B11732, Forwards Startup Test Rept,Cycle 7. Criticality Achieved on 850630 & 100% Power Reached on 850711 Following end-of-Cycle 6 Refueling Outage
| ML20133N054 | |
| Person / Time | |
|---|---|
| Site: | Millstone |
| Issue date: | 10/04/1985 |
| From: | Opeka J NORTHEAST NUCLEAR ENERGY CO., NORTHEAST UTILITIES |
| To: | Murley T NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| Shared Package | |
| ML20133N058 | List: |
| References | |
| B11732, NUDOCS 8510280370 | |
| Download: ML20133N054 (1) | |
Text
N UTILITIES cenerei Orvices seieen street. eeriin. connect'cui emc cu, u e ac. c,wa=,
J
.,v,
..u.c.ve rs ue c cw=
P.O. BOX 270 a.cw aeta wa ceaa' H ARTFORD. CONNECTICUT 06141-0270 k
L J [ [ [ E' U N,'c " 2',
(203) 665-5000 l
October 4,1985 Docket No. 50-336 Bil732 Dr. Thomas E. Murley, Regional Administrator Region I U.S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, PA 19406 Gentlemen:
Millstone Nuclear Power Station, Unit No. 2 Start-Up Test Report Millstone Unit No. 2 achieved criticality on June 30, 1985 and reached 100%
power on July 11, 1985 following its end-of-cycle 6 refueling outage.
As required by the Millstone Nuclear Power Station Unit No. 2 Technical Specifications, Section 6.9, Northeast Nuclear Energy Company hereby submits the attached Millstone Unit No. 2 Start-Up Test Report.
se trust you will find this information satisfactory.
Very truly yours, NORTHEAST NUCLEAR ENERGY COMPANY E. F CLvL
- 3. F. Opeka )
u Senior Vice President Director of Nuclear Reactor Regulation cc:
Attn:
Mr. Edward 3. Butcher, Chief Operating Reactors Branch #3 U.S. Nuclear Regulatory Commission d l)
Washington, D.C. 20555
. O, '
\\ v
.b ib B510280370 g h 36 PDH ADOCK PDR P
-