MONTHYEARIR 05000602/20242012024-02-20020 February 2024 University of Texas at Austin - U.S. Nuclear Regulatory Commission Safety Inspection Report 05000602/2024201 IR 05000602/20232012023-07-31031 July 2023 University of Texas at Austin - NRC Safety Inspection Report No. 05000602/2023201 ML23193B0332023-07-31031 July 2023 University of Texas at Austin - NRC Security Inspection 2023202 IR 05000602/20222012023-01-25025 January 2023 University of Texas at Austin - U.S. Nuclear Regulatory Commission Special Inspection Report 05000602/2022201 IR 05000602/20212012022-01-26026 January 2022 University of Texas at Austin - Us Nuclear Regulatory Commission Routine Safety Inspection Report No. 05000602/2021201 IR 05000602/20202012021-05-0707 May 2021 University of Texas at Austin - Nuclear Regulatory Commission Security Inspection Report No. 05000602/2020201 - Cover Letter Only (Public) IR 05000602/20202022021-01-0606 January 2021 University of Texas at Austin - Nuclear Regulatory Commission Routine Inspection Report 05000602/2020202 IR 05000602/20192012019-12-23023 December 2019 University of Texas - Austin U.S. Nuclear Regulatory Commission Routine Inspection Report NO.50-0602/2019-201 IR 05000602/20182012019-05-22022 May 2019 University of Texas at Austin - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 50-602/2018-201 IR 05000602/20172012017-12-14014 December 2017 University of Texas at Austin - U.S. Regulatory Commission Security Related Inspection Report No. 50-602/2017-201 Cover Letter IR 05000602/20162012016-12-0505 December 2016 University of Texas at Austin - Nuclear Regulatory Commission Routine Inspection Report No. 50-602/2016-201 IR 05000602/20152012015-10-0202 October 2015 IR 05000602/2015201, on 08/31 - 09/03/2015, University of Texas at Austin, NRC Routine Inspection Report IR 05000602/20092012009-10-0101 October 2009 IR 05000602-09-201 on 09/14/09 - 09/17/09 for University of Texas at Austin IR 05000602/20072022007-11-16016 November 2007 IR 05000602-07-202, on 11/07/2007 - 11/08/2007, for Univ. of Texas at Austin Nuclear Engineering Teaching Laboratory IR 05000602/20072012007-11-16016 November 2007 NRC Inspection Report No. 50-602/2007-201 IR 05000602/20062012006-11-21021 November 2006 IR 05000602-06-201, University of Texas - Austin, Primary Focus of This Routine, Announced Insp Included Onsite Review of Selected Aspects of the Licensee'S Class II Research Reactor Safety Program.... IR 05000602/20052012005-12-22022 December 2005 NRC Inspection Report No. 05000602-05-201, Univ of Texas at Austin IR 05000602/19982011999-03-0202 March 1999 Insp Rept 50-602/98-201 on 981207-11.No Violations Noted. Major Areas Inspected:Review of Selected Conditions & Records Since Last Insp,Verification of C/A Previously Committed to by Licensee IR 05000302/19972011998-01-0909 January 1998 Insp Rept 50-302/97-201 on 970929-1003.No Violations Noted. Major Areas Inspected:Review of Selected Conditions & Records Since Last Insp,Verification of CAs Previously Committed by Licensee & Related Discussion W/Personnel IR 05000602/19972011998-01-0909 January 1998 Forwards Insp Rept 50-602/97-201 on 970929-1003.No Violations Noted.Previous Level IV Violation Was Closed IR 05000192/19920021993-01-0505 January 1993 Insp Repts 50-192/92-02 & 50-602/92-02 on 921207-11.No Violations or Deviations Noted.Major Areas Inspected: Organization & Staffing,Procedures,Operator Requalification Training,Health Physics Program & Physical Security IR 05000602/19910011991-07-23023 July 1991 University of Texas Construction Inspection Report 05000602/1991001 IR 05000192/19900011990-10-0101 