Category:Letter type:NL
MONTHYEARNL-21-034, Notification of Expected Date of Transfer of Ownership of Nuclear Units to Holtec Indian Point 2, LLC and Holtec Indian Point 3, LLC; and Notification of Receipt of All Required Regulatory Approvals2021-05-26026 May 2021 Notification of Expected Date of Transfer of Ownership of Nuclear Units to Holtec Indian Point 2, LLC and Holtec Indian Point 3, LLC; and Notification of Receipt of All Required Regulatory Approvals NL-21-039, Response to Request for Additional Information - License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary2021-05-20020 May 2021 Response to Request for Additional Information - License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary NL-21-033, Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel2021-05-11011 May 2021 Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel NL-21-032, Termination of Emergency Response Data System Feed to the U.S. Nuclear Regulatory Commission at Indian Point Energy Center2021-05-11011 May 2021 Termination of Emergency Response Data System Feed to the U.S. Nuclear Regulatory Commission at Indian Point Energy Center NL-21-005, Cancellation of Commitments Related to Beyond-Design-Basis External Events Seismic and Flooding Actions2021-05-11011 May 2021 Cancellation of Commitments Related to Beyond-Design-Basis External Events Seismic and Flooding Actions NL-21-030, Submittal of 2020 Annual Radiological Environmental Operating Report2021-05-0606 May 2021 Submittal of 2020 Annual Radiological Environmental Operating Report NL-21-027, Registration of Spent Fuel Cask Use2021-04-20020 April 2021 Registration of Spent Fuel Cask Use NL-21-021, Registration of Spent Fuel Cask Use2021-04-19019 April 2021 Registration of Spent Fuel Cask Use NL-21-017, Pre-Notice of Disbursement from Decommissioning Trusts2021-04-0808 April 2021 Pre-Notice of Disbursement from Decommissioning Trusts NL-21-010, Submittal of 2020 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report2021-02-17017 February 2021 Submittal of 2020 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report NL-21-006, Relief Request IP3-ISI-RR-16, Proposed Alternative to American Society of Mechanical Engineers Code Case N-513-4 Inspection Requirement2021-02-10010 February 2021 Relief Request IP3-ISI-RR-16, Proposed Alternative to American Society of Mechanical Engineers Code Case N-513-4 Inspection Requirement NL-21-014, Response to 2nd Round Request for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2021-01-26026 January 2021 Response to 2nd Round Request for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device NL-20-082, Notice of Planned Transfer of Decommissioning Funds2020-12-14014 December 2020 Notice of Planned Transfer of Decommissioning Funds NL-20-081, Pre-Notice of Disbursement from Decommissioning Trusts2020-12-0909 December 2020 Pre-Notice of Disbursement from Decommissioning Trusts NL-20-080, Report in Accordance with 10 CFR 71.95(a) for Failure to Comply with Certificate of Compliance No. 71-93212020-11-19019 November 2020 Report in Accordance with 10 CFR 71.95(a) for Failure to Comply with Certificate of Compliance No. 71-9321 NL-20-079, (IP2 and IP3) - Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic2020-11-12012 November 2020 (IP2 and IP3) - Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic NL-20-077, Submittal of Quality Assurance Program Manual Revision 22020-11-0909 November 2020 Submittal of Quality Assurance Program Manual Revision 2 NL-20-078, Response to Requests for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2020-11-0909 November 2020 Response to Requests for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device NL-20-076, Revision of Commitment Related to Nuclear Reactor Safeguards Interim Compensatory Measure - Section B.5.b Issue Regarding Spent Fuel Dispersal2020-11-0202 November 2020 Revision of Commitment Related to Nuclear Reactor Safeguards Interim Compensatory Measure - Section B.5.b Issue Regarding Spent Fuel Dispersal NL-20-069, One-time Scheduler Exemption Request from 10 CFR 50, Appendix E Biennial Emergency Preparedness Exercise Requirements Due to COVID-19 Public Health Emergency2020-10-0808 October 2020 One-time Scheduler Exemption Request from 10 CFR 50, Appendix E Biennial Emergency Preparedness Exercise Requirements Due to COVID-19 Public Health Emergency NL-20-070, Response to Requests for Additional Information, License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2020-10-0202 October 2020 Response to Requests for Additional Information, License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device