Similar Documents at Fermi |
---|
Category:LICENSEE EVENT REPORT (SEE ALSO AO
MONTHYEARNRC-94-0025, LER 93-014-01:on 931225,turbine Generator Tripped When Mechanical Overspeed Device Was Activated.Caused by Severe Vibration.Corrective Action:Assessment of Structural Integrity of Pedestal Was conducted.W/940425 Ltr1994-04-25025 April 1994 LER 93-014-01:on 931225,turbine Generator Tripped When Mechanical Overspeed Device Was Activated.Caused by Severe Vibration.Corrective Action:Assessment of Structural Integrity of Pedestal Was conducted.W/940425 Ltr NRC-93-0058, LER 93-008-00:on 930518,discovered That Recorder T50-R802A Could Not Be Considered Operable Per TS 3.3.7.5.Caused by Personnel Error.Lessons Learned Will Be Incorporated Into Training Programs & Plant procedures.W/930618 Ltr1993-06-18018 June 1993 LER 93-008-00:on 930518,discovered That Recorder T50-R802A Could Not Be Considered Operable Per TS 3.3.7.5.Caused by Personnel Error.Lessons Learned Will Be Incorporated Into Training Programs & Plant procedures.W/930618 Ltr NRC-93-0055, LER 93-007-00:on 930420,reactor Tripped on Intermediate Range Monitor Upscale During Reactor Pressure & Feedwater Transient.Caused by Personnel Error.Affected Pressure Transmitters replaced.W/930520 Ltr1993-05-20020 May 1993 LER 93-007-00:on 930420,reactor Tripped on Intermediate Range Monitor Upscale During Reactor Pressure & Feedwater Transient.Caused by Personnel Error.Affected Pressure Transmitters replaced.W/930520 Ltr NRC-91-0058, LER 91-008-00:on 910424,reactor Bldg HVAC Tripped,Div I SGTS Auto Started & Div I Control Ctr HVAC Shifted to Recirculation Mode Due to Mispositioned Trip Output Logic switch.W/910524 Ltr1991-05-24024 May 1991 LER 91-008-00:on 910424,reactor Bldg HVAC Tripped,Div I SGTS Auto Started & Div I Control Ctr HVAC Shifted to Recirculation Mode Due to Mispositioned Trip Output Logic switch.W/910524 Ltr NRC-91-0069, LER 90-012-01:on 901016,HPIC Steam Line Flow Transmitter Failed Due to Short Circuit Across Capacitor Plates.Circuit Boards Replaced & Failure Analysis Performed by Rosemount,Inc.W/910524 Ltr1991-05-24024 May 1991 LER 90-012-01:on 901016,HPIC Steam Line Flow Transmitter Failed Due to Short Circuit Across Capacitor Plates.Circuit Boards Replaced & Failure Analysis Performed by Rosemount,Inc.W/910524 Ltr NRC-91-0055, LER 91-006-00:on 910410,balance of Plant Breaker Opened Causing Reactor Bldg HVAC Isolation.Caused by Component Failures.Nprds Search Conducted for Similiar Problems. W/910510 Ltr1991-05-10010 May 1991 LER 91-006-00:on 910410,balance of Plant Breaker Opened Causing Reactor Bldg HVAC Isolation.Caused by Component Failures.Nprds Search Conducted for Similiar Problems. W/910510 Ltr NRC-91-0004, LER 90-013-00:on 901228,determined That Inadequate Control Could Occur During Air Grab Sampling Process.Caused by Lack of Proper Administrative Controls in Sampling Procedure. Sample Suction added.W/910128 Ltr1991-01-28028 January 1991 LER 90-013-00:on 901228,determined That Inadequate Control Could Occur During Air Grab Sampling Process.Caused by Lack of Proper Administrative Controls in Sampling Procedure. Sample Suction added.W/910128 Ltr NRC-90-0144, LER 90-007-00:on 900829,control Ctr Ventilation Shifted to Recirculation Due to Blown Fuse.Caused by Design Deficiency in Div 1 & 2 Radiation Monitor Trip Circuitry.Design Change Implemented to Eliminate Trip Relay logic.W/900928 Ltr1990-09-28028 September 1990 LER 90-007-00:on 900829,control Ctr Ventilation Shifted to Recirculation Due to Blown Fuse.Caused by Design Deficiency in Div 1 & 2 Radiation Monitor Trip Circuitry.Design Change Implemented to Eliminate Trip Relay logic.W/900928 Ltr NRC-90-0107, LER 88-034-01:on 880831,RWCU Outboard Isolation Valve Closed,Causing RWCU Pumps to Trip.Caused by Loss of Continuity to Relay Due to Deposits Built Up on Surface of Contacts.Relay in Isolation Circuits replaced.W/900622 Ltr1990-06-22022 June 1990 LER 88-034-01:on 880831,RWCU Outboard Isolation Valve Closed,Causing RWCU Pumps to Trip.Caused by Loss of Continuity to Relay Due to Deposits Built Up on Surface of Contacts.Relay in Isolation Circuits replaced.W/900622 Ltr NRC-90-0087, LER 90-002-01:on 900202,determined That Area Radiation Surveillance Procedure 44.080.301 Listed Incorrect Values for Alarm Setpoints.Caused by Unavailable Setpoint Calculations.Procedure revised.W/900608 Ltr1990-06-0808 June 1990 LER 90-002-01:on 900202,determined That Area Radiation Surveillance Procedure 44.080.301 Listed Incorrect Values for Alarm Setpoints.Caused by Unavailable Setpoint Calculations.Procedure revised.W/900608 Ltr NRC-90-0075, LER 87-045-02:on 870908,operator Removed Fuse Which Deenergized Dc Control Power to Bus 72C,resulting in Loss of Power Supply to Swing Bus & to LPCI Loop Selection Valves. Caused by Design Flaw.Design Change initiated.W/900518 Ltr1990-05-18018 May 1990 LER 87-045-02:on 870908,operator Removed Fuse Which Deenergized Dc Control Power to Bus 72C,resulting in Loss of Power Supply to Swing Bus & to LPCI Loop Selection Valves. Caused by Design Flaw.Design Change initiated.W/900518 Ltr NRC-90-0073, LER 90-003-00:on 900410,Div I Reactor Protection Sys Power Supply Failure & Subsequent MSIV Closure.Caused by Coil Burn Up.Relays Replaced & MG Sets Returned to svc.W/900508 Ltr1990-05-0808 May 1990 LER 90-003-00:on 900410,Div I Reactor Protection Sys Power Supply Failure & Subsequent MSIV Closure.Caused by Coil Burn Up.Relays Replaced & MG Sets Returned to svc.W/900508 Ltr NRC-90-0048, LER 89-037-01:on 891220,determined That Tech Spec Stroke Time Testing for Outboard Reactor Water Sample Line Isolation Valve Not Performed Prior to Expiration on 891125. Caused by Personnel Error.Procedure revised.W/900322 Ltr1990-03-22022 March 1990 LER 89-037-01:on 891220,determined That Tech Spec Stroke Time Testing for Outboard Reactor Water Sample Line Isolation Valve Not Performed Prior to Expiration on 891125. Caused by Personnel Error.Procedure revised.W/900322 Ltr NRC-90-0027, LER 89-034-01:on 891208,two Members of Fire Watch Did Not Complete Assigned Hourly Rounds from 891002-1207 in Reactor & Auxiliary Bldgs.Both Individuals Terminated & Fire Stations Equipped W/Unique Bar code.W/900221 Ltr1990-02-21021 February 1990 LER 89-034-01:on 891208,two Members of Fire Watch Did Not Complete Assigned Hourly Rounds from 891002-1207 in Reactor & Auxiliary Bldgs.Both Individuals Terminated & Fire Stations Equipped W/Unique Bar code.W/900221 Ltr NRC-90-0021, LER 90-001-00:on 900108,annunciator 2D5 Alarmed for Div II ECCS Testability Logic/Power Failure.Caused by Blown Fuse. Fuse Installed During Course of Troubleshooting W/No Subsequent Problems noted.W/900207 Ltr1990-02-0707 February 1990 LER 90-001-00:on 900108,annunciator 2D5 Alarmed for Div II ECCS Testability Logic/Power Failure.Caused by Blown Fuse. Fuse Installed During Course of Troubleshooting W/No Subsequent Problems noted.W/900207 Ltr NRC-90-0019, LER 89-028-01:on 891028,eight Safety Relief Valves Failed Set Pressure Tolerance Test.Cause Under Review by Util & Generically by BWR Owners Group Safety Relief Valve Set Point Drift Committee.Valves Removed & cleaned.W/900131 Ltr1990-01-31031 January 1990 LER 89-028-01:on 891028,eight Safety Relief Valves Failed Set Pressure Tolerance Test.Cause Under Review by Util & Generically by BWR Owners Group Safety Relief Valve Set Point Drift Committee.Valves Removed & cleaned.W/900131 Ltr NRC-90-0018, LER 89-039-00:on 891226,Div I Emergency Equipment Cooling Water & Svc Water Sys Automatically Started Due to Partial Load Shed of Bus 72E.Caused by Personnel Error. Accountability Meeting Held on 900117.W/900125 Ltr1990-01-25025 January 1990 LER 89-039-00:on 891226,Div I Emergency Equipment Cooling Water & Svc Water Sys Automatically Started Due to Partial Load Shed of Bus 72E.Caused by Personnel Error. Accountability Meeting Held on 900117.W/900125 Ltr NRC-90-0008, LER 89-037-00:on 891220,determined That Tech Spec Stroke Time Testing for Outboard Reactor Water Sample Line Isolation Valve Not Performed.Caused by Personnel Error. Critique of Event Being developed.W/900119 Ltr1990-01-19019 January 1990 LER 89-037-00:on 891220,determined That Tech Spec Stroke Time Testing for Outboard Reactor Water Sample Line Isolation Valve Not Performed.Caused by Personnel Error. Critique of Event Being developed.W/900119 Ltr NRC-90-0007, LER 89-036-00:on 891218,control Room Operator Inadvertently Depressed Closed Push Buttons on Inboard MSIVs A,B & C & Reactor Scram Resulted.Caused by Operator Error.Operator Involved Was Removed from Licensed duties.W/900117 Ltr1990-01-17017 January 1990 LER 89-036-00:on 891218,control Room Operator Inadvertently Depressed Closed Push Buttons on Inboard MSIVs A,B & C & Reactor Scram Resulted.Caused by Operator Error.Operator Involved Was Removed from Licensed duties.W/900117 Ltr ML19354E0971990-01-12012 January 1990 LER 89-038-00:on 891223,reactor Scrammed When Fire Occurred in Vicinity of High Pressure Turbine.Caused by Oil Soaked Inlagging Pads & Ignited When Turbine Casing Heated Up to Oil Flashpoint.Insulation Pads replaced.W/900122 Ltr NRC-90-0005, LER 89-035-00:on 891210,steam Jet Air