NG-97-0327, Forwards DAEC 1996 Refueling Outage Inservice Insp Summary Rept Addressing Exams Performed from 950420-961116.Info Re Augmented ISIs Performed Also,Encl

From kanterella
(Redirected from ML20134P925)
Jump to navigation Jump to search
Forwards DAEC 1996 Refueling Outage Inservice Insp Summary Rept Addressing Exams Performed from 950420-961116.Info Re Augmented ISIs Performed Also,Encl
ML20134P925
Person / Time
Site: Duane Arnold NextEra Energy icon.png
Issue date: 02/14/1997
From: Peveler K
IES UTILITIES INC., (FORMERLY IOWA ELECTRIC LIGHT
To:
NRC (Affiliation Not Assigned), NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20134P928 List:
References
NG-97-0327, NG-97-327, NUDOCS 9702260171
Download: ML20134P925 (2)


Text

I Duane Amold Energy Center 3277 DAEC Road Palo, IA 52324 Telephone 319 8517611 Fat 319 8517611 UTILITIES

)

February 14,1997 NG-97-0327 Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission j

Attn: Document Control Desk Mail Station PI-37 Washington, DC 20555-0001

Subject:

Duane Arnold Energy Center Docket No: 50-331 Op. License No: DPR-49 DAEC Inservice Inspection Report

Reference:

NG-96-1807, from J. Franz (IES) to NRC, dated September 30,1996 File:

A-107a, A-286a, B-31c, SpF-118 In accordance with the requirements of Paragraph IWA-6230 in Section XI of the ASME Boiler and Pressure Vessel Code and 10 CFR Section 50.55a(g), we are submitting our 1996 Refueling Outage Inservice Inspection Summary Report (Attachment 1). This report addresses examinations which were performed at the Duane Arnold Energy Center (DAEC) during the time period from April 20,1995 through November 16,1996. As the third 10-year interval began on November 1,1996, this summary report contains inspections credited to both the second and the third 10-year inservice inspection intervals.

tf h

I i

9702260171 970214' PDR ADOCK 05000331 G

PDR(,

An IES Industnes Company

NG-97-0327 February 14,1997 Page 2

. ' Attachment 2 provides information regarding augmented inservice inspections performed during the 1996 Refueling Outage. These inspections include those required by NUREG-0313, Revision 2, " Technical Report on Material Selection and Processing Guidelines for BWR Coolant Pressure Boundary Piping" and NUREG-0619, "BWR Feedwater Nozzle and Control Rod Drive Retum Line Noz2le Cracking."

The examinations required by NUREG-0619 include a periodic penetrant test (PT) of the feedwater nozzles. In the referenced letter, IES Utilities informed the NRC of our intent to modify the DAEC's commitment to NUREG-0619, in accordance with the Nuclear Energy Institute (NEI)" Guideline for Managing NRC Commitments," Revision 2. We revised our commitment to perform this periodic feedwater nozzle PT and instead performed an ultrasonic examination (UT) of the feedwater nozzles during the 1996 Refueling Outage.

. Our review of the inspection reports has determined that all examined items are acceptable. These inspection reports are on file and are available for your review upon request.

- Should you have any questions regarding the attached information, please contact this office.

Sincerely, Kenneth E. Peveler Manager, Regulatory Performance Attachments: 1) Inservice Inspection Summary Report

2) Augmented Inspection Results RFO-14 cc:

C. Rushworth (w/o)

L. Root (w/o)

J. Franz (w/o)

G. Kelly (NRC-NRR)

A. B. Beach (Region III)

.NRC Resident Office W. Mueller(ANII)(w/o)