NL-20-067, Redacted Version of Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline2020-09-16016 September 2020 Redacted Version of Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline NL-20-064, 10 CFR 50.59(d)(2) Summary Report of Changes, Tests and Experiments2020-09-0101 September 2020 10 CFR 50.59(d)(2) Summary Report of Changes, Tests and Experiments NL-20-060, Status of Remaining Actions for Generic Letter 2004-022020-08-11011 August 2020 Status of Remaining Actions for Generic Letter 2004-02 NL-20-057, Cancellation of Commitment Related to Large Break LOCA Reanalysis2020-07-30030 July 2020 Cancellation of Commitment Related to Large Break LOCA Reanalysis NL-20-0851, 30-Day 10 CFR 21 Notification - Continuously Energized Eaton D26 Relays Could Fail to Deenergize Because of an Organic C3 Insulating Material2020-07-22022 July 2020 30-Day 10 CFR 21 Notification - Continuously Energized Eaton D26 Relays Could Fail to Deenergize Because of an Organic C3 Insulating Material NL-20-051, Submittal of Quality Assurance Program Manual, Revision 1 for the Indian Point Energy Center2020-07-0707 July 2020 Submittal of Quality Assurance Program Manual, Revision 1 for the Indian Point Energy Center NL-20-052, Unsatisfactory 10 CFR 26 Fitness-For-Duty Blind Performance Testing Results2020-07-0707 July 2020 Unsatisfactory 10 CFR 26 Fitness-For-Duty Blind Performance Testing Results NL-20-012, Application to Revise Provisional Operating License and Technical Specifications2020-06-30030 June 2020 Application to Revise Provisional Operating License and Technical Specifications NL-20-050, Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline2020-06-24024 June 2020 Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline NL-20-041, Registration of Unit 3 Spent Fuel Cask Use2020-05-13013 May 2020 Registration of Unit 3 Spent Fuel Cask Use NL-20-042, Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel2020-05-12012 May 2020 Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel NL-20-033, Technical Specifications Proposed Change - Permanently Defueled Technical Specifications2020-04-28028 April 2020 Technical Specifications Proposed Change - Permanently Defueled Technical Specifications NL-20-038, Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline2020-04-23023 April 2020 Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline NL-20-035, Response to Request for Additional Information - Temporary Exemption Request from 10 CFR Appendix R, Section Iii.H Due to COVID-19 Pandemic2020-04-16016 April 2020 Response to Request for Additional Information - Temporary Exemption Request from 10 CFR Appendix R, Section Iii.H Due to COVID-19 Pandemic NL-20-034, Temporary Exemption Request from 10 CFR Appendix R, Section Iii.H Due to COVID-19 Pandemic2020-04-13013 April 2020 Temporary Exemption Request from 10 CFR Appendix R, Section Iii.H Due to COVID-19 Pandemic NL-20-021, Proposed License Amendment to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2020-03-24024 March 2020 Proposed License Amendment to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device NL-20-020, Submittal of 2019 Annual Fitness for Duty Performance Data Report Update2020-02-26026 February 2020 Submittal of 2019 Annual Fitness for Duty Performance Data Report Update NL-20-015, Submittal of 2019 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report2020-02-10010 February 2020 Submittal of 2019 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report NL-20-008, Transmittal of Presentation Slides for Partially Closed Pre-Submittal Meeting to Discuss a Planned License Amendment Request to Replace the Fuel Handling Building Crane2020-01-0606 January 2020 Transmittal of Presentation Slides for Partially Closed Pre-Submittal Meeting to Discuss a Planned License Amendment Request to Replace the Fuel Handling Building Crane NL-19-094, 2018 Annual 10 CFR 50.46 Emergency Core Cooling System Evaluation Changes Report2019-12-16016 December 2019 2018 Annual 10 CFR 50.46 Emergency Core Cooling System Evaluation Changes Report NL-19-084, Application for Order Consenting to Transfers of Control of Licenses and Approving Conforming License Amendments2019-11-21021 November 2019 Application for Order Consenting to Transfers of Control of Licenses and Approving Conforming License Amendments NL-19-093, Proposed Technical Specifications (TS) Changes - Indian Point Nuclear Generating Unit 3 TS SR 3.7.7.2 and TS 3.7.6, Required Action A.12019-11-21021 November 2019 Proposed Technical Specifications (TS) Changes - Indian Point