Ejectors Placed in Svc W/O Required Surveillance Completed & Required Grab Sample Not Started Until 891213.Caused by Personnel Error.Off Gas Sys Operating Procedure Will Be revised.W/900111 Ltr1990-01-11011 January 1990 LER 89-035-00:on 891210,steam Jet Air Ejectors Placed in Svc W/O Required Surveillance Completed & Required Grab Sample Not Started Until 891213.Caused by Personnel Error.Off Gas Sys Operating Procedure Will Be revised.W/900111 Ltr NRC-90-0004, LER 89-030-00:on 891026,Channel C Level 1 & 2 Replacement Transmitter Found to Be Installed Incorrectly & Condition Recognized on 891210,when Level 2 Trip Unit Was Reading Upscale.Caused by Personnel error.W/900109 Ltr1990-01-0909 January 1990 LER 89-030-00:on 891026,Channel C Level 1 & 2 Replacement Transmitter Found to Be Installed Incorrectly & Condition Recognized on 891210,when Level 2 Trip Unit Was Reading Upscale.Caused by Personnel error.W/900109 Ltr NRC-90-0002, LER 89-033-00:on 891207,volt-ohm Meter Connected to Incorrect Terminal,Causing Div II of Emergency Equipment Cooling Water Sys to Actuate.Caused by Personnel Error.Sys Secured & Channel Test Successfully completed.W/900108 Ltr1990-01-0808 January 1990 LER 89-033-00:on 891207,volt-ohm Meter Connected to Incorrect Terminal,Causing Div II of Emergency Equipment Cooling Water Sys to Actuate.Caused by Personnel Error.Sys Secured & Channel Test Successfully completed.W/900108 Ltr NRC-90-0003, LER 89-034-00:on 891208,review of Key Card Transactions Showed That Fire Watch Personnel Missed Assigned Hourly Fire Watch from 891020-1207.Fire Watch Person Discharged.Plan Re Improvement of Fire Watches developed.W/900108 Ltr1990-01-0808 January 1990 LER 89-034-00:on 891208,review of Key Card Transactions Showed That Fire Watch Personnel Missed Assigned Hourly Fire Watch from 891020-1207.Fire Watch Person Discharged.Plan Re Improvement of Fire Watches developed.W/900108 Ltr NRC-89-0261, LER 89-028-00:on 891129,ESF Actuations Occurred During Set Up for Surveillance.Caused by Blown Fuse.Blown Fuse Replaced & Affected Sys Returned to Normal Operation Following Completion of surveillance.W/891228 Ltr1989-12-28028 December 1989 LER 89-028-00:on 891129,ESF Actuations Occurred During Set Up for Surveillance.Caused by Blown Fuse.Blown Fuse Replaced & Affected Sys Returned to Normal Operation Following Completion of surveillance.W/891228 Ltr NRC-89-0260, LER 89-021-01:on 890906,35 of 237 Containment Isolation Valves Exceeded Administrative Allowable Leakage Rate When Tested.Caused by Normal Wear & Degradation During Specified Time Interval.Valves Cleaned & repaired.W/891221 Ltr1989-12-21021 December 1989 LER 89-021-01:on 890906,35 of 237 Containment Isolation Valves Exceeded Administrative Allowable Leakage Rate When Tested.Caused by Normal Wear & Degradation During Specified Time Interval.Valves Cleaned & repaired.W/891221 Ltr NRC-89-0255, LER 89-031-00:on 891120,both Div II Emergency Equipment Cooling Water (EECW) & Emergency Equipment Svc Water Sys Pumps Tripped Immediately.Caused by Inadequacies in Stated Procedures.Procedures revised.W/891220 Ltr1989-12-20020 December 1989 LER 89-031-00:on 891120,both Div II Emergency Equipment Cooling Water (EECW) & Emergency Equipment Svc Water Sys Pumps Tripped Immediately.Caused by Inadequacies in Stated Procedures.Procedures revised.W/891220 Ltr NRC-89-0259, LER 89-017-01:on 890810,new Analysis of Feedwater Line Break Scenario Assumes Failure of Feedwater Startup Control Valve in Open Position.Review of Pipe Break Documentation Conducted.Updated FSAR Change to Be submitted.W/891215 Ltr1989-12-15015 December 1989 LER 89-017-01:on 890810,new Analysis of Feedwater Line Break Scenario Assumes Failure of Feedwater Startup Control Valve in Open Position.Review of Pipe Break Documentation Conducted.Updated FSAR Change to Be submitted.W/891215 Ltr NRC-89-0256, LER 89-022-01:on 890923 & 24,reactor Protection Sys Logic Actuations Occurred When Fuse C71A-F15B Blew.On 890928, Reactor Bldg HVAC Isolated.Caused by Personnel Error. Procedures Will Be revised.W/891215 Ltr1989-12-15015 December 1989 LER 89-022-01:on 890923 & 24,reactor Protection Sys Logic Actuations Occurred When Fuse C71A-F15B Blew.On 890928, Reactor Bldg HVAC Isolated.Caused by Personnel Error. Procedures Will Be revised.W/891215 Ltr NRC-89-0258, LER 89-025-00:on 891115,low Level 2 Signal Unintentionally Induced During Reactor Pressure Vessel Hydrostatic Pressure Test.Caused by Personnel Error.Personnel Counseled on Notifying & Coordinating Instrument lineups.W/891215 Ltr1989-12-15015 December 1989 LER 89-025-00:on 891115,low Level 2 Signal Unintentionally Induced During Reactor Pressure Vessel Hydrostatic Pressure Test.Caused by Personnel Error.Personnel Counseled on Notifying & Coordinating Instrument lineups.W/891215 Ltr NRC-89-0251, LER 89-019-01:on 890819,discovered That Div I Recirculation Fan Not Rotating Which Resulted in Decrease in Control Room Air Pressure.Caused by Lack of Lubrication in Bearings. Lubrication Program Improvements evaluated.W/891130 Ltr1989-11-30030 November 1989 LER 89-019-01:on 890819,discovered That Div I Recirculation Fan Not Rotating Which Resulted in Decrease in Control Room Air Pressure.Caused by Lack of Lubrication in Bearings. Lubrication Program Improvements evaluated.W/891130 Ltr NRC-89-0249, LER 89-029-00:on 891023,half Scram Signal Received When Power Was Lost on Reactor Protection Sys Bus B,Resulting in Several ESFs Actuation.Caused by Location of Breaker Operating Switch in High Traffic area.W/891122 Ltr1989-11-22022 November 1989 LER 89-029-00:on 891023,half Scram Signal Received When Power Was Lost on Reactor Protection Sys Bus B,Resulting in Several ESFs Actuation.Caused by Location of Breaker Operating Switch in High Traffic area.W/891122 Ltr NRC-89-0246, LER 89-028-00:on 891020,eight safety-related Valves Failed Set Pressure Test.Cause Under Review.All Valves Removed for Testing Being Refurbished,Cleaned,Retested & Recertified to Be within Plant Accepted tolerances.W/891120 Ltr1989-11-20020 November 1989 LER 89-028-00:on 891020,eight safety-related Valves Failed Set Pressure Test.Cause Under Review.All Valves Removed for Testing Being Refurbished,Cleaned,Retested & Recertified to Be within Plant Accepted tolerances.W/891120 Ltr NRC-89-0244, LER 89-024-00:on 891019,recognized That Secondary Containment Dampers Not Tested as Required by Tech Spec 3.6.5.2.Caused by Operations Personnel Error.Event Critique to Be Included in Required Reading program.W/891120 Ltr1989-11-20020 November 1989 LER 89-024-00:on 891019,recognized That Secondary Containment Dampers Not Tested as Required by Tech Spec 3.6.5.2.Caused by Operations Personnel Error.Event Critique to Be Included in Required Reading program.W/891120 Ltr NRC-89-0194, LER 89-027-00:on 891015,reactor Bldg Hvac,Control Ctr HVAC & Drywell Floor & Equipment Drain Sumps Isolated & Standby Gas Treatment Sys & Noninterrruptalbe Control Air Compressors Started.Caused by Personnel error.W/891114 Ltr1989-11-14014 November 1989 LER 89-027-00:on 891015,reactor Bldg Hvac,Control Ctr HVAC & Drywell Floor & Equipment Drain Sumps Isolated & Standby Gas Treatment Sys & Noninterrruptalbe Control Air Compressors Started.Caused by Personnel error.W/891114 Ltr NRC-89-0193, LER 89-026-00:on 891010,control Ctr HVAC Shifted to Recirculation Mode of Operaton Due to Short Circuit.Caused by Failure of Lamp Filament When Being Tightened.Fuse & Lamp Replaced & Sys Returned to Normal operation.W/891109 Ltr1989-11-0909 November 1989 LER 89-026-00:on 891010,control Ctr HVAC Shifted to Recirculation Mode of Operaton Due to Short Circuit.Caused by Failure of Lamp Filament When Being Tightened.Fuse & Lamp Replaced & Sys Returned to Normal operation.W/891109 Ltr NRC-89-0192, LER 87-045-01:on 870908,fuse Removed Which Deenergized Dc Control Power to Bus 72C & Resulted in Loss of Power Supply to Swing Bus & LPCI Loop Selection Valves.Caused by Design Error.Undervoltage Relay Added & Training held.W/891106 Ltr1989-11-0606 November 1989 LER 87-045-01:on 870908,fuse Removed Which Deenergized Dc Control Power to Bus 72C & Resulted in Loss of Power Supply to Swing Bus & LPCI Loop Selection Valves.Caused by Design Error.Undervoltage Relay Added & Training held.W/891106 Ltr NRC-89-0190, LER 89-023-00:on 890924,personnel Inadvertently Caused Trip of Essential Safety Sys Buses 64B & 64C.Caused by Failure of Personnel Involved to Review Applicable Prints Prior to Performing Test.Event Reviewed w/personnel.W/891024 Ltr1989-10-24024 October 1989 LER 89-023-00:on 890924,personnel Inadvertently Caused Trip of Essential Safety Sys Buses 64B & 64C.Caused by Failure of Personnel Involved to Review Applicable Prints Prior to Performing Test.Event Reviewed w/personnel.W/891024 Ltr NRC-89-0189, LER 89-022-00:on 890923 & 24,reactor Protection Sys Logic Actuations Occurred When Fuse Blew.On 890928,reactor Bldg HVAC Isolated When Jumper Lifted Per Incorrect Work Plan Instruction.Caused by Personnel error.W/891023 Ltr1989-10-23023 October 1989 LER 89-022-00:on 890923 & 24,reactor Protection Sys Logic Actuations Occurred When Fuse Blew.On 890928,reactor Bldg HVAC Isolated When Jumper Lifted Per Incorrect Work Plan Instruction.Caused by Personnel error.W/891023 Ltr NRC-89-0186, LER 89-016-01:on 890711,Div 1 of RHR Svc Water Sys Declared Inoperable Due to Low Nitrogen Pressure for Cooling Tower Fan Brake.Caused by Leak in One Hose.Leaking Hose Replaced & Nitrogen Pressure restored.W/891006 Ltr1989-10-0606 October 1989 LER 89-016-01:on 890711,Div 1 of RHR Svc Water Sys Declared Inoperable Due to Low Nitrogen Pressure for Cooling Tower Fan Brake.Caused by Leak in One Hose.Leaking Hose Replaced & Nitrogen Pressure restored.W/891006 Ltr NRC-89-0185, LER 89-021-00:on 890906,local Leak Rate Testing of Containment Isolation Valves & Penetrations Exceeded Tech Spec Limit.Caused by Excessive Containment Isolation Valve Leakage Due to Degradation of valve.W/891006 Ltr1989-10-0606 October 1989 LER 89-021-00:on 890906,local Leak Rate Testing of Containment Isolation Valves & Penetrations Exceeded Tech Spec Limit.Caused by Excessive Containment Isolation Valve Leakage Due to Degradation of valve.W/891006 Ltr 1994-04-25
