Category:Letter type:ND
MONTHYEARND-24-0019, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-02-0101 February 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0912, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-01-0202 January 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0881, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-12-0404 December 2023 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0817, (Vegp), Units 3 and 4 - Report of UFSAR Chapter 14 Changes to the Initial Test Program in Accordance with License Condition 2.D.(7)(a)2023-11-17017 November 2023 (Vegp), Units 3 and 4 - Report of UFSAR Chapter 14 Changes to the Initial Test Program in Accordance with License Condition 2.D.(7)(a) ND-23-0823, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-11-0303 November 2023 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0723, (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-10-0404 October 2023 (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0697, (Vegp), Unit 4, Submittal of Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-09-0505 September 2023 (Vegp), Unit 4, Submittal of Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0669, (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-08-0707 August 2023 (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0205, (Vegp), Unit 3 - Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests2023-07-28028 July 2023 (Vegp), Unit 3 - Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests ND-23-0618, Resubmittal of ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.07c.ii.a (Index Number 797)2023-07-20020 July 2023 Resubmittal of ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.07c.ii.a (Index Number 797) ND-23-0609, Notification of Completion of All ITAAC2023-07-20020 July 2023 Notification of Completion of All ITAAC ND-23-0608, ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72) ND-23-0607, ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13) ND-22-0796, ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.08 (Index Number 813)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.08 (Index Number 813) ND-23-0459, ITAAC Closure Notification on Completion of ITAAC 2.6.01.04d (Index Number 587)2023-07-19019 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.01.04d (Index Number 587) ND-23-0162, ITAAC Closure Notification on Completion of ITAAC 2.2.03.05a.i (Index Number 165)2023-07-19019 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.05a.i (Index Number 165) ND-23-0575, ITAAC Closure Notification on Completion of ITAAC 2.6.01.04e (Index Number 588)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.01.04e (Index Number 588) ND-23-0439, ITAAC Closure Notification on Completion of ITAAC 2.2.05.07a.i (Index Number 265)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.05.07a.i (Index Number 265) ND-23-0552, Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Unit 4, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02c (Index Number 624)2023-07-18018 July 2023 Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Unit 4, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02c (Index Number 624) ND-23-0483, ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4) ND-23-0586, ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159)2023-07-17017 July 2023 ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159) ND-23-0610, ITAAC Closure Notification on Completion of ITAAC Item 2.6.03.04c (Index Number 603)2023-07-17017 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.6.03.04c (Index Number 603) ND-23-0573, ITAAC Closure Notification on Completion of 2.4.02.02a (Index Number 497)2023-07-16016 July 2023 ITAAC Closure Notification on Completion of 2.4.02.02a (Index Number 497) ND-23-0406, ITAAC Closure Notification on Completion of ITAAC Item 2.4.02.02b (Index Number 498)2023-07-16016 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.4.02.02b (Index Number 498) ND-22-0816, ITAAC Closure Notification of Completion of ITAAC 2.1.02.05a (Index Number 19)2023-07-15015 July 2023 ITAAC Closure Notification of Completion of ITAAC 2.1.02.05a (Index Number 19) ND-23-0603, ITAAC Closure Notification on Completion of ITAAC Item 3.5.00.06 (Index Number 831)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 3.5.00.06 (Index Number 831) ND-23-0446, ITAAC Closure Notification on Completion of ITAAC 2.2.04.12a.iii (Index Number 250)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.04.12a.iii (Index Number 250) ND-23-0594, ITAAC Closure Notification on Completion of ITAAC 2.6.05.02.ii (Index Number 629)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.05.02.ii (Index Number 629) ND-23-0601, ITAAC Closure Notification on Completion of ITAAC Item 2.7.05.02.i (Index Number 719)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.7.05.02.i (Index Number 719) ND-23-0606, ITAAC Closure Notification on Completion of