ND-19-1109, ITAAC Closure Notification on Completion of ITAAC 2.3.05.03d.i (Index Number 351)

From kanterella
(Redirected from ML19268B669)
Jump to navigation Jump to search
ITAAC Closure Notification on Completion of ITAAC 2.3.05.03d.i (Index Number 351)
ML19268B669
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 09/24/2019
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of New Reactors
References
ND-19-1109
Download: ML19268B669 (6)


Text

,1 l. I I MichaeiJ. Yox 7825 River Road

^OUtnCrn INUClBdr Regulatory Affairs Director Waynesboro, GA 30830 Vogtle 3 & 4 706-848-6459 tel SEP 2 <1 2019 Docket No.: 52-025 ND-19-1109 10CFR 52.99(c)(1)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 ITAAC Closure Notification on Completion of ITAAC 2.3.05.03d.i [Index Number 3511 Ladies and Gentlemen:

In accordance with 10 CFR 52.99(c)(1), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRC)of the completion of Vogtle Electric Generating Plant(VEGP) Unit 3 Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 2.3.05.03d.i [Index Number 351]for verifying the Material Handling System Maintenance Hatch Hoist is single failure proof.

The closure process for this ITAAC is based on the guidance described in NEI 08-01, "Industry Guideline for the ITAAC Closure Process under 10 CFR Part 52," which was endorsed by the NRC in Regulatory Guide 1.215.

This letter contains no new NRC regulatory commitments. Southern Nuclear Operating Company (SNC) requests NRC staff confirmation of this determination and publication of the required notice in the Federal Register per 10 CFR 52.99.

/

If there are any questions, please contact Tom Petrak at 706-848-1575.

Respectfully submitted, Michael J. Yox Regulatory Affairs Direofor Vogtle 3 & 4

Enclosure:

Vogtle Electric Generating Plant(VEGP) Unit 3 Completion of ITAAC 2.3.05.03d.i [Index Number 351]

MJY/GCW/sfr

U.S. Nuclear Regulatory Commission ND-19-1109 Page 2 of 3 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. Peter P. Sena III (w/o enclosures)

Mr. D. L. McKinney (w/o enclosures)

Mr. M. D. Meier(w/o enclosures)

Mr. D. H. Jones(w/o enclosures)

Mr. G. Chick Mr. M. Page Mr. M. J. Vox Mr. A. S. Parton Ms. K. A. Roberts Mr. T. G. Petrak Mr. C. T. Defnall Mr. C. E. Morrow Mr. J. L. Hughes Ms. K. M. Stacy Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:

Nuclear Regulatory Commission Mr. W.Jones(w/o enclosures)

Mr. F. D. Brown Mr. C. P. Patel Mr. G. J. Khouri Ms. S. E. Temple Mr. N. D. Karlovich Mr. A. Lerch Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. J. Gaslevic Mr. V. Hall Mr. G. Armstrong Ms. T. Lamb Mr. M. Webb Mr. T. Fredette Mr. C. Weber Mr. S. Smith Ooiethorpe Power Corooration Mr. R. B. Brinkman Mr. E. Rasmussen

U.S. Nuclear Regulatory Commission ND-19-1109 Page 3 of 3 Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. 8. M. Jackson Dalton Utilities Mr. T. Bundros Westinqhouse Electric Comoanv. LLC Dr. L. Oriani (w/o enclosures)

Mr. D. 0. Durham (w/o enclosures)

Mr. M. M. Corletti Ms. L. G. Iller Mr. Z. 8. Harper Mr. J. L. Coward Other Mr. J. E. Hesler, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., CDS Associates, Inc.

Mr. 8. Roetger, Georgia Public Service Commission Ms. 8. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Baich Bingham

U.S. Nuclear Regulatory Commission ND-19-1109 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-19-1109 Enclosure Vogtle Electric Generating Plant(VEGP)Unit 3 Compietion of iTAAC 2.3.05.03d.i [Index Number 351]

U.S. Nuclear Regulatory Commission ND-19-1109 Enclosure Page 2 of 3 ITAAC Statement Design Commitment S.b) The maintenance hatch hoist is single failure proof.

inspections.Tests. Analysis

1) Validation of double design factors is provided for hooks where used as load bearing components. N^iidation of redundant factors is provided for load bearing components such as;
  • Hoisting ropes
  • Sheaves
  • Equalizer assembly
  • Holding brakes Acceptance Criteria i) A report exists and concludes that the maintenance hatch hoist is single failure proof. A certificate of conformance from the vendor exists and concludes that the maintenance hatch hoist is single failure proof.

ITAAC Determination Basis Multiple ITAAC are performed to demonstrate that the Maintenance Hatch Hoist is single failure proof. The subject ITAAC requires that validation of double design factors is provided for hooks where used as load bearing components, and that validation of redundant factors is provided for load bearing components such as hoisting ropes, sheaves, equalizer assembly and holding brakes.

The maintenance hatch hoist is a single failure proof design which conforms to the guidelines of NUREG-0554 "Single-Failure-Proof Cranes for Nuclear Power Plants"(Reference 1),

supplemented by American Society of Mechanical Engineers(ASME) NOG-1-1998,"Rules for Construction of Overhead and Gantry Cranes(Top Running Bridge, Multiple Girder)"

(Reference 2). Single failure proof design is described in NUREG-0554 as "a single failure will not result in the loss of the capability of the system to safely retain the load." The requirements to follow NUREG-0554, supplemented by ASME NOG-1-1998,for the design of the maintenance hatch hoist were imposed in the design specification (Reference 3).

The maintenance hatch hoist single failure proof report(Reference 4)exists and concluded that the maintenance hatch hoist is single failure proof. Additionally, a certificate of conformance (Reference 5)from the maintenance hatch hoist vendor (manufacturer) exists and concluded that the maintenance hatch hoist is single failure proof.

U.S. Nuclear Regulatory Commission ND-19-1109 Enclosure Page 3 of 3 ITAAC Finding Review In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company(SNC) performed a review of all ITAAC findings pertaining to the subject ITAAC and associated corrective actions. This review found that there are no relevant ITAAC findings associated with this ITAAC. The ITAAC completion review is documented in the ITAAC Completion Package for ITAAC 2.3.05.03d.i (Reference 6)and is available for NRC review.

ITAAC Completion Statement Based on the above information, SNC hereby notifies the NRC that ITAAC 2.3.05.03d.i was performed for VEGP Unit 3 and that the prescribed acceptance criteria were met.

Systems, structures, and components verified as part of this ITAAC are being maintained in their as-designed, ITAAC compliant condition in accordance with approved plant programs and procedures.

References(available for NRC inspection^

1. NUREG-0554,"Single-Failure-Proof Cranes for Nuclear Power Plants", May 1979
2. ASME NOG-1-1998,"Rules for Construction of Overhead and Gantry Cranes(Top Running Bridge, Multiple Girder)"
3. APP-MH40-Z0-101, Rev. 4,"Design Specification for API000 Equipment Hatch Hoist and Maintenance Hatch Hoist for: Mechanical Handling System (MHS)"
4. WEC_SV0_000012,"Vogtle Unit 3 MH40 Maintenance Hatch Hoist Supporting References to Topical Report EDR-I", September 23, 2019
5. SV3-MH40-VQQ-003, Rev. 0,"Quality Release and C of C for SV3 Maintenance Hatch Hoist"
6. 2.3.05.03d.i-U3-CP-Rev 0, ITAAC Completion Package