[Table view] Category:RO)
MONTHYEARNRC-94-0025, LER 93-014-01:on 931225,turbine Generator Tripped When Mechanical Overspeed Device Was Activated.Caused by Severe Vibration.Corrective Action:Assessment of Structural Integrity of Pedestal Was conducted.W/940425 Ltr1994-04-25025 April 1994 LER 93-014-01:on 931225,turbine Generator Tripped When Mechanical Overspeed Device Was Activated.Caused by Severe Vibration.Corrective Action:Assessment of Structural Integrity of Pedestal Was conducted.W/940425 Ltr NRC-93-0058, LER 93-008-00:on 930518,discovered That Recorder T50-R802A Could Not Be Considered Operable Per TS 3.3.7.5.Caused by Personnel Error.Lessons Learned Will Be Incorporated Into Training Programs & Plant procedures.W/930618 Ltr1993-06-18018 June 1993 LER 93-008-00:on 930518,discovered That Recorder T50-R802A Could Not Be Considered Operable Per TS 3.3.7.5.Caused by Personnel Error.Lessons Learned Will Be Incorporated Into Training Programs & Plant procedures.W/930618 Ltr NRC-93-0055, LER 93-007-00:on 930420,reactor Tripped on Intermediate Range Monitor Upscale During Reactor Pressure & Feedwater Transient.Caused by Personnel Error.Affected Pressure Transmitters replaced.W/930520 Ltr1993-05-20020 May 1993 LER 93-007-00:on 930420,reactor Tripped on Intermediate Range Monitor Upscale During Reactor Pressure & Feedwater Transient.Caused by Personnel Error.Affected Pressure Transmitters replaced.W/930520 Ltr NRC-91-0058, LER 91-008-00:on 910424,reactor Bldg HVAC Tripped,Div I SGTS Auto Started & Div I Control Ctr HVAC Shifted to Recirculation Mode Due to Mispositioned Trip Output Logic switch.W/910524 Ltr1991-05-24024 May 1991 LER 91-008-00:on 910424,reactor Bldg HVAC Tripped,Div I SGTS Auto Started & Div I Control Ctr HVAC Shifted to Recirculation Mode Due to Mispositioned Trip Output Logic switch.W/910524 Ltr NRC-91-0069, LER 90-012-01:on 901016,HPIC Steam Line Flow Transmitter Failed Due to Short Circuit Across Capacitor Plates.Circuit Boards Replaced & Failure Analysis Performed by Rosemount,Inc.W/910524 Ltr1991-05-24024 May 1991 LER 90-012-01:on 901016,HPIC Steam Line Flow Transmitter Failed Due to Short Circuit Across Capacitor Plates.Circuit Boards Replaced & Failure Analysis Performed by Rosemount,Inc.W/910524 Ltr NRC-91-0055, LER 91-006-00:on 910410,balance of Plant Breaker Opened Causing Reactor Bldg HVAC Isolation.Caused by Component Failures.Nprds Search Conducted for Similiar Problems. W/910510 Ltr1991-05-10010 May 1991 LER 91-006-00:on 910410,balance of Plant Breaker Opened Causing Reactor Bldg HVAC Isolation.Caused by Component Failures.Nprds Search Conducted for Similiar Problems. W/910510 Ltr NRC-91-0004, LER 90-013-00:on 901228,determined That Inadequate Control Could Occur During Air Grab Sampling Process.Caused by Lack of Proper Administrative Controls in Sampling Procedure. Sample Suction added.W/910128 Ltr1991-01-28028 January 1991 LER 90-013-00:on 901228,determined That Inadequate Control Could Occur During Air Grab Sampling Process.Caused by Lack of Proper Administrative Controls in Sampling Procedure. Sample Suction added.W/910128 Ltr NRC-90-0144, LER 90-007-00:on 900829,control Ctr Ventilation Shifted to Recirculation Due to Blown Fuse.Caused by Design Deficiency in Div 1 & 2 Radiation Monitor Trip Circuitry.Design Change Implemented to Eliminate Trip Relay logic.W/900928 Ltr1990-09-28028 September 1990 LER 90-007-00:on 900829,control Ctr Ventilation Shifted to Recirculation Due to Blown Fuse.Caused by Design Deficiency in Div 1 & 2 Radiation Monitor Trip Circuitry.Design Change Implemented to Eliminate Trip Relay logic.W/900928 Ltr NRC-90-0107, LER 88-034-01:on 880831,RWCU Outboard Isolation Valve Closed,Causing RWCU Pumps to Trip.Caused by Loss of Continuity to Relay Due to Deposits Built Up on Surface of Contacts.Relay in Isolation Circuits replaced.W/900622 Ltr1990-06-22022 June 1990 LER 88-034-01:on 880831,RWCU Outboard Isolation Valve Closed,Causing RWCU Pumps to Trip.Caused by Loss of Continuity to Relay Due to Deposits Built Up on Surface of Contacts.Relay in Isolation Circuits replaced.W/900622 Ltr NRC-90-0087, LER 90-002-01:on 900202,determined That Area Radiation Surveillance Procedure 44.080.301 Listed Incorrect Values for Alarm Setpoints.Caused by Unavailable Setpoint Calculations.Procedure revised.W/900608 Ltr1990-06-0808 June 1990 LER 90-002-01:on 900202,determined That Area Radiation Surveillance Procedure 44.080.301 Listed Incorrect Values for Alarm Setpoints.Caused by Unavailable Setpoint Calculations.Procedure revised.W/900608 Ltr NRC-90-0075, LER 87-045-02:on 870908,operator Removed Fuse Which Deenergized Dc Control Power to Bus 72C,resulting in Loss of Power Supply to Swing Bus & to LPCI Loop Selection Valves. Caused by Design Flaw.Design Change initiated.W/900518 Ltr1990-05-18018 May 1990 LER 87-045-02:on 870908,operator Removed Fuse Which Deenergized Dc Control Power to Bus 72C,resulting in Loss of Power Supply to Swing Bus & to LPCI Loop Selection Valves. Caused by Design Flaw.Design Change initiated.W/900518 Ltr NRC-90-0073, LER 90-003-00:on 900410,Div I Reactor Protection Sys Power Supply Failure & Subsequent MSIV Closure.Caused by Coil Burn Up.Relays Replaced & MG Sets Returned to svc.W/900508 Ltr1990-05-0808 May 1990 LER 90-003-00:on 900410,Div I Reactor Protection Sys Power Supply Failure & Subsequent MSIV Closure.Caused by Coil Burn Up.Relays Replaced & MG Sets Returned to svc.W/900508 Ltr NRC-90-0048, LER 89-037-01:on 891220,determined That Tech Spec Stroke Time Testing for Outboard Reactor Water Sample Line Isolation Valve Not Performed Prior to Expiration on 891125. Caused by Personnel Error.Procedure revised.W/900322 Ltr1990-03-22022 March 1990 LER 89-037-01:on 891220,determined That Tech Spec Stroke Time Testing for Outboard Reactor Water Sample Line Isolation Valve Not Performed Prior to Expiration on 891125. Caused by Personnel Error.Procedure revised.W/900322 Ltr NRC-90-0027, LER 89-034-01:on 891208,two Members of Fire Watch Did Not Complete Assigned Hourly Rounds from 891002-1207 in Reactor & Auxiliary Bldgs.Both Individuals Terminated & Fire Stations Equipped W/Unique Bar code.W/900221 Ltr1990-02-21021 February 1990 LER 89-034-01:on 891208,two Members of Fire Watch Did Not Complete Assigned Hourly Rounds from 891002-1207 in Reactor & Auxiliary Bldgs.Both Individuals Terminated & Fire Stations Equipped W/Unique Bar code.W/900221 Ltr NRC-90-0021, LER 90-001-00:on 900108,annunciator 2D5 Alarmed for Div II ECCS Testability Logic/Power Failure.Caused by Blown Fuse. Fuse Installed During Course of Troubleshooting W/No Subsequent Problems noted.W/900207 Ltr1990-02-0707 February 1990 LER 90-001-00:on 900108,annunciator 2D5 Alarmed for Div II ECCS Testability Logic/Power Failure.Caused by Blown Fuse. Fuse Installed During Course of Troubleshooting W/No Subsequent Problems noted.W/900207 Ltr NRC-90-0019, LER 89-028-01:on 891028,eight Safety Relief Valves Failed Set Pressure Tolerance Test.Cause Under Review by Util & Generically by BWR Owners Group Safety Relief Valve Set Point Drift Committee.Valves Removed & cleaned.W/900131 Ltr1990-01-31031 January 1990 LER 89-028-01:on 891028,eight Safety Relief Valves Failed Set Pressure Tolerance Test.Cause Under Review by Util & Generically by BWR Owners Group Safety Relief Valve Set Point Drift Committee.Valves Removed & cleaned.W/900131 Ltr NRC-90-0018, LER 89-039-00:on 891226,Div I Emergency Equipment Cooling Water & Svc Water Sys Automatically Started Due to Partial Load Shed of Bus 72E.Caused by Personnel Error. Accountability Meeting Held on 900117.W/900125 Ltr1990-01-25025 January 1990 LER 89-039-00:on 891226,Div I Emergency Equipment Cooling Water & Svc Water Sys Automatically Started Due to Partial Load Shed of Bus 72E.Caused by Personnel Error. Accountability Meeting Held on 900117.W/900125 Ltr NRC-90-0008, LER 89-037-00:on 891220,determined That Tech Spec Stroke Time Testing for Outboard Reactor Water Sample Line Isolation Valve Not Performed.Caused by Personnel Error. Critique of Event Being developed.W/900119 Ltr1990-01-19019 January 1990 LER 89-037-00:on 891220,determined