ITAAC 2.5.04.02.i (Index Number 557)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.5.04.02.i (Index Number 557) ND-23-0476, ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355) ND-23-0499, ITAAC Closure Notification on Completion of ITAAC 2.7.01.14 (Index Number 700)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.01.14 (Index Number 700) ND-23-0588, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78) ND-23-0121, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.07 (Index Number 667)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.07 (Index Number 667) ND-23-0122, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.08a (Index Number 668)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.08a (Index Number 668) ND-23-0597, ITAAC Closure Notification on Completion of ITAAC 2.5.02.06a.ii (Index Number 530)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.5.02.06a.ii (Index Number 530) ND-23-0002, ITAAC Closure Notification on Completion of ITAAC 2.2.05.07c (Index Number 270)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.05.07c (Index Number 270) ND-23-0111, ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646) ND-22-0980, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.06.i (Index Number 75)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.06.i (Index Number 75) ND-23-0587, ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595) ND-23-0461, ITAAC Closure Notification on Completion of ITAAC 2.6.09.13a (Index Number 652)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.09.13a (Index Number 652) ND-23-0543, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02a (Index Number 622)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02a (Index Number 622) ND-23-0394, ITAAC Closure Notification on Completion of ITAAC 2.7.02.03a (Index Number 703)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.02.03a (Index Number 703) ND-23-0592, ITAAC Closure Notification on Completion of 2.7.06.03.i (Index Number 726)2023-07-12012 July 2023 ITAAC Closure Notification on Completion of 2.7.06.03.i (Index Number 726) ND-23-0589, ITAAC Closure Notification on Completion of ITAAC 2.6.03.04a (Index Number 601)2023-07-12012 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.03.04a (Index Number 601) ND-23-0581, ITAAC Closure Notification on Completion of ITAAC 2.2.04.02a (Index Number 220)2023-07-12012 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.04.02a (Index Number 220) ND-23-0486, ITAAC Closure Notification on Completion of ITAAC 2.2.01.11a.iv (Index Number 117)2023-07-11011 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.01.11a.iv (Index Number 117) ND-23-0559, CFR26.719(c)(1) 30-Day Report for a Blind Sample Analysis Error2023-07-11011 July 2023 CFR26.719(c)(1) 30-Day Report for a Blind Sample Analysis Error ND-23-0443, ITAAC Closure Notification on Completion of ITAAC 2.3.10.07a.ii (Index Number 444)2023-07-0808 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.10.07a.ii (Index Number 444) ND-23-0183, ITAAC Closure Notification on Completion of ITAAC Item 2.3.11.03b (Index Number 454)2023-07-0808 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.3.11.03b (Index Number 454) 2024-02-01
[Table view] |
Text
Michael J. Yox 7825 River Road Regulatory Affairs Director
^ Southern Nuclear Vogtle 3 & 4 Waynesboro, GA 30830 706-848-6459 tel 410-474-8587 cell DEC 0 5 2018 myox@southernco.com Docket Nos.: 52-025 52-026 ND-18-1383 10CFR 52.99(c)(3)
U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 and Unit 4 Notice of Uncompleted ITAAC 225-davs Prior to Initial Fuel Load Item E.3.9.07.01.02 findex Number 8661 Ladies and Gentlemen:
Pursuant to 10 CFR 52.99(c)(3), Southern Nuclear Operating Company hereby notifies the NRC that as of December 4, 2018, Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Uncompleted Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item E.3.9.07.01.02
[Index Number 866] has not been completed greater than 225-days prior to ihitial fuel load. The Enclosure describes the plan for completing this ITAAC. Southern Nuclear Operating Company will, at a later date, provide additional notifications for ITAAC that have not been completed 225-days prior to initial fuel load.
This notification is informed by the guidance described in NEI 08-01, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215. In accordance with NEI 08-01, this notification includes ITAAC for which required inspections, tests, or analyses have not been performed or have been only partially completed. All ITAAC will be fully completed and all Section 52.99(c)(1) ITAAC Closure Notifications will be submitted to NRC to support the Commission finding that all acceptance criteria are met prior to plant operation, as required by 10 CFR 52.103(g).
This letter contains no new NRC regulatory commitments.
If there are any questions, please contact Tom Petrak at 706-848-1575.
Respectfully submitted.
