additional Information Regarding License Amendment Request to Revise the Fermi 2 Technical Specifications2021-08-17017 August 2021 Response to Request for Additional Information Regarding License Amendment Request to Revise the Fermi 2 Technical Specifications NRC-21-0032, Response to Request for Additional Information Regarding Revised Relief Request RR-A39 for the Fourth Ten-Year Inservice Inspection Interval2021-07-0101 July 2021 Response to Request for Additional Information Regarding Revised Relief Request RR-A39 for the Fourth Ten-Year Inservice Inspection Interval NRC-21-0007, Response to Request for Additional Information Regarding Revised Relief Request RR-A39 for the Fourth Ten-Year Inservice Inspection Interval2021-05-27027 May 2021 Response to Request for Additional Information Regarding Revised Relief Request RR-A39 for the Fourth Ten-Year Inservice Inspection Interval NRC-20-0077, Response to Request for Additional Information Regarding Exemption from the Annual Force on Force Training Requirements of 10 CFR 73, Appendix B, Section VI, Due to the COVID-19 Public Health Emergency2020-12-0303 December 2020 Response to Request for Additional Information Regarding Exemption from the Annual Force on Force Training Requirements of 10 CFR 73, Appendix B, Section VI, Due to the COVID-19 Public Health Emergency NRC-20-0057, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle2020-09-11011 September 2020 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle NRC-20-0046, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Utilize Neutron Absorbing Inserts in Criticality Safety Analysis for Fermi 2 Spent Fuel Storage Racks2020-07-30030 July 2020 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Utilize Neutron Absorbing Inserts in Criticality Safety Analysis for Fermi 2 Spent Fuel Storage Racks NRC-19-0084, Response to Request for Additional Information Regarding Inservice Testing Program Relief Request VRR-006 for the Fourth 10-Year Interval2019-12-0606 December 2019 Response to Request for Additional Information Regarding Inservice Testing Program Relief Request VRR-006 for the Fourth 10-Year Interval NRC-19-0039, Response to NRC Request for Additional Information for License Amendment Request to Revise Technical Specification 3.3.5.3, Reactor Pressure Vessel (RPV) Water Inventory Control Instrumentation2019-06-18018 June 2019 Response to NRC Request for Additional Information for License Amendment Request to Revise Technical Specification 3.3.5.3, Reactor Pressure Vessel (RPV) Water Inventory Control Instrumentation NRC-19-0045, Response to Request for Additional Information Regarding Snubber Program Relief Request RR-S1 for the Fourth 10-Year Interval2019-06-12012 June 2019 Response to Request for Additional Information Regarding Snubber Program Relief Request RR-S1 for the Fourth 10-Year Interval NRC-19-0042, Responses to Requests for Additional Information Regarding Relief Requests for the Inservice Inspection Program Fourth Ten-year Interval2019-06-11011 June 2019 Responses to Requests for Additional Information Regarding Relief Requests for the Inservice Inspection Program Fourth Ten-year Interval NRC-18-0045, Response to NRC Requests for Additional Information for License Amendment Request to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control2018-08-0707 August 2018 Response to NRC Requests for Additional Information for License Amendment Request to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control NRC-18-0040, Supplemental Information in Response to NRC Request for Additional Information for License Amendment Request to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control2018-06-27027 June 2018 Supplemental Information in Response to NRC Request for Additional Information for License Amendment Request to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control NRC-18-0032, Response to NRC Request for Additional Information for License Amendment Request to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control2018-05-17017 May 2018 Response to NRC Request for Additional Information for License Amendment Request to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control NRC-18-0019, Response to NRC Request for Additional Information for License Amendment Request to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control.2018-04-0404 April 2018 Response to NRC Request for Additional Information for License Amendment Request