Nuclear Generating Unit 3 TS SR 3.7.7.2 and TS 3.7.6, Required Action A.1 NL-19-092, Request for Rescission of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2019-11-20020 November 2019 Request for Rescission of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) NL-19-043, Request for Partial Exemption from Record Retention Requirements in 10 CFR 50.122019-10-22022 October 2019 Request for Partial Exemption from Record Retention Requirements in 10 CFR 50.12 NL-19-073, Request for Relaxation of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2019-10-22022 October 2019 Request for Relaxation of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) NL-19-078, Supplement to Technical Specifications Proposed Change - Permanently Defueled Technical Specifications2019-10-22022 October 2019 Supplement to Technical Specifications Proposed Change - Permanently Defueled Technical Specifications NL-19-091, Independent Spent Fuel Storage Installation (Isfsi), Registration of Spent Fuel Cask Use2019-10-17017 October 2019 Independent Spent Fuel Storage Installation (Isfsi), Registration of Spent Fuel Cask Use NL-19-090, Registration of Unit 2 Spent Fuel Cask Use2019-10-0909 October 2019 Registration of Unit 2 Spent Fuel Cask Use NL-19-079, 50.59(d)(2) Summary Report of Changes, Tests and Experiments2019-09-26026 September 2019 50.59(d)(2) Summary Report of Changes, Tests and Experiments 2021-05-06
[Table view] Category:License-Application for Facility Operating License (Amend/Renewal) DKT 50
MONTHYEARML23024A0462023-01-17017 January 2023 License Amendment Request for the Independent Spent Fuel Storage Installation-Only Security, Training and Qualification, Safeguards Contingency Plan ML22332A0482022-11-22022 November 2022 New York State Alyse Peterson Comments on Completion of Emergency Planning Nd License Amendment Request Prior to Spent Fuel Transfer from Spent Fuel Pools to Casts (Dockets 50-003, 50-247, 50-286) ML22321A1482022-11-17017 November 2022 License Amendment Request to Approve the Independent Spent Fuel Storage Installation-Only Emergency Plan ML22306A1262022-11-0202 November 2022 License Amendment Request to Revise Indian Point Nuclear Generating Unit Nos. 2 and 3 Renewed Facility Licenses and Permanently Defueled Technical Specifications and IP3 Appendix C Technical Specifications to Reflect Permanent Removal of Sp ML22214A1282022-08-0202 August 2022 License Amendment Request to Revise Indian Point Nuclear Generating Unit No. 2 Permanently Defueled Technical Specifications to Modify Staffing Requirements Following Transfer of Spent Fuel to Dry Storage ML22140A1262022-05-20020 May 2022 License Amendment Request - Revise License Condition to Eliminate Cyber Security Plan Requirements ML22035A1212022-02-0404 February 2022 Revision to Holtec Decommissioning International, LLC, License Amendment Request to Revise the Emergency Plan and Emergency Action Level Scheme to Address the Permanently Defueled Condition ML21356B7042021-12-22022 December 2021 License Amendment Request to Revise the Emergency Plan and Emergency Action Level Scheme to Address the Permanently Defueled Condition NL-20-012, Application to Revise Provisional Operating License and Technical Specifications2020-06-30030 June 2020 Application to Revise Provisional Operating License and Technical Specifications ML20078L1402020-04-15015 April 2020 Issuance of Amendment Nos. 62, 293, and 268 Changes to Emergency Plan for Post-Shutdown and Permanently Defueled Condition ML20017A2902020-01-17017 January 2020 Supplement to Application for Order Consenting to Transfers of Control of Licenses and Approving Conforming License Amendments NL-19-093, Proposed Technical Specifications (TS) Changes - Indian Point Nuclear Generating Unit 3 TS SR 3.7.7.2 and TS 3.7.6, Required Action A.12019-11-21021 November 2019 Proposed Technical Specifications (TS) Changes - Indian Point Nuclear Generating Unit 3 TS SR 3.7.7.2 and TS 3.7.6, Required Action A.1 NL-19-084, Application for Order Consenting to Transfers of Control of Licenses and Approving Conforming License Amendments2019-11-21021 November 2019 Application for Order Consenting to Transfers of Control of Licenses and Approving Conforming License Amendments NL-19-053, Request for Rescission of Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051)2019-06-0606 June 2019 Request for Rescission of Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051) NL-19-013, Proposed Technical Specifications Change - Administrative Controls for Permanently Defueled Condition2019-04-15015 April 2019 Proposed Technical Specifications