ND-19-0002, Unit 4 - Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.2.00.02 (Index Number 745)

From kanterella
(Redirected from ML19011A085)
Jump to navigation Jump to search
Unit 4 - Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.2.00.02 (Index Number 745)
ML19011A085
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 01/10/2019
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of New Reactors
References
ITAAC 3.2.00.02, ND-19-0002
Download: ML19011A085 (7)


Text

A Southern Nuclear Michael J. Yox Regulatory Affairs Director 7825 River Road Waynesboro, GA 30830 Vogtle 3 & 4 706-848-6459 tel 41 0-4 74-8587 cell JAN 10 2019 myox @southernco.com Docket Nos.: 52-025 52-026 ND-19-0002 10 CFR 52.99(c)(3)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 and Unit 4 Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.2.00.02 (Index Number 7451 Ladies and Gentlemen:

Pursuant to 10 CFR 52.99(c)(3), Southern Nuclear Operating Company hereby notifies the NRC that as of January 07, 2019, Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Uncompleted Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 3.2.00.02 (Index Number 745] has not been completed greater than 225-days prior to initial fuel load. The Enclosure describes the plan for completing ITAAC 3.2.00.02 [Index Number 745). Southern Nuclear Operating Company will , at a later date, provide additional notifications for ITAAC that have not been completed 225-days prior to initial fuel load.

This notification is informed by the guidance described in NEl-08-01, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215. In accordance with NEI 08-01, this notification includes ITAAC for which required inspections, tests , or analyses have not been performed or have been only partially completed.

All lTAAC will be fully completed and all Section 52.99(c)(3) ITAAC Closure Notifications will be submitted to NRC to support the Commission finding that all acceptance criteria are met prior to plant operation , as required by 10 CFR 52.103(9) .

This letter contains no new NRC regulatory commitments.

If there are any questions, please contact Tom Petrak at 706-848-1575.

Michael J. Yox Regulatory Affairs Director Vogtle 3 & 4 I

U.S. Nuclear Regulatory Commission ND-19-0002 Page2 of 4

Enclosure:

Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 3.2.00.02 [Index Number 745]

MJY/LBP/sfr

U.S. Nuclear Regulatory Commission ND-19-0002 Page 3 of 4 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. D. A. Bost (w/o enclosures)

Mr. D. L. McKinney (w/o enclosures)

Mr. M. D. Meier (w/o enclosures)

Mr. D. H. Jones (w/o enclosures)

Mr. J.B. Klecha Mr. G. Chick Mr. M. J. Yox Mr. A. S. Parton Ms. A. L. Pugh Mr. T. G. Petrak Mr. W. A. Sparkman Mr. C. T. Defnall Mr. C. E. Morrow Mr. J. L. Hughes Ms. K. M. Stacy Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.U.L06 File AR.01.02.06 cc:

Nuclear Regulatory Commission Mr. W. Jones (w/o enclosures)

Mr. F. D. Brown Ms. J.M. Heisserer Mr. C. P. Patel Mr. G. J. Khouri Ms. S. E. Temple Mr. N. D. Karlovich Mr. A. Lerch Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. I. Cozens Mr. J. Gaslevic Mr. V. Hall Oglethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Dalton Utilities Mr. T. Bundros

U.S. Nuclear Regulatory Commission ND-19-0002 Page 4 of 4 Westinghouse Electric Company. LLC Dr. L. Oriani (w/o enclosures)

Mr. D. C. Durham (w/o enclosures)

Mr. M. M. Corletti Ms. L. G. Iller Ms. J. Monahan Mr. J. L. Coward Other Mr. J. E. Hesler, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W.R. Jacobs, Jr., Ph.D., GOS Associates, Inc.

Mr. S. Roetger, Georgia Public Service Commission Ms. S. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. S. Blanton, Balch Bingham

U.S. Nuclear Regulatory Commission ND-19-0002 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-19-0002 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 3.2.00.02 [Index Number 745]

U.S. Nuclear Regulatory Commission ND-19-0002 Enclosure Page 2 of 3 ITAAC Statement Design Commitment

2. The MCR includes reactor operator workstations, supervisor workstation(s), safety-related displays, and safety-related controls.

Inspections/rests/Analyses An inspection of the MCR workstations and control panels will be performed.

Acceptance Criteria The MCR includes reactor operator workstations, supervisor workstation(s), safety-related displays, and safety-related controls.

ITAAC Completion Description An inspection of the Main Control Room (MCR) workstations and control panels is performed to verify that the MCR includes reactor operator workstations, supervisor workstation(s), safety-related displays, and safety-related controls.

The inspection utilizes approved construction drawings and control room panel design specifications to perform walkdown inspections of the Unit 3 and Unit 4 MCR. The walkdown inspections compare the as-built workstations, displays, and controls with References 1 through 5 to confirm that the MCR includes reactor operator workstations, supervisor workstation(s),

safety-related displays, and safety-related controls.

The inspection results are documented in the Unit 3 and Unit 4 Principal Closure Documents (References 6 and 7) which confirm that the MCR includes reactor operator workstations, supervisor workstation(s), safety-related displays, and safety-related controls.

References 6 and 7 are available for NRC inspection as part of the Unit 3 and Unit 4 ITAAC 3.2.00.02 Completion Packages (References 8 and 9, respectively).

List of ITAAC Findings In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company (SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC.

U.S. Nuclear Regulatory Commission ND-19-0002 Enclosure Page 3 of 3 References (available for NRC inspection)

1. SV3(4)-JC01-V1-001, "AP1000 Main Control Area Layout Top View
2. SV3(4)-JC01-V1-003, "AP1000 Main Control Area Component Tag Assignments"
3. SV3(4)-JC01-V1-311, "AP1000 Primary Dedicated Safety Panel Layout"
4. SV3(4)-JC01-V1-370, "AP1000 Secondary Dedicated Safety Panel Layout"
5. SV3(4)-JC01-Z0-001, "AP1000 Design Specification for Control Room Consoles and Panels"
6. Unit 3 Principal Closure Document XXX Unit 3
7. Unit 4 Principal Closure Document YYY Unit 4
8. 3.2.00.02-U3-CP-Rev0, ITAAC Completion Package
9. 3.2.00.02-U4-CP-Rev0, ITAAC Completion Package
10. NEI 08-01, "Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52"