to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control. NRC-18-0015, Response to Request for Additional Information (Set 1) Regarding License Amendment Request to Revise Technical Specifications to Eliminate Main Steam Line Radiation Monitor Reactor Trip and Primary Containment Isolation System Group 1.2018-02-27027 February 2018 Response to Request for Additional Information (Set 1) Regarding License Amendment Request to Revise Technical Specifications to Eliminate Main Steam Line Radiation Monitor Reactor Trip and Primary Containment Isolation System Group 1. NRC-18-0014, Response to Request for Additional Information Regarding Relief Request No. RR-A37, Revision 1, for the Inservice Inspection Program Third 10-Year Interval2018-02-0606 February 2018 Response to Request for Additional Information Regarding Relief Request No. RR-A37, Revision 1, for the Inservice Inspection Program Third 10-Year Interval NRC-18-0001, DTE Energy Company - Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification Section 3.7.22018-01-0808 January 2018 DTE Energy Company - Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification Section 3.7.2 NRC-17-0036, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications for Emergency Core Cooling System Instrumentation and Reactor Core Isolation Cooling System Instrumentation2017-03-30030 March 2017 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications for Emergency Core Cooling System Instrumentation and Reactor Core Isolation Cooling System Instrumentation NRC-16-0067, Spent Fuel Pool Evaluation Supplemental Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2016-12-0909 December 2016 Spent Fuel Pool Evaluation Supplemental Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident NRC-16-0049, Response to Request for Additional Information Regarding License Amendment Request to Revise Integrated Leak Rate Test - Type a and Type C Test Intervals2016-08-11011 August 2016 Response to Request for Additional Information Regarding License Amendment Request to Revise Integrated Leak Rate Test - Type a and Type C Test Intervals NRC-16-0042, Response to NRC Request for Additional Information Regarding Environmental Review of the License Renewal Application, Severe Accident Mitigation Alternatives Sensitivity Analysis2016-07-19019 July 2016 Response to NRC Request for Additional Information Regarding Environmental Review of the License Renewal Application, Severe Accident Mitigation Alternatives Sensitivity Analysis NRC-16-0038, Response to Request for Additional Information Regarding Revised Relief Request PRR-007 for the Inservice Testing Program Third 10-Year Interval2016-06-23023 June 2016 Response to Request for Additional Information Regarding Revised Relief Request PRR-007 for the Inservice Testing Program Third 10-Year Interval NRC-16-0021, Supplemental Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 17 RAI 4.3.3-12016-03-10010 March 2016 Supplemental Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 17 RAI 4.3.3-1 NRC-16-0003, Response to NRC Request for Additional Information for the Review of the License Renewal Application - Set 382016-02-0101 February 2016 Response to NRC Request for Additional Information for the Review of the License Renewal Application - Set 38 NRC-16-0004, Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) and Response to Request for Additional Information2016-01-20020 January 2016 Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) and Response to Request for Additional Information NRC-15-0089, Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 372015-09-24024 September 2015 Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 37 NRC-15-0083, Supplemental Response to NRC Request for Additional Information for the Review of the License Renewal Application - Set 332015-08-20020 August 2015 Supplemental Response to NRC Request for Additional Information for the Review of the License Renewal Application - Set 33 NRC-15-0077, Response to Request for Additional Information (RAI) Regarding the License Amendment Request to Revise the Emergency Action Level (EAL) Scheme for the Emergency Plan2015-07-28028 July 2015 Response to Request for Additional Information (RAI) Regarding the License Amendment Request to Revise the Emergency Action Level (EAL) Scheme for the Emergency Plan NRC-15-0066, Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 332015-07-0606 July 2015 Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 33 2024-05-30
[Table view] |
Text