Change - Administrative Controls for Permanently Defueled Condition NL-19-026, Technical Specifications Proposed Change - Permanently Defueled Technical Specifications2019-04-15015 April 2019 Technical Specifications Proposed Change - Permanently Defueled Technical Specifications NL-19-001, License Amendment Request to Revise the Indian Point Energy Center Site Emergency Plan to Address the Permanently Shut Down and Defueled Condition2019-04-15015 April 2019 License Amendment Request to Revise the Indian Point Energy Center Site Emergency Plan to Address the Permanently Shut Down and Defueled Condition CNRO-2019-00003, Application to Revise Technical Specifications to Adopt TSTF-529 11 Clarify Use and Application Rules, 11 Revision 42019-01-31031 January 2019 Application to Revise Technical Specifications to Adopt TSTF-529 11 Clarify Use and Application Rules, 11 Revision 4 NL-18-034, License Amendment Request- Deletion of Facility Operating License Conditions Related to Decommissioning Trust Provisions2018-06-20020 June 2018 License Amendment Request- Deletion of Facility Operating License Conditions Related to Decommissioning Trust Provisions NL-17-157, Amendment 19 to License Renewal Application (LRA)2017-12-14014 December 2017 Amendment 19 to License Renewal Application (LRA) NL-17-070, Additional Information for the Review of the Plants License Renewal Application (LRA) Regarding the Containment Leak Rate Program2017-05-31031 May 2017 Additional Information for the Review of the Plants License Renewal Application (LRA) Regarding the Containment Leak Rate Program NL-17-049, Unit Nos., 1, 2, and 3, License Amendment Request - Cyber Security Plan Implementation Schedule2017-04-28028 April 2017 Unit Nos., 1, 2, and 3, License Amendment Request - Cyber Security Plan Implementation Schedule NL-17-035, Proposed License Amendment Regarding Connection of Non-Seismic Boric Acid Recovery System to the Refueling Water Storage Tank2017-04-0707 April 2017 Proposed License Amendment Regarding Connection of Non-Seismic Boric Acid Recovery System to the Refueling Water Storage Tank NL-17-018, Consistency Certification for Entergy Nuclear Indian Point 2 and Entergy Nuclear Indian Point 3 License Renewal Application2017-01-31031 January 2017 Consistency Certification for Entergy Nuclear Indian Point 2 and Entergy Nuclear Indian Point 3 License Renewal Application NL-16-138, Amendment 18 to License Renewal Application2016-12-15015 December 2016 Amendment 18 to License Renewal Application NL-16-118, Indian Point Nuclear Power Plant, Units 2 & 3, Proposed License Amendment Regarding the Inter-Unit Transfer of Spent Fuel2016-12-14014 December 2016 Indian Point Nuclear Power Plant, Units 2 & 3, Proposed License Amendment Regarding the Inter-Unit Transfer of Spent Fuel ML16355A0682016-12-14014 December 2016 Licensing Report on the Inter-Unit Transfer of Spent Nuclear Fuel NL-16-118, Proposed License Amendment Regarding the Inter-Unit Transfer of Spent Fuel2016-12-14014 December 2016 Proposed License Amendment Regarding the Inter-Unit Transfer of Spent Fuel CNRO-2016-00020, Application for Order to Transfer Master Decommissioning Trust from PASNY to ENO, Consenting to Amendments to Trust Agreement, and Approving Proposed License Amendments to Modify and Delete Decommissioning .2016-08-16016 August 2016 Application for Order to Transfer Master Decommissioning Trust from PASNY to ENO, Consenting to Amendments to Trust Agreement, and Approving Proposed License Amendments to Modify and Delete Decommissioning . NL-15-148, Amendment 17 to License Renewal Application (LRA)2015-12-14014 December 2015 Amendment 17 to License Renewal Application (LRA) NL-15-144, License Amendment Request - Conditional Exemption from End-of-Life (Eol) Moderator Temperature Coefficient (Mtc) Measurement2015-12-10010 December 2015 License Amendment Request - Conditional Exemption from End-of-Life (Eol) Moderator Temperature Coefficient (Mtc) Measurement NL-15-144, Indian Point, Units 2 and 3 - License Amendment Request - Conditional Exemption from End-of-Life (Eol) Moderator Temperature Coefficient (Mtc) Measurement2015-12-10010 December 2015 Indian Point, Units 2 and 3 - License Amendment Request - Conditional Exemption from End-of-Life (Eol) Moderator Temperature Coefficient (Mtc) Measurement NL-15-109, Reply to Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application, Set 2015-022015-09-0101 September 2015 Reply to Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application, Set 2015-02 NL-15-067, License Amendment Request - Cyber Security Plan