B16243, Transmits Operational Readiness Plan,Rev 1 Covering Three Key Phases of Activities at Millstone Unit 2:Readiness for Restart,Startup & Power Ascension & Performance Improvement

From kanterella
(Redirected from ML20147H125)
Jump to navigation Jump to search
Transmits Operational Readiness Plan,Rev 1 Covering Three Key Phases of Activities at Millstone Unit 2:Readiness for Restart,Startup & Power Ascension & Performance Improvement
ML20147H125
Person / Time
Site: Millstone Dominion icon.png
Issue date: 03/27/1997
From: Bowling M
NORTHEAST NUCLEAR ENERGY CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20147H129 List:
References
B16243, NUDOCS 9704020156
Download: ML20147H125 (1)


Text

_ __

. ~ _.

l-m\\

. Nordet Rope Ferry Rd. (Route 156), Waterford, CT 06385 r

Nuclear Energy untooe Nocica, power station

)

3 Northeast Nuclear Energy Company

)

P.O. Box 128 i

j Waterford, CT 06385-0128 (203) 447-1791 Faz (203) 444-4277 j

He Northeast Utilities System March 27,1997 Docket No. 50-336 B16243 U.S. Nuclear Regulatory Commission i

Attention: Document Control Desk i

Washington, DC 20555 i

Millstone Nuclear Power Station, Unit No. 2 I

Operational Readiness Plan l-As stated in our letter dated February 26,1997,m Northeast Nuclear Energy Company (NNECO) hereby transmits for Millstone Unit 2 the Operational Readiness Plan (ORP),

j Revision 1. The ORP covers three key phases of activities at Millstone Unit No. 2: Readiness '

For Restart, Startup and Power Ascension, and Performance improvement. The ORP has been completed for the Readiness for Restart Phase at this time. The entire plan will be j

completed as part of the Readiness for Restart activities. The list of currently open items that can be safely deferred until after restart will be addressed in the Performance !mprovement phase of the ORP.

)

It should be noted that the ORP Performance improvement phase will be a' long-term commitment to excellence. The determination that standards are sufficient for Readiness for Restart will be made from a review of overall performance as collectively exhibited by key l

performance indicators, self-assessment, and the completion of the items identified in our February 26,1997 letter.

if you have any questions, please contact me at (860) 440-0436.

1 l

Very Truly yours,.

{

l NORTHEAST NUCLEAR ENERGY COMPANY l

  1. E SA Pof $oo$ obO$$336[_

Martin L Bowling, Jr.

j

}'

P PDR Millstone Unit No. 2 Recovery Officer a

I cc:

H. J. Miller, Region l Administrator i

4 D. G. Mcdonald, Jr., NRC Project Manager, MUstone Unit No. 2

}q@

l D. P. Beaulieu, Senior Resident inspector, Millstone Unit No. 2 W. D. Travers, PhD., Director, Special Projects Office 2

l M

M. L. Bowling, Jr. letter to the U.S. Nuclear Regulatory Commission, " Readiness-for-Restart Worklist," dated February 26,1997.

jgggggggggg$