Michael J Regulatory Affairs irector Vogtle 3 & 4
Enclosure:
Vogtle Electric Generating Plant (VEGP) Unit 3 & Unit 4 Completion Plan for Uncompleted ITAAC E.3.9.07.01.02 [Index Number 866]
MJY/RLB/sfr
U.S. Nuclear Regulatory Commission ND-18-1383 Page 2 of 3 To:
Southern Nuclear Operating Company/ Georgia Power Company Mr. D. A. Bost (w/o enclosures)
Mr. D. L. McKinney (w/o enclosures)
Mr. M. D. Meier (w/o enclosures)
Mr. D. H. Jones (w/o enclosures)
Mr. J. B. Klecha Mr. G. Chick Mr. M. J. Yox Mr. A. 8. Parton Ms. A. L. Pugh Mr. T. G. Petrak Mr. W. A. Sparkman Mr. C. T. Defnall Mr. C. E. Morrow Mr. J. L. Hughes Ms. K. M. Stacy Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:
Nuclear Reaulatorv Commission Mr. W. Jones (w/o enclosures)
Mr. F. D. Brown Ms. J. M. Heisserer Mr. C. P. Patel Mr. G. J. Khouri Ms. S. E. Temple Mr. N. D. Karlovich Mr. A. J. Lerch Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. I. Cozens Mr. J. Gaslevic Mr. V. Hall Oalethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen Municipal Electric Authorltv of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Dalton Utilities Mr. T. Bundros
U.S. Nuclear Regulatory Commission ND-18-1383 Page 3 of 3 Westinahouse Electric ComDanv. LLC Dr. L. Oriani (w/o enclosures)
Mr. D. 0. Durham (w/o enclosures)
Mr. M. M. Corletti Ms. L. G. Iller Ms. J. Monahan Mr. J. L. Coward Other Mr. J. E. Hosier, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.
Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, Inc.
Mr. 8. Roetger, Georgia Public Service Commission Ms. 8. W. Kernlzan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Batch Bingham
U.S. Nuclear Regulatory Commission ND-18-1383 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-18-1383 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 3 & Unit 4 Completion Plan for Uncompleted ITAAC E.3.9.07.01.02 [Index Number 866]
U.S. Nuclear Regulatory Commission ND-18-1383 Enclosure Page 2 of 3 ITAAC Statement Prooram Commitment 7.1 The means exists to warn and advise onsite individuals of an emergency, including those in areas controlled by the operator, including:
- Employees not having emergency assignments
- Contractor and construction personnel
- Other persons who may be in the public access areas, on or passing through the site, or within the owner controlled area
[J.I]
Insoections/Tests/Analvses 7.1 Atest will be performed of the capabilities to warn and advise onsite individuals of an emergency, including nonessential personnel; visitors; contractor and construction personnel; and other personnel within the owner controlled area.
Acceotance Criteria 7.1.2 Demonstrate the ability to notify and advise onsite personnel, including:
- 1. Non-essential personnel;
- 2. Visitors;
- 3. Contractor and construction personnel; and
- 4. Other personnel within the owner controlled area.
ITAAC Completion Description AVogtle Electric Generating Plant (VEGP) Unit 3 (Unit 4) test of the capabilities to warn and advise onsite individuals of an emergency is performed to demonstrate the ability to notify and advise onsite personnel including non-essential personnel; visitors; contractor and construction personnel; and other personnel within the VEGP Unit 3 (Unit 4) owner controlled area.
The Unit 3 (Unit 4) test, in the form of an emergency plan drill scenario, is developed in accordance with procedure NMP-EP-303 (Reference 1). The drill scenario is ofsufficient severity to demonstrate the ability to notify and advise onsite personnel ofan emergency through implementation of procedure NMP-EP-142 (Reference 2), applicable sub-tier document(s) to NMP-EP-142, and procedure 91704-0 (Reference3).
An evaluation of the Unit 3 (Unit 4) drill performance is conducted per procedure NMP-EP-303.
The drill performance (test) results are documented in Unit 3 (Unit 4) Drill/Exercise Report XXX (Reference 4) perprocedure NMP-EP-303. The Unit 3 (Unit 4) Drill/Exercise Report documents and confirms the ability to notify and advise onsite personnel ofan emergency, including non-essential personnel; visitors; contractor and construction personnel; and other personnel within the owner controlled area.
U.S. Nuclear Regulatory Commission ND-18-1383 Enclosure Page 3 of 3 References 1 tfirough 4 are available for NRG inspection as part of the Unit 3 (Unit 4) ITAAC E.3.9.07.01.02 Completion Package (Reference 5 (6)).
List of ITAAC Findings In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company (SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAACfindings associated with this ITAAC.
References favaiiable for NRG inspection)
- 1. Procedure NMP-EP-303, Drill and Exercise Standards
- 2. Procedure NMP-EP-142, Emergency Notification
- 3. Procedure 91704-C, Actions for Security During an Emergency
- 4. Unit 3 (Unit 4) Drill/Exercise Report XXX
- 5. E.3.9.07.01.02-U3-CP-Rev 0, ITAAC Completion Package
- 6. E.3.9.07.01.02-U4-CP-Rev 0, ITAAC Completion Package
- 7. NEI 08-01, "IndustryGuideline for the ITAAC Closure Process Under 10 CFR Part 52"