Implementation Schedule2015-06-16016 June 2015 License Amendment Request - Cyber Security Plan Implementation Schedule NL-15-021, Proposed License Amendment Regarding a Change to Technical Specification 3.1.4 Reactivity Control Systems Indian Point Unit Number 22015-02-12012 February 2015 Proposed License Amendment Regarding a Change to Technical Specification 3.1.4 Reactivity Control Systems Indian Point Unit Number 2 NL-14-146, Amendment 16 to License Renewal Application (LRA)2014-12-15015 December 2014 Amendment 16 to License Renewal Application (LRA) NL-14-128, Proposed License Amendment Regarding Extending the Containment Type a Leak Rate Testing Frequency to 15 Years2014-12-0909 December 2014 Proposed License Amendment Regarding Extending the Containment Type a Leak Rate Testing Frequency to 15 Years ML14304A7002014-04-30030 April 2014 Annual Energy Outlook 2014 NL-13-145, Proposed License Amendment to Adopt TSTF-510, Revision 2, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection Indian Point Unit Nuclear Generating Unit Nos. 2 and 32014-04-0101 April 2014 Proposed License Amendment to Adopt TSTF-510, Revision 2, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection Indian Point Unit Nuclear Generating Unit Nos. 2 and 3 NL-14-035, Proposed Changes to Technical Specifications Regarding Reactor Vessel Pressure/Temperature Limit Curves2014-04-0101 April 2014 Proposed Changes to Technical Specifications Regarding Reactor Vessel Pressure/Temperature Limit Curves NL-14-016, License Amendment Request - Cyber Security Plan Implementation Schedule2014-01-30030 January 2014 License Amendment Request - Cyber Security Plan Implementation Schedule NL-13-131, Amendment 14 to License Renewal Application (LRA)2013-09-26026 September 2013 Amendment 14 to License Renewal Application (LRA) NL-13-077, License Renewal Application-Update to Electrical Meb and Structures Monitoring Program Scope, Aging Management Programs2013-05-0606 May 2013 License Renewal Application-Update to Electrical Meb and Structures Monitoring Program Scope, Aging Management Programs NL-13-015, Proposed License Amendment Regarding Connection of Non Seismic Boric Acid Recovery System to the Refueling Water Storage Tank2013-04-15015 April 2013 Proposed License Amendment Regarding Connection of Non Seismic Boric Acid Recovery System to the Refueling Water Storage Tank ML13116A0082013-04-0909 April 2013 Engineering Evaluation of Postulated RWST Inventory Loss During the Reverse Osmosis Clean-up Skid Process in Accordance to 2-TAP-001-ROS Due to Seismic Event NL-13-046, Amendment 13 to License Renewal Application (LRA) Pertaining to One-Time Inspection and Selective Leaching Programs2013-03-18018 March 2013 Amendment 13 to License Renewal Application (LRA) Pertaining to One-Time Inspection and Selective Leaching Programs ML13046A1662013-02-22022 February 2013 Issuance of Amendment Connecting Non-Seismic Purification System Piping to the Refueling Water Storage Tank NL-12-190, Amendment 12 to License Renewal Application (LRA)2012-12-27027 December 2012 Amendment 12 to License Renewal Application (LRA) NL-12-090, Proposed License Amendment Regarding Connection of Non Seismic Purification Line to Refuel Water Storage Tank2012-08-14014 August 2012 Proposed License Amendment Regarding Connection of Non Seismic Purification Line to Refuel Water Storage Tank NL-12-107, Application to Renew Operating Licenses for Indian Point Nuclear Power Reactors Unit 2 and Unit 3, General Correspondence - NL-12-1072012-08-0808 August 2012 Application to Renew Operating Licenses for Indian Point Nuclear Power Reactors Unit 2 and Unit 3, General Correspondence - NL-12-107 2023-01-17
[Table view] |
Text
- ~ Entergr. Entergy Nuclear Operations, Inc.
1340 Echelon Parkway Jackson, MS 39213 Tel 601-368-5138 Ron Gaston Director, Nuclear Licensing 10 CFR 2.202 EA-12-051 NL-19-053 June 6, 2019 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
SUBJECT:
Request for Rescission of Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051)
Indian Point Nuclear Generating Unit Nos. 2 and 3 NRC Docket Nos. 50-247 and 50-286 Renewed Facility Operating License Nos. DPR-26 and DPR-64 On March 12, 2012, the U.S. Nuclear Regulatory Commission (NRC) issued Order EA-12-051 (Reference 1) to all power reactor licensees. The Order was effective immediately and directed Entergy Nuclear Operations, Inc. (Entergy) to install reliable spent fuel pool (SFP) level instrumentation at Indian Point Nuclear Generating Unit Nos. 2 (IP2) and 3 (IP3). Specific requirements of the Order are contained in Reference 1.