October 1990 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-192/90-01 IR 05000602/19900041990-08-0202 August 1990 University of Texas Construction Inspection Report 05000602/1990004 IR 05000602/19900031990-07-27027 July 1990 University of Texas Construction Inspection Report 05000602/1990003 IR 05000602/19900021990-05-0909 May 1990 University of Texas Construction Lnspection Report 05000602/1990002 IR 05000602/19900011990-04-16016 April 1990 University of Texas Construction Lnspection Report 05000602/1990001 IR 05000602/19890071990-01-11011 January 1990 University of Texas Construction Inspection Report 05000602/1989007 IR 05000602/19890061989-11-29029 November 1989 University of Texas Construction Inspection Report 05000602/1989006 IR 05000192/19890021989-07-13013 July 1989 University of Texas Construction Inspection Reports 05000192/1989002 & 05000602/1989004 IR 05000192/19890031989-07-0606 July 1989 University of Texas Construction Inspection Reports 05000192/1989003 & 05000602/1989005 IR 05000602/19890031989-05-23023 May 1989 University of Texas Construction Inspection Report 05000602/1989003 IR 05000602/19890021989-04-27027 April 1989 University of Texas Construction Inspection Report 05000602/1989002 IR 05000192/19890011989-02-10010 February 1989 University of Texas Construction Inspection Reports 0500192/1989001 & 0500602/1989001 IR 05000602/19880051988-10-12012 October 1988 Insp Rept 50-602/88-05 on 880922-23.No Violations or Deviations Noted.Major Areas Inspected:Mechanical Equipment, Piping,Electrical Sys Installation,Const Progress & Schedule Status IR 05000192/20020021988-09-22022 September 1988 Amend 4 to License 50-19202-02 for Cti,Inc,Amending License in Entirety.W/Ba Riedlinger IR 05000192/20020011988-09-21021 September 1988 Amend 19 to License 50-19202-01 for Cti,Inc,Amending License in Entirety.W/Ba Riedlinger IR 05000192/19880021988-09-0202 September 1988 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-192/88-02 & 50-602/88-02 IR 05000602/19880041988-08-0404 August 1988 University of Texas Construction Inspection Report 05000602/1988004 IR 05000602/19880031988-07-0505 July 1988 University of Texas Construction Inspection Report 05000602/1988003 IR 05000192/19880011988-06-0808 June 1988 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-192/88-01 & 50-602/88-01.Based on Listed Understanding of Util Response, Per 880516 Telcon,Actions Responsive to NRC Concerns IR 05000602/19870011987-12-18018 December 1987 University of Texas Construction Lnspection Report 05000602/1987001 IR 05000192/19860011986-06-0404 June 1986 University of Texas Construction Inspection Reports 05000192/1986001 & 05000602/1986001 IR 05000192/19980011985-07-19019 July 1985 Advises That License 50-19298-01 Retired,Per 830801 Memo 2024-02-20
[Table view] |
Inspection Report - - 1989001 |
---|
|
|
Text
APPENDIX U.S. NUCLEAR PEGULATORY COMMISSION
REGION IV
NRC Inspection Peport: 50-192/89-01 OpPrating Licenses: R-9?
50-602/89-01 Construction Permit: CPRR-123 Dockets: 50-192 50-602 Licensee: University of Texas College of Engineering Department of Mechanical Engineering Nuclear Engineering Programs Austin, Texas 7871?
Fae i 11 ty Name: Nuclear Engineering Teaching Laboratory (NETL) (TRIGA Mark I and Mark II)
Inspection At: NETL Balcones Research Center, and Taylor Hall NF.TL (Main Campus)
Inspection Conducted: January 25. 1989 -;
/
rograms
- l-- - 19 ystems nate Approved:/,,.,:
. / {' rograms ect on L*
- :'1 ****, ;\ ... \: **..1 '.i
, .-. :::..:*,:*.(.
\ - ...
,4*,,*.
,:, .r ,(, .*' *: :() *':*:'.:.*.::_'.
!\'(\\ -\1 ... \.
1:*[IF l"L .