That Tech Spec Stroke Time Testing for Outboard Reactor Water Sample Line Isolation Valve Not Performed.Caused by Personnel Error. Critique of Event Being developed.W/900119 Ltr NRC-90-0007, LER 89-036-00:on 891218,control Room Operator Inadvertently Depressed Closed Push Buttons on Inboard MSIVs A,B & C & Reactor Scram Resulted.Caused by Operator Error.Operator Involved Was Removed from Licensed duties.W/900117 Ltr1990-01-17017 January 1990 LER 89-036-00:on 891218,control Room Operator Inadvertently Depressed Closed Push Buttons on Inboard MSIVs A,B & C & Reactor Scram Resulted.Caused by Operator Error.Operator Involved Was Removed from Licensed duties.W/900117 Ltr ML19354E0971990-01-12012 January 1990 LER 89-038-00:on 891223,reactor Scrammed When Fire Occurred in Vicinity of High Pressure Turbine.Caused by Oil Soaked Inlagging Pads & Ignited When Turbine Casing Heated Up to Oil Flashpoint.Insulation Pads replaced.W/900122 Ltr NRC-90-0005, LER 89-035-00:on 891210,steam Jet Air Ejectors Placed in Svc W/O Required Surveillance Completed & Required Grab Sample Not Started Until 891213.Caused by Personnel Error.Off Gas Sys Operating Procedure Will Be revised.W/900111 Ltr1990-01-11011 January 1990 LER 89-035-00:on 891210,steam Jet Air Ejectors Placed in Svc W/O Required Surveillance Completed & Required Grab Sample Not Started Until 891213.Caused by Personnel Error.Off Gas Sys Operating Procedure Will Be revised.W/900111 Ltr NRC-90-0004, LER 89-030-00:on 891026,Channel C Level 1 & 2 Replacement Transmitter Found to Be Installed Incorrectly & Condition Recognized on 891210,when Level 2 Trip Unit Was Reading Upscale.Caused by Personnel error.W/900109 Ltr1990-01-0909 January 1990 LER 89-030-00:on 891026,Channel C Level 1 & 2 Replacement Transmitter Found to Be Installed Incorrectly & Condition Recognized on 891210,when Level 2 Trip Unit Was Reading Upscale.Caused by Personnel error.W/900109 Ltr NRC-90-0002, LER 89-033-00:on 891207,volt-ohm Meter Connected to Incorrect Terminal,Causing Div II of Emergency Equipment Cooling Water Sys to Actuate.Caused by Personnel Error.Sys Secured & Channel Test Successfully completed.W/900108 Ltr1990-01-0808 January 1990 LER 89-033-00:on 891207,volt-ohm Meter Connected to Incorrect Terminal,Causing Div II of Emergency Equipment Cooling Water Sys to Actuate.Caused by Personnel Error.Sys Secured & Channel Test Successfully completed.W/900108 Ltr NRC-90-0003, LER 89-034-00:on 891208,review of Key Card Transactions Showed That Fire Watch Personnel Missed Assigned Hourly Fire Watch from 891020-1207.Fire Watch Person Discharged.Plan Re Improvement of Fire Watches developed.W/900108 Ltr1990-01-0808 January 1990 LER 89-034-00:on 891208,review of Key Card Transactions Showed That Fire Watch Personnel Missed Assigned Hourly Fire Watch from 891020-1207.Fire Watch Person Discharged.Plan Re Improvement of Fire Watches developed.W/900108 Ltr NRC-89-0261, LER 89-028-00:on 891129,ESF Actuations Occurred During Set Up for Surveillance.Caused by Blown Fuse.Blown Fuse Replaced & Affected Sys Returned to Normal Operation Following Completion of surveillance.W/891228 Ltr1989-12-28028 December 1989 LER 89-028-00:on 891129,ESF Actuations Occurred During Set Up for Surveillance.Caused by Blown Fuse.Blown Fuse Replaced & Affected Sys Returned to Normal Operation Following Completion of surveillance.W/891228 Ltr NRC-89-0260, LER 89-021-01:on 890906,35 of 237 Containment Isolation Valves Exceeded Administrative Allowable Leakage Rate When Tested.Caused by Normal Wear & Degradation During Specified Time Interval.Valves Cleaned & repaired.W/891221 Ltr1989-12-21021 December 1989 LER 89-021-01:on 890906,35 of 237 Containment Isolation Valves Exceeded Administrative Allowable Leakage Rate When Tested.Caused by Normal Wear & Degradation During Specified Time Interval.Valves Cleaned & repaired.W/891221 Ltr NRC-89-0255, LER 89-031-00:on 891120,both Div II Emergency Equipment Cooling Water (EECW) & Emergency Equipment Svc Water Sys Pumps Tripped Immediately.Caused by Inadequacies in Stated Procedures.Procedures revised.W/891220 Ltr1989-12-20020 December 1989 LER 89-031-00:on 891120,both Div II Emergency Equipment Cooling Water (EECW) & Emergency Equipment Svc Water Sys Pumps Tripped Immediately.Caused by Inadequacies in Stated Procedures.Procedures revised.W/891220 Ltr NRC-89-0259, LER 89-017-01:on 890810,new Analysis of Feedwater Line Break Scenario Assumes Failure of Feedwater Startup Control Valve in Open Position.Review of Pipe Break Documentation Conducted.Updated FSAR Change to Be submitted.W/891215 Ltr1989-12-15015 December 1989 LER 89-017-01:on 890810,new Analysis of Feedwater Line Break Scenario Assumes Failure of Feedwater Startup Control Valve in Open Position.Review of Pipe Break Documentation Conducted.Updated FSAR Change to Be submitted.W/891215 Ltr NRC-89-0256, LER 89-022-01:on 890923 & 24,reactor Protection Sys Logic Actuations Occurred When Fuse C71A-F15B Blew.On 890928, Reactor Bldg HVAC Isolated.Caused by Personnel Error. Procedures Will Be revised.W/891215 Ltr1989-12-15015 December 1989 LER 89-022-01:on 890923 & 24,reactor Protection Sys Logic Actuations Occurred When Fuse C71A-F15B Blew.On 890928, Reactor Bldg HVAC Isolated.Caused by Personnel Error. Procedures Will Be revised.W/891215 Ltr NRC-89-0258, LER 89-025-00:on 891115,low Level 2 Signal Unintentionally Induced During Reactor Pressure Vessel Hydrostatic Pressure Test.Caused by Personnel Error.Personnel Counseled on Notifying & Coordinating Instrument lineups.W/891215 Ltr1989-12-15015 December 1989 LER 89-025-00:on 891115,low Level 2 Signal Unintentionally Induced During Reactor Pressure Vessel Hydrostatic Pressure Test.Caused by Personnel Error.Personnel Counseled on Notifying & Coordinating Instrument lineups.W/891215 Ltr NRC-89-0251, LER 89-019-01:on 890819,discovered That Div I Recirculation Fan Not Rotating Which Resulted in Decrease in Control Room Air Pressure.Caused by Lack of Lubrication in Bearings. Lubrication Program Improvements evaluated.W/891130 Ltr1989-11-30030 November 1989 LER 89-019-01:on 890819,discovered That Div I Recirculation Fan Not Rotating Which Resulted in Decrease in Control Room Air Pressure.Caused by Lack of Lubrication in Bearings. Lubrication Program Improvements evaluated.W/891130 Ltr NRC-89-0249, LER 89-029-00:on 891023,half Scram Signal Received When Power Was Lost on Reactor Protection Sys Bus B,Resulting in Several ESFs Actuation.Caused by Location of Breaker Operating Switch in High Traffic area.W/891122 Ltr1989-11-22022 November 1989 LER 89-029-00:on 891023,half Scram Signal Received When Power Was Lost on Reactor Protection Sys Bus B,Resulting in Several ESFs Actuation.Caused by Location of Breaker Operating Switch in High Traffic area.W/891122 Ltr NRC-89-0246, LER 89-028-00:on 891020,eight safety-related Valves Failed Set Pressure Test.Cause Under Review.All Valves Removed for Testing Being Refurbished,Cleaned,Retested & Recertified to Be within Plant Accepted tolerances.W/891120 Ltr1989-11-20020 November 1989 LER 89-028-00:on 891020,eight safety-related Valves Failed Set Pressure Test.Cause Under Review.All Valves Removed for Testing Being Refurbished,Cleaned,Retested & Recertified to Be within Plant Accepted tolerances.W/891120 Ltr NRC-89-0244, LER 89-024-00:on 891019,recognized That Secondary Containment Dampers Not Tested as Required by Tech Spec 3.6.5.2.Caused by Operations Personnel Error.Event Critique to Be Included in Required Reading program.W/891120 Ltr1989-11-20020 November 1989 LER 89-024-00:on 891019,recognized That Secondary Containment Dampers Not Tested as Required by Tech Spec 3.6.5.2.Caused by Operations Personnel Error.Event Critique to Be Included in Required Reading program.W/891120 Ltr NRC-89-0194, LER 89-027-00:on 891015,reactor Bldg Hvac,Control Ctr HVAC & Drywell Floor & Equipment Drain Sumps Isolated & Standby Gas Treatment Sys & Noninterrruptalbe Control Air Compressors Started.Caused by Personnel error.W/891114 Ltr1989-11-14014 November 1989 LER 89-027-00:on 891015,reactor Bldg Hvac,Control Ctr HVAC & Drywell Floor & Equipment Drain Sumps Isolated & Standby Gas Treatment Sys & Noninterrruptalbe Control Air Compressors Started.Caused by Personnel error.W/891114 Ltr NRC-89-0193, LER 89-026-00:on 891010,control Ctr HVAC Shifted to Recirculation Mode of Operaton Due to Short Circuit.Caused by Failure of Lamp Filament When Being Tightened.Fuse & Lamp Replaced & Sys Returned to Normal operation.W/891109 Ltr1989-11-0909 November 1989 LER 89-026-00:on 891010,control Ctr HVAC Shifted to Recirculation Mode of Operaton Due to Short Circuit.Caused by Failure of Lamp Filament When Being Tightened.Fuse & Lamp Replaced & Sys Returned to Normal operation.W/891109 Ltr NRC-89-0192, LER 87-045-01:on 870908,fuse Removed Which Deenergized Dc Control Power to Bus 72C & Resulted in Loss of Power Supply to Swing Bus & LPCI Loop Selection Valves.Caused by Design Error.Undervoltage Relay Added & Training held.W/891106 Ltr1989-11-0606 November 1989 LER 87-045-01:on 870908,fuse Removed Which Deenergized Dc Control Power to Bus 72C & Resulted in Loss of Power Supply to Swing Bus & LPCI Loop Selection