In accordance with the Order implementation schedule specified in Reference 1, IP3 achieved full compliance with the Order on March 24, 2015 and IP2 achieved full compliance on June 14, 2016. In References 2 and 3, Entergy provided the respective IP3 and IP2 required reports of full compliance with Order EA-12-051 documenting the bases for compliance with the Order.
In Reference 4, the NRC provided the results of their review of the SFP level instrumentation installed at IP2 and IP3, which concluded that the developed guidance and proposed designs, if implemented appropriately, should adequately address the requirements of Order EA-12-051.
In Reference 5, the NRC verified that the SFP instrumentation was in compliance with Order EA-12-051.
In Reference 6, Entergy notified the NRC that it has decided to permanently cease power operations of IP2 by April 30, 2020 and IP3 by April 30, 2021.
The purpose of this letter is to request rescission of Order EA-12-051 for IP2 and IP3 upon each unit's docketing of the Title 1O of the Code of Federal Regulations (1 O CFR) 50.82(a)(1) certifications for permanent cessation of operations and permanent removal of fuel from the reactor vessel. The Enclosure to this letter provides the good cause justification for this request.
NL-19-053 Page 2 of 3 Entergy requests review and approval of this request for rescission of Order EA-12-051 by May 15, 2020.
If you have any questions or require additional information, please contact Mr. Robert Walpole, Manager, Regulatory Assurance, at (914) 254-6710.
There are no new regulatory commitments made in this letter.
I declare under penalty of perjury that the foregoing is true and correct. Executed on June 6, 2019.
Respectfully, Ron Gaston RWG/cdm
Enclosure:
Request for Rescission of Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051)
References:
- 1. NRC Order EA-12-051, "Order Modifying Licenses with Regard to Reliable Spent Fuel Instrumentation," dated March 12, 2012 (ADAMS Accession No. ML12056A044)
- 2. Entergy Nuclear Operations, Inc. (Entergy) letter to U.S. Nuclear Regulatory Commission (NRC), "Notification of Full Compliance with Order EA-12-049, 'Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events,' and Order EA-12-051 'Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation' (TAC Nos.
MF0745 and MF0738), Indian Point Unit Number 3, Docket No. 50-286, License No. DPR-64," dated May 20, 2015 (Letter No. NL-15-059)
(ADAMS Accession No. ML15149A140)
- 3. Entergy letter to NRC, "Notification of Full Compliance with Order EA-12-049, 'Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events,' and Order EA-12-051 'Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation' (TAC Nos. MF0744 and MF0737), Indian Point Unit Number 2, Docket No. 50-247, License No.
DPR-26," dated August 12, 2016 (Letter No. NL-16-089) (ADAMS Accession No. ML16235A292)
NL-19-053 Page 3 of 3
- 4. NRC letter to Entergy, "Indian Point Nuclear Generating Unit Nos. 2 and 3 - Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Order EA-12-049 and EA-12-051 (CAC Nos. MF0737, MF0738, MF0744, and MF0745)," dated March 27, 2017 (ADAMS Accession No. ML17065A171)
- 5. NRC letter to Entergy, "Indian Point Nuclear Generating - Temporary Instruction 2515/191 Inspection Report 05000247/2017010 and 05000286/2017010," dated January 31, 2018 (ADAMS Accession No. ML18031A358)
- 6. Entergy letter to NRC, "Notification of Permanent Cessation of Power Operations," dated February 8, 2017 (Letter No. NL-17-021) (ADAMS Accession No. ML17044A004) cc: Director, Office of Nuclear Reactor Regulation NRC Senior Project Manager, NRC NRR DORL Regional Administrator, NRC Region I NRC Senior Resident Inspector, Indian Point Energy Center President and CEO, NYSERDA New York State (NYS) Public Service Commission
Enclosure NL-19-053 Request for Rescission of Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051)
Enclosure NL-19-053 Page 1 of 4 I. Proposed Order Rescission On March 12, 2012, the U.S. Nuclear Regulatory Commission (NRC) issued Order EA-12-051, "Order to Modify Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation," (Reference 1) to all power reactor licensees. The Order was effective immediately and directed Entergy Nuclear Operations, Inc. (Entergy) to install reliable spent fuel pool (SFP) level instrumentation at Indian Point Nuclear Generating Unit Nos. 2 (IP2) and 3 (IP3). In accordance with the Order implementation schedule specified in Reference 1, IP3 achieved full compliance with the Order on March 24, 2015 and IP2 achieved full compliance on June 14, 2016. In References 2 and 3, Entergy provided the respective IP3 and IP2 required reports of full compliance with Order EA-12-051, documenting the bases for compliance with the Order. In Reference 4, the NRC provided the results of their review of the SFP level instrumentation installed at IP2 and IP3, which concluded that the developed guidance and proposed designs, if implemented appropriately, should adequately address the requirements of Order EA-12-051. In Reference 5, the NRC verified that the SFP instrumentation was in compliance with Order EA-12-051.