Peter Dietrich Senior Vice President and Chief Nuclear Officer DTE Electric Company 6400 N. Dixie Highway, Newport, MI 48166 Tel: 734.586.4153 Fax: 734.586.1431 Email: peter.dietrich@dteenergy.com December 3, 2020 NRC-20-0077 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555-0001 Fermi 2 Power Plant NRC Docket No. 50-341 NRC License No. NPF-43
Subject:
Response to Request for Additional Information Regarding Exemption from the Annual Force on Force Training Requirements of 10 CFR 73, Appendix B, Section VI, Due to the COVID-19 Public Health Emergency
References:
- 1) DTE letter NRC-20-0071, Fermi Nuclear Plant, Unit 2, Request for Exemption from the Annual Force on Force Training Requirements of 10 CFR 73, Appendix B, Section VI, Due to the COVID-19 Public Health Emergency, dated November 13, 2020 (ML20318A383)
- 2) NRC letter to DTE Electric Company, Fermi 2 - Temporary Exemption from the Annual Force-on-Force Training Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel,Section VI (EPID L-2020-LLE-0128) [COVID-19], dated September 10, 2020 (ML20226A116)
In Reference 1, DTE Electric Company (DTE), requested an exemption from the annual force-on-force (FOF) requirement of Title 10 of the Code of Federal Regulations (CFR) Part 73, Appendix B,Section VI, for the Fermi Nuclear Plant, Unit 2 (Fermi 2). The exemption would supersede the previously approved exemption (Reference 2) that required Fermi 2 to restore compliance with the annual FOF exercise requalification requirement within 90 days after the end of the coronavirus disease 2019 (COVID-19) public health emergency (PHE), or December 31, 2020, whichever occurs first.
In an email from Mr. Surinder Arora to Ms. Margaret Offerle dated November 23, 2020, the NRC sent DTE a Request for Additional Information (RAI) regarding the Reference 1 exemption request. The response to the RAI is provided in the Enclosure.
USNRC NRC-20-0077 Page 2 No new commitments are being made in this submittal.
Should you have any questions or require additional information, please contact Mr. Greg Anderson, Manager - Nuclear Security, at (734) 586-1527.
Sincerely, Peter Dietrich Senior Vice President and Chief Nuclear Officer
Enclosure:
Response to Request for Additional Information cc: NRC Project Manager NRC Resident Office Regional Administrator, Region III
Enclosure to NRC-20-0077 Fermi 2 NRC Docket No. 50-341 Operating License No. NPF-43 Response to Request for Additional Information
Enclosure to NRC-20-0077 Page 1 Response to Request for Additional Information NRC RAI
Background
By letter dated November 13, 2020 (Agencywide Documents and Access Management System (ADAMS) Accession No. ML20318A383), DTE Electric Company (DTE), requested an exemption from the annual force-on-force (FOF) requirement of Title 10 of the Code of Federal Regulations (CFR) Part 73, Appendix B,Section VI, subsection C.3.(l)(1) for the Fermi Nuclear Plant, Unit 2 (Fermi). This exemption would supersede the previously approved exemption dated September 10, 2020 (ADAMS Accession No. ML20226A116) that required Fermi to restore compliance with the annual FOF exercise requalification requirement within 90 days after the end of the coronavirus disease 2019 (COVID-19) public health emergency (PHE), or December 31, 2020, whichever occurs first.
Subsection C.3.(l)(1) requires that:
Each member of each shift who is assigned duties and responsibilities required to implement the safeguards contingency plan and licensee protective strategy participates in at least one (1) tactical response drill on a quarterly basis and one (1) force-on-force exercise on an annual basis.
DTE indicated that Fermi will not be able to comply with the annual FOF exercise requirement of the specified regulation for calendar year (CY) 2020 due to the continued implementation of COVID-19 PHE training requalification controls consistent with those recommended by the State of Michigan and the DTE corporate pandemic response plan.
In the request, DTE stated that in order to ensure impacted security personnel maintain the knowledge, skills, and abilities required to effectively perform assigned duties and responsibilities and thus maintain contingency response readiness, Fermi will continue to conduct quarterly tactical response drills, including tabletop exercises. DTE also said Fermi will maintain a list of the names of the individuals who will not meet the requalification requirements and will include the dates of the last qualification.
