ND-19-0661, Vogtie, Units 3 and 4, Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.3.11.03b (Index Number 454)

From kanterella
(Redirected from ML19151A637)
Jump to navigation Jump to search
Vogtie, Units 3 and 4, Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.3.11.03b (Index Number 454)
ML19151A637
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 05/31/2019
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of New Reactors
References
ND-19-0661
Download: ML19151A637 (5)


Text

Michael J. Yox 7825 River Road

^Southern Nuclear Regulatory Affairs Director Vogtie 3 & 4 Waynesboro, GA 30830 706-848-6459 tei MAY 3 12019 Docket Nos.52-025 52-026 ND-19-0661 10 CFR 52.99(c)(3)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtie Electric Generating Plant Unit 3 and Unit 4 Notice of Uncompleted ITAAC 225-davs Prior to Initial Fuel Load Item 2.3.11.03b [Index Number 4541 Ladies and Gentlemen:

Pursuant to 10 CFR 52.99(c)(3), Southern Nuclear Operating Company hereby notifies the NRC that as of May 6, 2019, Vogtie Electric Generating Plant(VEGP) Unit 3 and Unit 4 Uncompleted Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 2.3.11.03b [Index Number 454]

has not been completed greater than 225-days prior to initial fuel load. The Enclosure describes the plan for completing this ITAAC. Southern Nuclear Operating Company will, at a later date, provide additional notifications for ITAAC that have not been completed 225-days prior to initial fuel load.

This notification is informed by the guidance described in NEI 08-01, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215. In accordance with NEI 08-01, this notification includes ITAAC for which required inspections, tests, or analyses have not been performed or have been only partially completed. All ITAAC will be fully completed and all Section 52.99(c)(1) ITAAC Closure Notifications will be submitted to NRC to support the Commission finding that all acceptance criteria are met prior to plant operation, as required by 10 CFR 52.103(g).

This letter contains no new NRC regulatory commitments.

If there are any questions, please contact Tom Petrak at 706-848-1575.

Respectfully submitted.

Michael J. Yox Regulatory Affairs Direbtor Vogtie 3 & 4

Enclosure:

Vogtie Electric Generating Plant(VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 2.3.11.03b [Index Number 454]

MJY/DLW/sfr

U.S. Nuclear Regulatory Commission ND-19-0661 Page 2 of 3 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. R. G. West(w/o enclosures)

Mr. D. L. McKlnney (w/o enclosures)

Mr. M. D. Meier (w/o enclosures)

Mr. D. H. Jones(w/o enclosures)

Mr. J. B. Klecha Mr. G. Chick Mr. M. J. Vox Mr. A. 8. Parton Ms. K. A. Roberts Mr. T. G. Petrak Mr. W. A. Sparkman Mr. C. T. Defnall Mr. C. E. Morrow Mr. J. L. Hughes Ms. K. M. Stacy Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:

Nuclear Reoulatorv Commission Mr. W.Jones(w/o enclosures)

Mr. F. D. Brown Ms. J. M. Heisserer Mr. C. P. Patel Mr. G. J. Khouri Ms. S. E. Temple Mr. N. D. Karlovich Mr. A. Lerch Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. I. Cozens Mr. J. Gaslevic Mr. V. Hall Qqiethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen Municipal Eiectric Authoritv of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Daiton Utilities Mr. T. Bundros

U.S. Nuclear Regulatory Commission ND-19-0661 Page 3 of 3 Westinqhouse Electric Company. LLC Dr. L. Oriani (w/o enclosures)

Mr. D. C. Durham (w/o enclosures)

Mr. M. M. Corletti Ms. L. G. Iller Ms. J. Monahan Mr. J. L. Coward Other Mr. J. E. Hesler, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, Inc.

Mr. 8. Roetger, Georgia Public Service Commission Ms. 8. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Batch Bingham

U.S. Nuclear Regulatory Commission ND-19-0661 Enclosure Page 1 of 2 Southern Nuclear Operating Company ND-19-0661 Enclosure Vogtle Electric Generating Plant(VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 2.3.11.03b [Index Number 454]

U.S. Nuclear Regulatory Commission ND-19-0661 Enclosure Page 2 of 2 ITAAC Statement Desion Commitment 3.b) The WGS provides the nonsafety-reiated function of controlling the releases of radioactive materials in gaseous effluents.

I nspections/Tests/Analvses Tests will be performed to confirm that the presence of a simulated high radiation signal from the discharge radiation monitor, WGS-017,causes the discharge control isolation valve WGS-PL-V051 to close.

Acceptance Criteria A simulated high radiation signal causes the discharge control isolation valve WGS-PL-V051 to close.

ITAAC Completion Description Testing is performed to confirm the Gaseous Radwaste System (WGS) provides the nonsafety-reiated function of controlling the releases of radioactive materials in gaseous effluents by verifying a simulated high radiation signal causes the discharge control isolation valve WGS-PL-V051 to close.

Testing is performed in accordance with the Unit 3 and Unit 4 component test packages SNC922146 and SNCXXXXXX (References 1 and 2), by verifying WGS-PL-V051 is initially open. The test simulates a high radiation signal on the discharge radiation monitor, WGS-PL-V051 is verified to close on the Plant Control System (PLS) monitor in the Main Control Room and verification is documented in the component test package.

This testing verifies that a simulated high radiation signal causes the discharge control isolation valve WGS-PL-V051 to close.

References 1 and 2 are available for NRC inspection as part of Unit 3 and Unit 4 ITAAC Completion Packages (Reference 3 and 4).

List of ITAAC Findings In accordance with plant procedures for ITAAC completion. Southern Nuclear Operating Company(SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC.

References(available for NRC inspection)

1. SNC922146,'Waste Gas System Verification ITAAC: SV3-ITAAC-ST-2.3.11.03b"
2. SNCXXXXXX,'Waste Gas System Verification ITAAC: SV4-ITAAC-ST-2.3.11.03b"
3. 2.3.11.03b-U3-CP-Rev 0, ITAAC Completion Package
4. 2.3.11.03b-U4-CP-Rev 0, ITAAC Completion Package
5. NEI 08-01,"Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52"