In Reference 6, Entergy notified the NRC that it has decided to permanently cease power operations of IP2 by April 30, 2020 and IP3 by April 30, 2021. In accordance with Section IV of the Order, Entergy hereby submits a request that Order EA-12-051 be rescinded for IP2 and IP3 upon each unit's docketing of the Title 10 of the Code of Federal Regulations (10 CFR) 50.82(a)(1) certifications for permanent cessation of operations and permanent removal of fuel from the reactor vessel.
II. Basis for Rescission Request Section IV of Order EA-12-051 provides the NRC Director of the Office of Nuclear Reactor Regulation the authority to relax or rescind any or all of the conditions of the Order upon demonstration by the licensee of good cause.
By letter dated February 8, 2017 (Reference 6), Entergy notified the NRC of the decision to permanently cease power operations of IP2 by April 30, 2020 and IP3 by April 30, 2021.
Section III of Order EA-12-051 states that the Commission determined that all power reactor licensees and construction permit holders must have a reliable means of remotely monitoring wide-range SFP levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. This statement forms the basis of the Order and reflects the need to effectively deploy limited resources to mitigate very low frequency events with the potential to challenge both the reactor and SFP. With reliable indication of the SFP coolant level, decision-makers can determine when to deploy resources to the SFP and avoid unnecessary deployment of staff to monitor pool level.
Upon docketing of the 10 CFR 50.82(a)(1) certifications for permanent cessation of operations and permanent removal of fuel from the reactor vessel, the 10 CFR Part 50 license will no longer authorize operation of the reactor or emplacement or retention of fuel in the reactor vessel. The safety of the irradiated fuel in the SFP will be the primary safety function for site personnel. In the event of a challenge to the safety of fuel stored in the SFP, decision-makers would not have to prioritize actions and the focus of the facility staff would be the SFP condition.
Enclosure NL-19-053 Page 2 of 4 Thus, the basis for Order EA-12-051 will no longer apply to the configurations of IP2 and IP3 upon their respective docketing of the 10 CFR 50.82(a)(1) certifications.
III. Spent Fuel Pool Level Indication Two physically separate and independent channels of SFP direct level indication are installed at IP2 and IP3. The SFP level can be monitored on displays located in each unit's Fan House building, and are accessible without unreasonable delay from the unit's Central Control Room (CCR). In addition to each unit's two channels of remote level indication, local alarms are provided in each unit's CCR that annunciate on high and low SFP level.
Both the primary and backup SFP level instrument channels for each unit are permanently installed, mounted in opposite corners of the SFP. Each level sensor probe utilizes Guided Wave Radar (GWR) technology through the principal of Time Domain Reflectometry (TDR) to provide a single continuous span that extends from a point above the normal water level down to within one foot of the top of the spent fuel racks (probe length approximately 24 feet-2 inches). The high sensor range limit for each unit corresponds to the SFP high level alarm setpoint. The low sensor range limit for each unit provides assurance that reliable SFP water level indication is available to support identification of the condition where the spent fuel remains covered and actions to implement make-up should no longer be deferred. The SFP low level alarm setpoints are above the IP2 Technical Specification (TS) 3.7.11 and IP3 TS 3.7.14 minimum level requirements, and will provide advanced warning of a decreasing level that could potentially result in a loss of SFP cooling due to the loss of pump suction and substantial loss of radiation shielding.
In addition to the instrumentation available for monitoring the IP2 and IP3 SFP levels, the level can also be observed locally from each unit's Fuel Storage Building refueling floor.