Issue On October 13, 2020, the NRC issued updated guidance for licensees that require exemptions from CY 2020 annual FOF exercises during the COVID-19 PHE (ADAMS Accession No. ML20273A058). The guidance states, in part:
. . . Since the NRC issued the April 2020 letter, some licensees have taken measures recommended by Federal, State, and local authorities to help protect their personnel, including security personnel, from exposure to COVID-19. These measures include the implementation of COVID-19-related controls such as the widespread use of face
Enclosure to NRC-20-0077 Page 2 coverings for site personnel, frequent surface sanitization and handwashing, and social distancing (i.e., maintaining 6 feet of separation between individuals where practical).
Accordingly, some of these licensees have been able to resume many routine activities with little or no disruption or with the use of other controls, to accomplish the same tasks safely. In addition, due to site-specific configurations and implementation of certain safety measures, some commercial power reactor and fuel cycle facility licensees have successfully conducted their required annual FOF exercises during the PHE without adversely impacting the sites security staffing or operations.
Nevertheless, the impacts of COVID-19 are still ongoing for some licensees and will likely extend beyond December 31, 2020. These circumstances may prevent licensees from completing their missed CY 2020 FOF exercises by December 31, 2020. They may also prevent licensees that did not previously request an exemption from the annual FOF exercise requirements and, therefore, are still required to complete an FOF exercise before the end of the CY, from being able to complete that exercise by December 31, 2020. To address this situation, the NRC is prepared to expedite consideration of requests for an exemption that would relieve licensees from making up any missed CY 2020 annual FOF exercises. The NRC is also prepared to expedite consideration of exemption requests from the requirement to conduct an annual FOF exercise in CY 2020 for those licensees who were not previously granted such an exemption.
This updated guidance requests that licensees submit the following information if they have previously been granted a temporary exemption from the annual FOF exercise requirement:
- a discussion as to why the licensee is unable to conduct make-up exercises due to continuing COVID-19 PHE impacts as committed to in their initial exemption request submission; and
- In addition to the information above, a description of how they intend to maintain contingency response readiness.
Request Other than continuing to conduct quarterly tactical response drills, including tabletop exercises, describe the security training activities that Fermi will conduct to reinforce the skills or activities associated with annual FOF exercises and contribute to Fermis ability to maintain contingency response readiness. Attachment 1 to EGM 20-002, Enforcement Guidance Memorandum 20-002 - Attachment 1, Dispositioning Violations of NRC Requirements for Completion Periodicities Associated with Security Training and Requalification Requirements During the COVID-19 Public Health Emergency (ADAMS Accession No. ML20091L385), and Regulatory Guide 5.75, Training and Qualification of Security Personnel at Nuclear Power Reactor Facilities (ADAMS Accession No. ML091690037), provide the following examples of such activities: timeline and limited-scope drills, virtual-based communication exercises, firearms qualifications and range activities, and individual walkdowns of response routes and contingency positions.
Enclosure to NRC-20-0077 Page 3 DTE RESPONSE Impacted security personnel continue to maintain proficiency with the knowledge, skills and abilities required to effectively implement the protective strategy to protect the station against the design basis threat as described in 10 CFR 73.1, Purpose and Scope, because Fermi 2 has continued to conduct the following training requalification requirements of Section VI of Appendix B to Part 73.
- Quarterly tactical response drills (Tabletop drills, Timeline drills, Limited-scope tactical response drills)
- Annual firearms familiarization
- Annual daylight qualification course
- Annual night fire qualification course
- Annual tactical qualification course
- Annual physical examination
- Annual physical fitness test
- Weapons range activity (4-month periodicity)
- Annual written exam Therefore, Fermi 2 continues to maintain a physical protection program that provides high assurance of the effectiveness of the onsite physical protection program and protective strategy, including the capability of the armed response team to carry out their assigned duties and responsibilities during safeguards contingency events.