BECO-LTR-96-108, Forwards Rev 11D of Pilgrim Nuclear Power Station Colr

From kanterella
(Redirected from ML20133A845)
Jump to navigation Jump to search
Forwards Rev 11D of Pilgrim Nuclear Power Station Colr
ML20133A845
Person / Time
Site: Pilgrim
Issue date: 12/23/1996
From: Boullette E
BOSTON EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20133A849 List:
References
BECO-LTR-96-108, NUDOCS 9701020133
Download: ML20133A845 (1)


Text

.

c i

y. ? - A l

G Boston Edison Pilgnm Nuclear Power Station 1

Rocky Hill Road i

Plymouth, Massachusetts 02300 i

l December 23, 1996 E. T. Boulette, PhD BECo Ltr # 96-108 i

Senior Vice President-Nuclear U.S. Nuclear Regulatory Commission i

Attention: Document Control Desk Washington, DC 20555 Docket No. 50-293 License No. DPR-35 Core Operatina Limits Reports The attached revision of Pilgrim's Core Operating Limits Report is submitted in accordance with I

the requirements of Pilgrim's Technical Specification 6.9.A.4.d.

Revision #11D provides cycle-specific limits for operating Pilgrim with reduced feedwater temperatures during the remainder of cycle #11.

OY L

i E. T. Boulette, PhD i

PMK\\dmc\\ rap 96\\colr

[

Attachment:

Pilgrim Nuclear Power Station Core Operating Limits Report I

cc: Mr. Alan Wang, Project Manager Division of Reactor Projects - 1/11 Mail Stop: 14B2 U.S. Nuclear Regulatory Commission l

1 White Flint North 1

11555 Rockville Pike Rockville, MD 20852 1

U.S, Nuclear Regulatory Commission Region 1

/

475 Allendale Road I

KOf /f King of Prussia, PA 19406 Senior Resident inspector i

Pilgrim Nuclear Power Station 9701020133 961223 PDR ADOCK 05000293 p

PDR 61U1iU