Valves.Caused by Design Error.Undervoltage Relay Added & Training held.W/891106 Ltr NRC-89-0190, LER 89-023-00:on 890924,personnel Inadvertently Caused Trip of Essential Safety Sys Buses 64B & 64C.Caused by Failure of Personnel Involved to Review Applicable Prints Prior to Performing Test.Event Reviewed w/personnel.W/891024 Ltr1989-10-24024 October 1989 LER 89-023-00:on 890924,personnel Inadvertently Caused Trip of Essential Safety Sys Buses 64B & 64C.Caused by Failure of Personnel Involved to Review Applicable Prints Prior to Performing Test.Event Reviewed w/personnel.W/891024 Ltr NRC-89-0189, LER 89-022-00:on 890923 & 24,reactor Protection Sys Logic Actuations Occurred When Fuse Blew.On 890928,reactor Bldg HVAC Isolated When Jumper Lifted Per Incorrect Work Plan Instruction.Caused by Personnel error.W/891023 Ltr1989-10-23023 October 1989 LER 89-022-00:on 890923 & 24,reactor Protection Sys Logic Actuations Occurred When Fuse Blew.On 890928,reactor Bldg HVAC Isolated When Jumper Lifted Per Incorrect Work Plan Instruction.Caused by Personnel error.W/891023 Ltr NRC-89-0186, LER 89-016-01:on 890711,Div 1 of RHR Svc Water Sys Declared Inoperable Due to Low Nitrogen Pressure for Cooling Tower Fan Brake.Caused by Leak in One Hose.Leaking Hose Replaced & Nitrogen Pressure restored.W/891006 Ltr1989-10-0606 October 1989 LER 89-016-01:on 890711,Div 1 of RHR Svc Water Sys Declared Inoperable Due to Low Nitrogen Pressure for Cooling Tower Fan Brake.Caused by Leak in One Hose.Leaking Hose Replaced & Nitrogen Pressure restored.W/891006 Ltr NRC-89-0185, LER 89-021-00:on 890906,local Leak Rate Testing of Containment Isolation Valves & Penetrations Exceeded Tech Spec Limit.Caused by Excessive Containment Isolation Valve Leakage Due to Degradation of valve.W/891006 Ltr1989-10-0606 October 1989 LER 89-021-00:on 890906,local Leak Rate Testing of Containment Isolation Valves & Penetrations Exceeded Tech Spec Limit.Caused by Excessive Containment Isolation Valve Leakage Due to Degradation of valve.W/891006 Ltr 1994-04-25
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217N4381999-10-25025 October 1999 Safety Evaluation Supporting Amend 17 to License DPR-9 ML20217P3551999-10-22022 October 1999 LER 99-S01-00:on 990922,loaded 9mm Handgun Was Discovered on Truck Cargo Area of Vehicle Inside Protected Area.Caused by Inadequate Vehicle Search.Guidance in Procedures & Security Training to Address Multiple Vehicle Searches Was Provided NRC-99-0095, Monthly Operating Rept for Sept 1999 for Fermi 2.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Fermi 2.With NRC-99-0067, Monthly Operating Rept for Aug 1999 for Fermi 2.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Fermi 2.With NRC-99-0065, Monthly Operating Rept for July 1999 for Fermi 2.With1999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Fermi 2.With NRC-99-0088, Detroit Edison Co Enrico Fermi Atomic Power Plant,Unit 1 Annual Rept for Period 980701-990630. with1999-06-30030 June 1999 Detroit Edison Co Enrico Fermi Atomic Power Plant,Unit 1 Annual Rept for Period 980701-990630. with NRC-99-0064, Monthly Operating Rept for June 1999 for Fermi 2.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Fermi 2.With NRC-99-0062, Monthly Operating Rept for May 1999 for Fermi 2.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Fermi 2.With ML20206J9301999-05-10010 May 1999 SER Concluding That Util Adequately Addressed Actions Requested in GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Powered-Operated Gate Valves ML20206G5081999-05-0505 May 1999 Safety Evaluation Approving Request for Relief PR-8,Rev 2 on Basis That Licensee Committed to Meet All Related Requirements of ASME OM-6 Std & PR-12 on Basis That Proposed Alternative Will Provide Acceptable Level of Safety NRC-99-0022, Monthly Operating Rept for Apr 1999 for Fermi 2.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Fermi 2.With ML20205Q7141999-04-15015 April 1999 Safety Evaluation Supporting Amend 16 to License DPR-9 ML20205P9721999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Fermi 2 ML20204E0371999-03-17017 March 1999 Safety Evaluation Accepting Licensee Request for NRC Approval of Alternative Rv Weld Exam,Per Provisions of 10CFR50.55a(a)(3)(i) & 10CFR50.55a(g)(6)(ii)(A)(5) for Plant,Unit 2 for 40-month Period ML20204D0361999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Fermi 2 ML20198S3341999-01-0606 January 1999 Safety Evaluation Supporting Amend 15 to License DPR-9 NRC-99-0005, Monthly Operating Rept for Dec 1998 for Fermi 2.With1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Fermi 2.With ML20207B7491998-12-31031 December 1998 1998 Annual Operating Rept for Fermi 2 ML20205Q9621998-12-31031 December 1998 Revised Monthly Operating Rept for Dec 1998 for Fermi 2 NRC-99-0021, 1998 Annual Financial Rept for Detroit Edison Co. with1998-12-31031 December 1998 1998 Annual Financial Rept for Detroit Edison Co. with NRC-98-0153, Monthly Operating Rept for Nov 1998 for Fermi 2.With1998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Fermi 2.With NRC-98-0160, Monthly Operating Rept for Oct 1998 for Fermi 2.With1998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Fermi 2.With ML20154R2331998-10-21021 October 1998 Safety Evaluation Supporting Amend 13 to License DPR-9 ML20154L1031998-10-14014 October 1998 Safety Evaluation Accepting Licensee Response to NRC Bulletin 95-002, Unexpected Clogging of Residual Heat Removal Pump Strainer While Operating in Suppression Pool Cooling Mode NRC-98-0139, Monthly Operating Rept for Sept 1998 for Fermi,Unit 2.With1998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Fermi,Unit 2.With ML20154H8161998-09-30030 September 1998 Rev 0 to COLR Cycle 7 for Fermi 2 ML20153B8811998-09-18018 September 1998 Safety Evaluation Accepting Request for Relief from Certain Requirements of ASME Boiler & Pressure Vessel Code,Section Xi,For Plant,Unit 2 ML20151X0651998-09-11011 September 1998 Safety Evaluation Re Inservice Testing Program Relief Request VR-63 for Plant NRC-98-0111, Monthly Operating Rept for Aug 1998 for Fermi 2.With1998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Fermi 2.With ML20153B7921998-08-31031 August 1998 Rev 0 to Fermi 1 Sar ML20237E1171998-08-25025 August 1998 Safety Evaluation Accepting Licensee Relief Requests for First 10-yr Interval Inservice Insp Nondestructive Exam Program ML20236X8611998-08-0505 August 1998 SER Related to Revised Feedwater Nozzle Analysis to Facility Operating License NPF-43,Enrico Fermi Nuclear Power Plant, Unit 2 NRC-98-0109, Monthly Operating Rept for July 1998 for Fermi 21998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Fermi 2 ML20236K3261998-07-0101 July 1998 SER Accepting Licensee Response Related to Revised Feedwater Nozzle Analysis to License NPF-43 for Enrico Fermi Nuclear Power Plant,Unit 2 NRC-98-0097, Monthly Operating Rept for June 1998 for Fermi,Unit 21998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Fermi,Unit 2 NRC-98-0127, Annual Rept for Period 970701-9806301998-06-30030 June 1998 Annual Rept for Period 970701-980630 NRC-98-0079, Monthly Operating Rept for May 1998 for Fermi 21998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Fermi 2 NRC-98-0076, Monthly Operating Rept for Apr 1998 for Fermi 21998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Fermi 2 NRC-98-0072, Monthly Operating Rept for Mar 1998 for Fermi 21998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for Fermi 2 NRC-98-0050, Monthly Operating Rept for Feb 1998 for Fermi 21998-02-28028 February 1998 Monthly Operating Rept for Feb 1998 for Fermi 2 NRC-98-0019, Monthly Operating Rept for Jan 1998 for Fermi 21998-01-31031 January 1998 Monthly Operating Rept for Jan 1998 for Fermi 2 ML20198L4241998-01-0808 January 1998 Safety Evaluation Accepting Proposed Rev 2 to Relief Request VR-51 Under Fermi 2 Pump & Valve Inservice Testing Program Per 10CFR50.55a(f)(6)(i) for First 10-yr Interval NRC-98-0015, Monthly Operating Rept for Dec 1997 for Fermi 21997-12-31031 December 1997 Monthly Operating Rept for Dec 1997 for Fermi 2 ML20217N3821997-12-31031 December 1997 Annual Operating Rept for 970101-1231 NRC-98-0053, 1997 Annual Financial Rept for Detroit Edison Company1997-12-31031 December 1997 1997 Annual Financial Rept for Detroit Edison Company ML20205Q9601997-12-31031 December 1997 Revised Monthly Operating Rept for Dec 1997 for Fermi 2 NRC-97-0141, Deficiency Rept Re Malfunction of EDG Number 11 Automatic Voltage Regulator (AVR) Printed Circuit Board Rev B,Due to Failure of Operational Amplifier U8 Chip.Avr Board Rev B Was Sent Offsite to Independent Engineering Facility1997-12-23023 December 1997 Deficiency Rept Re Malfunction of EDG Number 11 Automatic Voltage Regulator (AVR) Printed Circuit Board Rev B,Due to Failure of Operational Amplifier U8 Chip.Avr Board Rev B Was Sent Offsite to Independent Engineering Facility ML20197A9921997-12-15015 December 1997 Rev 0 to Efp,Unit 1 Fermi 1 Sar NRC-97-0131, Monthly Operating Rept for Nov 1997 for Fermi 21997-11-30030 November 1997 Monthly Operating Rept for Nov 1997 for Fermi 2 ML20248H1151997-10-31031 October 1997 Rev 1 to Colr,Cycle 6 for Fermi 2 1999-09-30
