Unit 4 - Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.6.01.04c (Index Number 586)
ML19120A352
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 04/30/2019
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of New Reactors
References
ND-19-0503
Download: ML19120A352 (6)


Text

Michael J. Yox 7825 River Road

^Southern Nuclear Regulatory Affairs Director Waynesboro, GA 30830 Vogtle3&4 706-848-6459 tel APR 3 0 2D19 Docket Nos.: 52-025 52-026 ND-19-0503 10CFR 52.99(c)(3)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 and Unit 4 Notice of Uncompleted ITAAC 225-davs Prior to Initial Fuel Load Item 2.6.01.04c [Index Number 5861 Ladies and Gentlemen:

Pursuant to 10 CFR 52.99(c)(3), Southern Nuclear Operating Company hereby notifies the NRC that as of April 22, 2019, Vogtle Electric Generating Plant(VEGP) Unit 3 and IJnit 4 Uncompleted Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 2.6.01.04c [Index Number 586]

has not been completed greater than 225-days prior to initial fuel load. The Enclosure describes the plan for completing this ITAAC. Southern Nuclear Operating Company will, at a later date, provide additional notifications for ITAAC that have not been completed 225-days prior to initial fuel load.

This notification is informed by the guidance described in NEI 08-01, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215. In accordance with NEI 08-01, this notification includes ITAAC for which required inspections, tests, or analyses have not been performed or have been only partially completed. All ITAAC will be fully completed and all Section 52.99(c)(1) ITAAC Closure Notifications will be submitted to NRC to support the Commission finding that all acceptance criteria are met prior to plant operation, as required by 10 CFR 52.103(g).

This letter contains no new NRC regulatory commitments.

If there are any questions, please contact Tom Petrak at 706-848-1575.

Respectfully submitted.

Michael J. Yox Regulatory Affairs Director Vogtle 3 & 4

Enclosure:

Vogtle Electric Generating Plant(VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 2.6.01.04c [Index Number 586]

MJY/DLW/sfr

U.S. Nuclear Regulatory Commission ND-19-0503 Enclosure Page 2 of 3 To:

Southern Nuclear Operating ComDanv/ Georgia Power Company Mr. D. A. Bost(w/o enclosures)

Mr. D. L. McKinney (w/o enclosures)

Mr. M. D. Meier (w/o enclosures)

Mr. D. H. Jones(w/o enclosures)

Mr. J. B. Klecha Mr. G. Chick Mr. M. J. Yox Mr. A. 8. Parton Ms. K. A. Roberts Mr. T. G. Petrak Mr. W. A. Sparkman Mr. C. T. Defnall Mr. C. E. Morrow Mr. J. L. Hughes Ms. K. M. Stacy Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:

Nuclear Regulatory Commission Mr. W.Jones(w/o enclosures)

Mr. F. D. Brown Ms. J. M. Heisserer Mr. C. P. Patel Mr. G. J. Khouri Ms. S. E. Temple Mr. N. D. Karlovich Mr. A. Lerch Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. I. Cozens Mr. J. Gaslevic Mr. V. Hall Ooiethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen Municipal Electric Authoritv of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Dalton Utilities Mr. T. Bundros

U.S. Nuclear Regulatory Commission ND-19-0503 Enclosure Page 3 of 3 Westinqhouse Electric Company. LLC Dr. L. Oriani (w/o enclosures)

Mr. D. C. Durham (w/o enclosures)

Mr. M. M. Corletti Ms. L. G. Iller Ms. J. Monahan Mr. J. L. Coward Other Mr. J. E. Hosier, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., CDS Associates, inc.

Mr. 8. Roetger, Georgia Public Service Commission Ms. 8. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Baich Bingham

U.S. Nuclear Regulatory Commission ND-19-0503 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-19-0503 Enclosure Vogtle Electric Generating Plant(VEGP)Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 2.6.01.04c [Index Number 586]

U.S. Nuclear Regulatory Commission ND-19-0503 Enclosure Page 2of 3 ITAAC Statement Desion Commitment 4.c) Each standby diesel generator 6900 Vac circuit breaker closes after receiving a signal from the onsite standby power system.

I nsoections/Tests/Analvses Testing will be performed using real or simulated signals from the standby diesel load system.

Acceptance Criteria Each standby diesel generator 6900 Vac circuit breaker closes after receiving a signal from the standby diesel system.

ITAAC Completion Description Testing is performed in accordance with 3-ZOS-ITPP-503 and 4-ZOS-ITPP-503(References 1 and 2) using real signals from the standby diesel load system to confirm each standby diesel generator 6900 Vac circuit breaker closes after receiving a signal from the standby diesel system.

References 1 and 2 install temporary modifications which allow for tripping of the Unit Auxiliary Transformer(UAT)and Reserve Auxiliary Transformer feeder breakers, ensuring that a bus transfer does not occur, and creating a real undervoltage condition on bus ECS-ES-1 which in turn initiates a bus load shed, the start of the A diesel generator, and a closure of the diesel generator 6900Vac output circuit breaker when the diesel generator is ready to load. The test is repeated for bus ECS-ES-2 and the B diesel generator.

The results of the testing confirm that for Unit 3 and Unit 4 each standby diesel generator 6900 Vac circuit breaker closes after receiving a signal from the standby diesel system.

References 1 and 2 are available for NRC inspection as part of Unit 3 and Unit 4 ITAAC 2.6.01.04c Completion Packages(Reference 3 and 4).

List of ITAAC Findings In accordance with plant procedures for ITAAC completion. Southern Nuclear Operating Company(SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC.

U.S. Nuclear Regulatory Commission ND-19-0503 Enclosure Page 3of 3 References favailable for NRG inspection)

1. 3-ZOS-ITPP-503,"Onsite Standby Power System - Load Sequencing Tests"
2. 4-ZOS-ITPP-503,"Onsite Standby Power System - Load Sequencing Tests"
3. 2.6.01.04c-U3-CP-Rev0, ITAAC Completion Package
4. 2.6.01.04c-U4-CP-Rev0, ITAAC Completion Package
5. NEI 08-01,"Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52"