1)
- ?. -
Inspection Surrmary Inspection Conducted January 25, 1989 (Report 50-192/89-01; 50-60?/89-01)
Areas Inspected: Routine, announced inspection of surveillance requirements and general condition of the Mark I unit; construction status, schedule update, ad reactor equipment preservation and protective storage for the Mark Tl unit.
Results: Within the areas inspected, no violations or deviations were identified. Construction has resumed following selection of a new contractor (R. L. Pender and Associates) by the licensee's bonding company. The reactor systems and components provided hy General Atomic are adequately protected and stored. Techical Specifications (TS) requirements for the Mark T unit are being properly me DETAILS Persons Contacted
- T. Bauer, Assistant Director, NETL J. Green, Construction Inspector
- Denotes individual contacted for exit interview. TRIGA Mark I Unit The NRC inspectors reviewed the procedures manual and Technical Specifications for the Mark I unit. The University has discontinued operations of this unit but continues to maintain it until the fuel can be transferred to the new unit now under final construction. The review determined that the only surveillance requirements during this condition are periodic pool water level and conductivity checks. These are being accomplished as required. The licensee is also running the area radiation monitor and the continuous air monitoring syste Except for the F" ring, a11 fue 1 elements have been removed from the core II and are temporarily suspended in the pool. Fuel transfer to the new unit is presently planned for June 1989. Procedures for handling, loading, shipping and unloading are in draft form at this time. TRIGA Mark II Unit The NRC inspectors toured thP facility to review completion status and general area conditions. Some work has restarted in the office and laboratory area. The new contractor (R. L. Pender and Associates of Miami, Florida) will resume reactor building work when final insurance arrangements are complete During the tour, it was pointed out that the manufacturer (Patterson Kelley) had shipped the pool cooling heat exchanger without cleaning the unit's internals. The manufacturer hs since completed one field cleaning with unsatisfactory results. The unit is to he recleaned before final pipe installatio Some work had started on the pool water recirculation pipe but was presently held up because of a problem identified with some of the large size valve These valves are made from epoxy coated cast iron with stainless steel internals. It was noted that the epoxy coating on the valves was chipping, raising concerns over the potential for long tenn corrosion. This is being resolved by the license The tour also included the storage and prPservation of reactor equipmen The NRC inspectors found that the skid mounted pool water purification system, core support structure, beam port plug removal/storage container, and other miscellaneous structural material were being stored in a sealed
- 4 -
trailer shippinq container. It was noted that the PVC piping for thP purification system filter had sustained damage during shipment and required repair by General Atomic (GA) prior to installatio The NRC inspertors observed that crated ractor control consoles, control equ;pment, radi,.tion monitors, ion exchange resin, radiation control assemblies and other miscellaneous equipment were stored 1n a separate, environfflf!ntally controlled buildin. It was pointed out that the refurbished transient rod control system had not been received from G One other item that has not been received from GA is the argon-41 measurement sytem.
4. Schedule Milestones Oue to construction delays, the milestone schedule dates as published tn NRC Inspection Report 50-602/RR-05 have been revised and are as follows as of January 25, 1989:
Milestones Completion Dat Actual Receive control room console October J, 1988 October 1, 19P8 and mechanical components Complete HVAC balancing February 15, 1989 f.omplete physical security elements ay 1, 19P9 Complete pool water system March 31, 1989 (1 ns ta11ation)
Complete preoperational test May l, 1989 procedures (including GA installation and test)
rnstall control room console April 15, 189 Install GA mechanical components April 1, 1989 (including purification system)
Install radiation monitoring April 15, 1989 equipment (installation by GA)
license two Senior Reactor Operators May 15, 1 f.omplete all operating procedures Complete a required by equipment irstallation 98% complete as of
,January 24, 1989
- 5 *
Receive operating license June 1. 1989 Load reactor fuel - achieve 1n1t1al June 20, 19A9 cr1t1cal1ty 5. Exit Interview The 1nspection scope and findings were discussed with th Assistant Director, NETL, et the conclusion of the inspection on January ?5, 198 The licensee did not identify as proprietary any of the material provided to, or reviewPd, by the NRC inspector.