[Table view] |
Text
- .-
.r 4
Wilham S. orser E!!.'i's."kons d 10CFRS0.73 _ 4
.:a -<
\ lY Edisori m=
6400 North Dixie Hi ghway Nucleat
-- o-"-
oece.ber 15. 1989 NRC-89-0259 l
1 U. S. Nuclear Regulatory Commission Attention: Document Control' Desk !
Washington, D.C. 20555 l
Reference:
(1) Fermi 2 NRC Docket No. 50-341 Facility Operating License No. NPF-43 (2) Transmittal of Licensee Event Report 89-017-00 dated September 11 1989.
NRC-89-0178
Subject:
Licensee Event Report _ _(LER) No. 89-017-01 Please-find enclosed LER No. 89-017-01, dated December ,
15, 1989 for a reportable event that occurred on August !
8 1989. This LER has been revised to reflect the finalized Feedwater and Main Steam Line Break analyses '
that-have been. approved by Detroit Edison. A copy of i
-this'LER is also beire sent to the Regional ;
-Administrator. USNRC wogion III.
If you have any questions, please contact Joseph Pendergast at (313) 586-1682.
Sincerely j N :
Enclosure:
NRC Forms- 366. 366A cc: A. B. Davis J. R. Eckert R. W. Defayette/W. L. Axelson W. G. Rogers J. F. Stang Wayne County EmerBency Management Division hDR912190057 891213 ;2Tgf;Q;g
'g ADOCK 03000341 f PDC /
r-'
f:
{
ii.' ,
y EfftC Poem JOS '
U.S. NUCLEMd E.EgULATOaY COMM10SION s.PM4VED OMS NO. 31504104 5x*'a58 8'*v" LICENSEE EVENT REPORT (LER) ,
F ACILITY NAME m DOCKET NUMSER (21 FAGE (3i Fermi.2' o i s' l o l o I o l3 l 4 l1 i lor l1 l 1 TITLEtes, llevised Feedwater Line Break Analysis ivlNT DATE 166 LER NUMSE R IG) Pr. PORT DATE 17) OTHER F ACILITIES INVOLVED (St YEAR 5 O i' MONTH DAY YEAR F ACILITV NAMES DOLKET NUMBERtSt f
MONT H DAY YEAR n N/A o1sl01010 1 l l
.0l8 1l0 8' 9 8l9 0 l ' 1l 7 0l 1 1l2 1l5 8] 9 N/A oisto r otoi i i TH18 REPORT IS SUSMITTED FURSUANT TO THE REQUIREMENTS OF 10 CFR {: ICheck one or more of the fonouring) 011 OPE R ATING "oot t 1 20 402m) 20 m., so.7:an2Hi.i n.7i mi PO ER 20 406(sH1H4) 60.341sH1) 50.73teH2Hvl 13.711e1 0 06 09i9 t 20 40.a>H Ha
.0x.n2> T .0 a .H2H.c
_ gHER;s,e<ggg
.g . .
20.406telH Helil 50.73teH2H4) 50.734eH2HouiHAl usa) 20 406laH1 Howl 60.73deH2 H4il 61.73tsH2HviiHIB) i 20 406teH1Het 50.73hH2flitil 60.73(sH2Hal
- LICENSEE CONT ACT FOR THIS LER Uti NAME TELEPHONE NUM6ER Joseph Pendergast, Licensing Engineer ^ " ' ' ' '
3 ! 11 3 Si8 161-11 1618i2
- COMPLETE ONE LINE FOR E ACH COMPONENT F AILURE DESCRISED IN THIS REPORT (13)
[ CAUSE SYSTEM COMPONENT h U~
o,"pp[3 CAUSE SYSTEM COMPONENT Mh C. 0RT AB E 9 qpp i s
u I I I !
1 I I I I I I I I i 1 L :
i I i ! l I I I j_, I I I I I I i SUPPLEMENTAL REPORT EXPECTEC H4) MONTH DAY YEAR SUBuissiON
l G vES ur e . more.o rnectrO svowssion Oa re) v ~ NO l l l A88TKACT ILuwt so 1400 spaces. le., soorommatory Muen sine'e-soece troewsreen f>nes! nel l
r 1
1 The analysis of the postulated f eedwater line break in the steam tunnel is described in Updated Final Saf e ty Analysis Report (U FS AR)- s e c tion 3. 6. 2. 2. 2. The UFSAR evaluation was completed in the early 1970's. Since documentation for the UFSAR conclusions l could not be retrieved, a new analysis was conducted. The I difference between the new analysis and the UFSAR is that the single failure of the fast closing feedwater pump discharge valves as described in the UFSAR could not be confirmed as the most conservative flood scenario. A failure in the open position of the feedwater start-up control valve was found to be the most conservative flood scenario. With this failure of the feedwater start-up control valve, the break will not be icolated until the tripping of the condensate and hcater feed pumps on low hotwell level. Therefore the consequences of the revised analysis are !
additional flooding beyond that previously analyzed for this event.
The review of the new feedwater and main steam line break analyses has been completed by Detroit Edison. A UFSAR change will be submitted with the next annual UFSAR update in March 1990.
, ,, _ . , , 4 - , , . , , - - - --m , -~ -~.. ~._. - -.-4 .c - . -
U GIIBC Pekm 8BBA U.S. NUCLEA3 EEIULATORY COMM80860N ;
j **" ai._c,._.UCENSEE EVENT-REPORT (LER) TEXT CONTINUATION "
~uenovio oMe Nossoas = '
Ce EXPIRES; B!3UN j l
FACILtTV feAmet (H . DOCKER NtA4th (2) LER NUMSER 14) th0E (3) ~
"aa -
"202. B "'#.D ;
o f510 lo lo 131411 81 9 0l1 l 7 -
0 11 0l2 OF 1 l.1 1xtin - a, <. .acr asuunn '
I q
s .-
y i Initial' Plant' Conditions:
Operational Condition: 1- (Power Operation)
Reactor Power 99.5 Percent Reactor Temperature: 535 degrees Fahrenheit Reactor Pressure: 1010 psig {
Description of' Event:
l
- The analysis of'the postulated feedwater (SJ) line break in the steam 1 tunnel is described in Updated Final Safety Analysis Report .
(U F S AR) section 3.'6.2.2.2. The UFSAR analysis was-completed-in the early 1970's. Documentatic, supporting the conclusions reached,hasEbeen searched for # could not be retrieved.
Therefore a new analysis w a s d w. to. support the UFSAR conclusions;--A difference was found between the new analysis : and-
' the'UFSAR. conclusions. For the feedwater line-break scenario..the single. failure assumed in the UFSAR.was failure of a-fast closure
. (8~ seconds) inboard feedwater pump discharge valve. The break scenario ends when the. slow (88 second) outboard feedwater' pump discharge valves close (ISV) and High Pressure Coolant: Injection
' ~
= (HPCI)l (BJ) , restores Reactor Pressure Vessel (RPV) level.
- The new. analysis of the feedwater line break se'enario assumes failure of the feedwater startup control valve (TV) in the o' pen L,
- positiou. This single failure-was relected to maximize flooding' in affected areas of the plant. . The f eedwa ter lin e break scenario with the single failure of the startup control valve is-therefore p more conservative. The new feedwater line break would not
; terminate until'the tripping of the condensate (SG) and heater feedipumps (P) on low hotwell level (SD). No operator action was assumed for the 8 1/2 minutes during which water flows through the E postulated pipe break. Supporting documentation is provided in Tables-I. II..and III. and the figures attached to this Licensee
[; Event Report (LER). >
l-Cause o f _Ey.en t :
A review of pipe break documentation supporting the original FSAR and' existing UFSAR analyses was conducted. Documentation for all pipe break scenarios exists with the exception of the main steam (SB) and feedwater line breaks in the steam tunnel. The UFSAR 1
[ NRC FORM 360A , *U.S. CPos 1968 5J0489 000 70 ,
' C 831 E ' i . _ , . . - - . . , _ . , ,. . . _ . . . . _
T' i
~
*~
0 l
NRC7 elm 308A m_ e U.S NUCLEAR KEEULATOIY COMMISSION I
" c '
LICENSEE EVENT REPORT (LER) TEXT CONTINUATION AreaOvEo ous NO. siso.oio.