Based on the above description, there is adequate indication available to determine the level in the IP2 and IP3 SFPs.
IV. Precedent This request for rescission of Order EA-12-051 for IP2 and IP3 upon each unit's docketing of the 10 CFR 50.82(a)(1) certifications is similar to the Vermont Yankee Nuclear Power Station request that was approved by the NRC on March 2, 2015 (Reference 7) and the Oyster Creek Nuclear Generating Station request that was approved by the NRC on December 14, 2018 (Reference 8).
V. Conclusion Upon docketing of the 10 CFR 50.82(a)(1) certifications for permanent cessation of operations and permanent removal of fuel from the reactor vessel, the 10 CFR Part 50 licenses for IP2 and IP3 will no longer authorize operation of the reactors or emplacement or retention of fuel in the reactor vessels. Since IP2 and IP3 will be permanently shutdown and defueled, no additional fission products will be generated from the reactors and the decay heat load on the spent fuel will continue to decline.
Enclosure NL-19-053 Page 3 of 4 After IP2 and IP3 are permanently shutdown and their reactors permanently defueled, the requirements of Order EA-12-051 applicable to each unit are no longer necessary. In the event of a challenge to the safety of fuel stored in the SFP, decision-makers would not have to prioritize event mitigation and recovery actions because the focus of the facility staff would be the SFP condition. Thus, the basis for the Order will no longer apply to the configurations of IP2 and IP3 upon their respective docketing of the 10 CFR 50.82(a)(1) certifications. The foregoing evaluation demonstrates that the Order is unnecessary for IP2 and IP3 and provides good cause to support this request that the Order be rescinded in its entirety upon docketing of the 10 CFR 50.82(a)(1) certifications for permanent cessation of operations and permanent removal of fuel from the reactor vessel.
Based on the above, the Director, Office of Nuclear Reactor Regulation is requested to rescind Order EA-12-051 for IP2 and IP3 upon each unit's docketing of the 10 CFR 50.82(a)(1) certifications for permanent cessation of operations and permanent removal of fuel from the reactor vessel.
VI. References
- 1. NRC Order EA-12-051, "Order Modifying Licenses with Regard to Reliable Spent Fuel Instrumentation," dated March 12, 2012 (ADAMS Accession No. ML12056A044)
- 2. Entergy Nuclear Operations, Inc. (Entergy) letter to U.S. Nuclear Regulatory Commission (NRC), "Notification of Full Compliance with Order EA-12-049, 'Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events,' and Order EA-12-051 'Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation' (TAC Nos. MF0745 and MF0738), Indian Point Unit Number 3, Docket No. 50-286, License No. DPR-64," dated May 20, 2015 (Letter No.
NL-15-059) (ADAMS Accession No. ML15149A140)
- 3. Entergy letter to NRC, "Notification of Full Compliance with Order EA-12-049, 'Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events,' and Order EA-12-051 'Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation' (TAC Nos. MF0744 and MF0737), Indian Point Unit Number 2, Docket No. 50-247, License No. DPR-26," dated August 12, 2016 (Letter No. NL-16-089) (ADAMS Accession No. ML16235A292)
- 4. NRC letter to Entergy, "Indian Point Nuclear Generating Unit Nos. 2 and 3 - Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Order EA-12-049 and EA-12-051 (CAC Nos. MF0737, MF0738, MF0744, and MF0745)," dated March 27, 2017 (ADAMS Accession No. ML17065A171)
- 5. NRC letter to Entergy, "Indian Point Nuclear Generating - Temporary Instruction 2515/191 Inspection Report 05000247/2017010 and 05000286/2017010," dated January 31, 2018 (ADAMS Accession No. ML18031A358)
- 6. Entergy letter to NRC, "Notification of Permanent Cessation of Power Operations," dated February 8, 2017 (Letter No. NL-17-021) (ADAMS Accession No. ML17044A004)
Enclosure NL-19-053 Page 4 of 4
- 7. NRC letter to Entergy, "Vermont Yankee Nuclear Power Station - Rescission of Order EA-12-051, 'Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation' (TAC No. MF4764)," dated March 2, 2015 (ADAMS Accession No. ML14321A696)
- 8. NRC letter to Exelon Generation Company, LLC, "Oyster Creek Nuclear Generating Station - Withdrawal of Order EA-12-051, 'Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation' (EPID L-2018-JLD-0005)," dated December 14, 2018 (ADAMS Accession No. ML18176A070)