EXPIRES: 8?31/88
#ACILITV NAME tu DOCKEY NUMBER (2) LER NUMBER (S) PAGE (3)
,E .
w =.v Fermi 2 I o my w ., . , 4 o l5 Io Io l0131411 3l9 -
0l1l 7 -
0l1 0l3 OF 1l1 mac i-- =w nn conclusions resulted from an analysis completed in the early '
1970's. Documentation supporting these existing UFSAR. conclusions could not be retrieved, therefore a new UFSAR analysis was developed for the main steam and f e edwa t er line br eaks. The UFSAR analysis for feedwater line break was found.to be ,
non-conservative.
Analysis of-Eventi ,
The new analysis for a feedwater line break in the Steam Tunnel has different. consequences. The Steam Tunnel (NM) and Auxiliary Building (NF) first floor, where the Reactor Building Closed Cooling Water (RBCCW) (CC) heat exchangers are located, reach peak flood depths of 53.7" and'45.8". respectively. The steam Tunnel and RBCCW hec: exchanger room flood elevations then begin to decrease due to flow through the Steam Tunnel floor and equipment drains (DRN). The water in the RBCCW heat exchanger room drains to the southeast corner room of the Auxiliary Building.
The northeast corner room peak flood depth of 80.9" is reached due to.. floor drain-flow into the sump. Equipment drain flow causes flooding:in.the southeast corner room to a depth of 169".
Approximately 10 hours after the lin e break s, water would begin to spill into the torus and HPC1 rooms. The Torus room peak flood depth reaches 14.8". The HPCI room would reach a peak flood depth of 78.8". With the RBCCW heat exchanger floor drains open, the evaluation concludes that the' control air compressor room could flood. However, when preliminary results of the analysis were received in 1987, to mitigate possible flooding in this room plugs were promptly installed in the RBCCW room floor drains.
Plugging of the floor drains eliminates flooding in the control air compressor room and reduces northeast corner room flooding.
However, it results in substantially more flooding in the sou*heast corner room. More flooding of the southeast corner room will have no impact on safe shutdown of the plant since Division 2 of Core Spray is assumed to be lost even without plugging the floor drains. The original UFSAR analysis assumed that the drainage system is sufficient to remove the flood water from the Reactor / Auxiliary Buildings. As a result, the sub-basement corner rooms. air compressor room, and Torus room would not have flooded.
Reanalysis of the main steam line break in the Steam Tunnel shows that the break' flow and flow path are similar to those described in UFSAR 3.6.2.2.1. Flooding levels due to the main steam line break are bounded by the feedwater line break. The resultant peak.
temperature, pressure and humidity are shown in Table III.
N%C FORM 34ea *U.s. cro,1960 *>20 $80 000 :0 4343).
i esac Pem assa U.s NUCLt13 f.tiULATORY COMMWBION UCENSEE EVENT REPORT (LER) TEXT CONTINUATION AreHovto oMe No sino-oio.
EXPIRES: B/31/08 P ACILITY NAA.E (Il DOCKET NUMDEM (23 LtR NUMetR lEl Pact (3)
"^a "WOu^' :'#.?:
Fermi 2 15 l l l 13 l 41 1 81 9 01117,- 01 1 014 OF jp i
. Texta - . ~ - ,,c, .i. u m, The safe shutdown path considers systems necessary to scram the reactor, depressurize the reactor, and to establish and maintain the core cooling utilizing the Residual Heat Removal (RHR) (BO) system. For feedwater line breaks. the availability of offsite power maximizes the consequential effects of flooding. Therefore.
offsite power was assumed to be available. If offsite power is not available, the Condensate and Heater Feed pumps will trip, thus ending the break scenario sooner. No water will be lost from the reactor since the feedwater check valves are designed to close immediately.
1An evaluation of the effects of a feedwater and main steam line break has been completed, with the exception of Equipment Qualification Evaluation and Hydrostatic Loads on the plant structures. These evaluations will be completed and reflected in the March 1990 UFSAR Update. The feedwater evaluation shows the first floor Auxiliary Building containing the RBCCW. the northeast corner room containing Division 1 Core Spray (BM) and Reactor Core Isolation Cooling (RCIC) (BN). the southeast corner room containing Division 2 Core Spray. HPCI and the Torus room would flood to the elevations shown in Table II. Under these conditions the plant can achieve safe shutdown by using the Automatic Depressurization System (ADS) (BF) and both divisions of RHR.
Also, since the HPCI room is not predicted to flood until ten hours after the line breaks. HPCI is available for the first ten hours and ADS and RHR are available throughout the event. HPCI' will restore water level to compensate the loss of feedwater flow. The vessel can be manually depressurized by using the Main Steam Safety Relief Valves. After pressure reduction, the operator places the RHR System (Division 1 or Division 2) in the Low Pressure Coolant Injection (BO) mode. The Residual Heat Removal Service Water (RHRSW) (BI) System is used as the heat sink in the RHR cooling mode.
The effects of a main steam line break are confined to the Steam Tunnel, first floor Auxiliary Building and the Turbine Building.
The Steam Tunnel temperature is boun41ed by the existing temperature in the UFSAR. The highe r Steam Tunnel pressure has been evaluated and found to be acceptable. The higher temperature and pressure in the first floor Auxiliary Building containing RBCCW has no impact to safe shutdown-since no safety related equipment is located in this area.
4
. NRC FORU 366A *v.s. CFO 1988 SN-W M0 70 69 832
.- - - .. - _-. ~ .. O_n
sesH: Form age.) u S. NUCttA2 ILEOULATO3Y COMMISSION j UCENSEE EVENT REPORT (LER) TEXT CONTINUATION arenovio ove no sisoaio4 ;
- EXPIRES. 8'31/08 FACleliv NAmt til DOCKET NUMSE R (2) LER NUMBER lel PAGE131 naa $40 .W. $rJ3:
Fermi 2 0 l5 l0 l0 l013 l 4l1 8l 9 -
011l7 -
011 01 5 0F 111 TEKt I:more spen a requeod, un ennonel NRC form JesA M (1n .
i I In UFSAR Section 3.4.4.4 Internal Flood Protection, under site l flooding conditions both divisions of Core Spray, and HPCI, RCIC, ;
the Torus room and control air rooms are flooded. With the loss i of Divisions 1 and 2 of Core Spray. RCIC and HPCI, safe shutdown capability of the reactor is not affected. ADS and both divisions of RHR are still available for safe shutdown of the plant. I Therefore the consequences of the feedwater line break are bounded l by this analysis. !
, Corrective Actions:
When the UFSAR feedwater/ main steam line break analyses I documentation was determined to be missing, a further review of other pipe break analysis documentation was conducted for other systems. This review concluded that appropriate documentation is available for all other postulated breaks. i i
The feedwater and main steam line break analyses have been I reviewed and approved by Detroit Edison. A UFSAR change will be submitted with the next annual UFSAR update in March 1990. l Previous Similar Events:
This is the first LER describing an inaccu' rate UFSAR analysis. ;
1 1
\
l I
I l
1 NRC FOZM 386A *U.S. GPos 1986 520 589,00010 E43)
_ . . ._ .__ _ . - ._ ~ _ _ ._
GiftC PeMn 3BSA U t. NUCLEAJR 5.82VLAT03Y COhlMISSION e .
LICENSEE EVENT REPORT (LER) TEXT CONTINUATION APPxOvtp oMe =0. 3iS0-OiOA L EXPIRis: t/31/00 f
FACILITY NA488 Ill DOCKET NUMSLR 12) LER NUMega (t) PAGE (31 vtAR '. AL ..me my 68 $a Fermi 2 i l, TEXT (# more ausse a meuwod ses sewsonst NAC form JuBA'st (17)
O l5 l 0 l 0 l 0131411, 319 -
01117 -
0l1 ol6 OF 1l1
.j i
l' l
-}
q"
]
sect 1 0F 2 l APre0mlesA f t 148L8 I PL0m RA18- Ev5N1 'i f lest t5EC) ( tas ) ')
UF5Au Rivl5ED uF54R Rfvi5ED uF545 WYvl5ED J
$k 0 0 0 Datan '
entan
- 0+ 0+ 30.000 43.000 Fttomaten FL0s atenAIN vnt 5Aut l e Fisc wAfta Flow JuuP5 TO 43.000' j G8u.
o AFP talPPto Oss Low SUCTION Pets 5 pat. <
?- 43.000 l e alACTon watta LawtL 3 talp INiflAfts A SCham TRIP.
o scram talP INlt!Afts CLD5unt OF-ALL Fttomatta Puur O!5CHAAGE VALvts CLD580 AFf th 30 SECOsso otLAv e POST SCRae Fit 0 EATER CONTA0L '
AUTouATICALLv Put INTO Stevitt.
Il 30.000 piattpa wAtta Ltytt 3 Talp A. SChau D. #tACYDA FRE0 matt A Puesp OISCMa#GE v&LVt5 START CLO51NG.
14 43.000 e 5ftam fuMNik LtAs Otittil0M it : 23.000 SV5ftes itaspeaAtuat EACito ONE PAst CLotunt saft IS SECI.
Fttomatta puesp Ol5CHARGt v&Lvt CLOSES. OTHER CONSIDERED TO HAvt Faltto 10 CLO5tD.
20 23.000' patssunt attler 000a5 OPEN.
waf f e PLOO05 F IR57 FLOOR OF AvalLIARY Sul0 LING. s 22 43.000 AFTER AN 8.0 SECONO INSTRulBENT CHANNEL RESPONSE TIM e53v CLO5uRE 15 INiilAft0.
25 43.000 vtSSEL matta Ltytt IL28 talp INITIAft5 HPCI AND RCIC OPERAfl0N.
aCIC 15 se01 Tenth Catof t F0a IN THE SCENARIO. SINCE If IS se01 s!NvlaoselltNT ALLY OUALIFito AND SECAust THE Nt Consete 000ss IS AFFECTED SV FLOOOlseG.
32 .
43.000 AFita A 50 SECOMO assiv CLD5unt flut THE eslav'S Ant FULLv CLO5ED.
~ 6t' 43.000 AFita TMt HPCI INiflATION StGNAL.
**PCI atACNts RAf t0 Flow WITHIN 25 54 CON 05.
57 21.000 Artta AN 4 stCOND DELAV (IN A00l*
flose 10 TME 30 SECOMO POST SCRAes -
DELAV) AND A 12 SECOseo CLO5unt flNE. FAST CLO5unt VALyts v12=2531 ANO vl2 2533 Amt CLOSED AND ALL Flow 15 Fontto 1Hn0uGM THE staat up LEvtk C0esTROL vaLvt.
F I
r i
- NRC FORM 366A sU.$. CP0s 1969-520-589-@ 070 i t0 83)
, , , _ . . . . . . ~ . . . . .m . . . . _ . . . . . _ _ . . ._._,_m . . . . . _ _ . __-
b OfftC Pete ageA U.S. NUCLEAR F.tOULAT03Y commits 10N <
LICENSEE EVENT REPORTlLER) TEXT CONTINUATION maovio ous No. aiso-oios
.e EXPIRES: 8/31/86 -
PAC #LITY NAmt til . DOCKei NUnetR (2) ggggg .
"aa -
" O u ^' dife?;
Fermi 2~ !
0151010 I n 131411 819 -
01117 -
0l1 017 OF gl j TEXT W awe alpas a soeweer, use eawsonst Nec perm mw (17 ,
p 9Mt i SP 3 ,
ADee0sleaft' DLes toit twtm?
tant (Sect tapes) ursas etvi sts waan uuvunum w aam mavamme
. 64 30.000 TMt Itaste S PeteWatte teatte Levsk toutAOL vatwet att CLO&te aus Ptem TeGOWGM TME esafte DeaIN P W e8 88 888Latte PAW Tee getae.
38 0.000- 840s CLOSuet sett (et SGC).
Pettusafte pump DISCsenau ?
WALwtS CLOSS.
TME erp SLOW CASSWG DISteeneet 4t? 30.000 waLwel Set PuLLV CLeste (wit-3603 VII*tteel. TMis test 80 arFSCY 918 TME estes PLes gut S esOfte 18 pe0VIOS ASSpacett Teenf Pattutt OP tee PAST CLolute waLwt$ WOULD seOf M AS Sewtet AS PetLust SP 1ee START Up CentAOL watwt.
CLOSuet er feeSt waLwel attulets 80 SSConDS PLUS A 30 SSCSIS Sebay tSe 0.000 - StaCf00 teatte LtvtL 3 Talp
- a. ACIC AseO espCI Staat S. WS3wl Staat CLolleet .?
igg 3.000 statt0A Petematte pues Coast TO A ST0p.
374 30.000 ' stattet matte L0wSL IS DOS?tett tv
- tepC8. testCM eIOWLS State fee Steet CoseTROL wakwel seat IT sIST SStu 45&W89 TO Palk.
340 0 staCTee esatte LawtL AGC0wtel. 3' Patomafte evpASS L3 set Steefue C0 eve 84 waLws CLOS 48, Cemeentatt AsID esatte Pete pWes 44? 30.000 Talp 011 Leu seDTutLL Ltwth ase puispat PLSW ll ASSullte TO BBCetAS$
TO Este.
Test unite lesweestent (88376 GAL.)
D0useltetade er toe af t'S $$ Atlam .
TO M StSteeneste paens Tee these Owte A 4 etanuTS 98A400 SV Geowliv Pteu.
909 e fee esatte lesvteIT0Av 301 fee PIP 8086 IS TOTALLY DISCoeneetD.
10t aL ' 43.333 106.734 Ptem (GAL) h n
NMC FORM 3ega 'U.S. GPO: 19 6 8
" C43,
-l 80RC Peren ageA U.S. NUCLt#.2 f.EIULATORY ConsulegeON 4
LICENSEE EVENT REPORT (LER) TEXT C3NTINUAT10N . unovto ous no sico-oioo EXPlRES 4?31/N f ACILITV feAsef of DOCKET NunsetR us LER NUMeER (6) PA06 (31 vi.a a m ,rt' -tre.y:
Fermi 2:
0 5 0 0 01314 l 1 819 -
0l117 -
0l1 0l8 O F. 1 l1 l rext er ., ,w. -unc F mswnn TABLE II s ,
FEEDWATER LINE BREAK IN STEAM TUNNEL ;
. FLOOD HEIGHT WITH RBCCW- '
HEAT: EXCHANGER ROOM FLOOR l -DRAINS PLUGGED -
\
\
' Affacted Flood Area Flood 4 Elevation
- Depth
- Steam Tunnel 587.988 u -- 'RBCCW Room 53.7" 507.318 45.8" I
Control Air Compressor Room 551.00'**
NE Corner Room 0.0"**
546.74' 80.9" l
'SE Corner Room 554.088 1 Torus Room 169" l HPCI' Room.
541.238 14.8" l 546.57' 78.8" l l
j;
- This table-lists maximum flood heights for each area, maximum l
height do not occur simultaneously for all rooms.
l This room is unaffected by flooding'but is listed because of l- its significance to the evaluations. -
L i
l-k f
l NAC FOMM 366A *d.5. CFOs L 968 4 2 0 - 3M 9, W010
[ [ g 63)
u h4 . < !. i -
a p - ;
i esRC Pom asea '
U.S. NUCLEA3 REEutATD3Y CoMuteSloN
]
'"* ' ? . UCENSEE EVF,NT REPORT (LER) TEXT CONTINUATION' - snaovio ove mo. siso-oiw Li j txants; eraves 'j G rAcitety =Aus m _ ooenasuvueen m tra muusen <si raos m l n"" "8 L";. A';;.?: 1 Fermt 2 i iexi tu o,.we m a w. m m unc ra asu v <m 0 1510101013 141 1 81 9 0l1 l 7 -
01 1 019 OF 1l1 ]
\
a l
TABLE III MAIN STEAM LINE BREAK IN STEAM TUNNEL J i
-l l I l i TEMPERATURE _
l PRESSURE j,___ HUMIDITY _ l REVISED'J UFSAR 1 REVISED l__UFSAR____j_ R_EVISED 1_UFSAR__l~
J, Steam _ Tunnel 1_227, F 1_26_6_ F l'4.9 PSIG__1 3.4_PSIG l_ 100%
J,_100% l l1st Aux. Bldgl l l 1 l l l l l(RBCCW Roomlgj,_215__F__J_175 F l 0.8 PSIG l 2 25 PSIG J_ 100% J,100% l
~
,!'l 1
I i
(
I
( '.
lf
)
,. . NXC FOI.M Desa *U,s. GPos 1988-520-S89s00070 l' GS3)
' lr GIRC Penn EOSA - U.S. NUCLEAR KEEULt. TORY COMMtOSiOes
' ' ' ' . , * '.-J LICENSEE EVENT REPORT (LER) TEXT CONTINUATION '
maovio oMe no. 3 u-oim 7
EXPmES. $/31/88I >
PACILify 8sAset (1) . .. DOCKETprue4BER Gl Lf R NUMSf A 161 PAGE(3) .
n'a -
"Rtt;;'. %*.?: -
. Fermi 2 0F 1 l .1 015 0 l o'l o l 314 l 1 819 -
0 l 1l 7 -
0l1 ' 1l 0 rexr a- a m m me p.uuw nn
'. MedN J '
', JANN/5/fCAlWM4/M/3' , ,
.. MihM9fff $4f2/.sF .. MH'd I'
h _ h*
" %.sa.,
1 43e97 d# '
x fy
--l l 7 i s '
p af MortVepeinf.
ggggg, ,
1 M4 t ,
enWdff/2=2 U3) . ;
246W d'denne VKfMt 2904) ,
q, 3 ~~
.apws4
_ma 2asaw MACM Ai910.
mas - nxos ,
d .
I i P d
1 )(
, ~4 s
~
y gQf f :
4 ed f 66
'r
. seuMr>L t - -
a emmuum een emum emum - enano j
g , e
- > l w m -- .
I I nw,, mra.- I v AeWA>- M" L __tsWKdtMMry7 _ le 5
5 ttRC FORM 366A *U.5, Cro 1968-420-569-00010 ,
i ' 19 831
.-~ -__ _____ ____-._ ____.,
- . . . - _ . . . . - . .- . . . . . . . . ~ - - . - _ ~ . ..~.....a.~.., ,...,,
,b ]
- RC Pere 300A U S. NUCLEAR RESULATORY COnensisstow
-(
#'f *
- 3 LICENSEE EVENT REPORT (LERl' TEXT CONTINUATION :- urnoveo ous no. iso +e . "i exmts+3um !
*4ceury =A., in DOCKl1 NUGABER (2)
LER NUh48ER ill PA04 (3)
. .i: -
"*" "O!, ! e-ny,fy;
' Yermt 2 01510101013141 1 8l 9 -
o l1 l 7 _
o; 3 3; 3 op 3,y _
Ten * = . , e.,, %y ,,,,,, ..,, ,,,
FIGURE 2 ;
FEEDWATER UNE BREAK >
NTHE STEAM TUNNEL S
" FLOODING MODEL :
l
[
STEAM ,
ROOM 106 g i
petsssuRE RELEF DOOR .
y V ,
BREAKPLUD eq } m' ans d _ a
.9 ' y ,jAppg], ,
i -.
I' , d' FD y/ U
-p. ,
AUXLIARY SULDNQ SW BASW i: $E I
l TORUS ROOM
' g gy con ,-
- I-.
etaae%d; a .
L 'i*EJ _g,[
L t!!
L _
j l ..
t-I1 NOTES- l t u '
g, $ 9tDISATES PbOW 9m40Tleet a
[..
,, . e s. ..as o
s, g setcAttl 9fATSA SURPA08 f'
}2 d, pp ,bOOtt DAASI 30 - BOUrutNT SaAst A tat % uoT 5* W l
l
,~.
NXC FORM 386A - 'U.S. GPO: 1988 520 589,00070
> C *,31 -
,-..~ ,}}