ND-18-0807, Unit 4 - Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.6.09.08 (Index Number 650)

From kanterella
(Redirected from ML18211A622)
Jump to navigation Jump to search
Unit 4 - Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.6.09.08 (Index Number 650)
ML18211A622
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 07/25/2018
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of New Reactors
References
ND-18-0807
Download: ML18211A622 (6)


Text

Sk Southern Nuclear Michael J. Vox Regulatory Affairs Director 7825 River Road Waynesboro, GA 30830 Vogtie 3 & 4 706-848-6459 tei 410-474-8587 ceii JUL 2 5 2018 myox soutfiernco.com Docket Nos.: 52-025 52-026 ND-18-0807 10CFR 52.99(c)(3)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtie Electric Generating Plant Unit 3 and Unit 4 Notice of Uncompleted ITAAC 225-davs Prior to Initial Fuel Load Item 2.6.09.08 [Index Number 6501 Ladies and Gentlemen:

Pursuant to 10 CFR 52.99(c)(3), Southern Nuclear Operating Company hereby notifies the NRC that as of July 20, 2018, Vogtie Electric Generating Plant (VEGP) Unit 3 and Unit 4 Uncompleted Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 2.6.09.08 [Index Number 650]

has not been completed greater than 225-days prior to initial fuel load. The Enclosure describes the plan for completing this ITAAC. Southern Nuclear Operating Companywill, at a later date, provide additional notifications for ITAAC that have not been completed 225-days prior to initial fuel load.

This notification is informed by the guidance described in NEI 08-01, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215. In accordance with NEI 08-01, this notification includes ITAAC for which required inspections, tests, or analyses have not been performed or have been only partially completed. All ITAAC will be fully completed and all Section 52.99(c)(1) ITAAC Closure Notifications will be submitted to NRC to support the Commission finding that all acceptance criteria are met priorto plant operation, as required by 10 CFR 52.103(g).

This letter contains no new NRC regulatory commitments.

If there are any questions, please contact Tom Petrak at 706-848-1575.

Respectfully submitted.

Michael J. Vox Regulatory Affairs Director Vogtie 3 & 4

Enclosure:

Vogtie Electric Generating Plant (VEGP) Unit 3 & Unit 4 Completion Plan for Uncompleted ITAAC 2.6.09.08 [Index Number 650]

MJY/RAS/amw

U.S. Nuclear Regulatory Commission ND-18-0807 Page 2 of 3 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. D. A. Bost (w/o enclosures)

Mr. M. D. Meier Mr. D. H. Jones (w/o enclosures)

Mr. D. L. McKlnney Mr. M. J. Yox Mr. D. L. Fulton Mr. J. B. Klecha Mr. G. Chick Ms. A. L. Pugh Mr. A. S. Parton Mr. W. A. Sparkman Mr. C. E. Morrow Ms. K. M. Stacy Mr. M. K. Washington Ms. A. C. Chamberlain Mr. T. G. Petrak Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:

Nuclear Reaulatorv Commission Mr. W. Jones (w/o enclosures)

Ms. J. M. Heisserer Mr. C. P. Patel Mr. M. E. Ernstes Mr. G. J. Khouri Mr. T. E. Chandler Ms. S. E. Temple Ms. P. Braxton Mr. N. D. Karlovich Mr. A. J. Lerch Mr. C. J. Even Mr. F. D. Brown Mr. B. J. Kemker Ms. A. E. Rivera-Varona Mr. P. B. Donnelly Ms. N. C. Coovert Qqiethoroe Power Corporation Mr. R. B. Brinkman Municlpai Eiectric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Daiton Utilities Mr. T. Bundros

U.S. Nuclear Regulatory Commission ND-18-0807 Page 3 of 3 Westinahouse Electric Company. LLC Dr. L. Oriani (w/o enclosures)

Mr. D. 0. Durham (w/o enclosures)

Mr. M. M. Corletti Ms. L. G. Iller Mr. D. Hawkins Ms. J. Monahan Mr. J. L. Coward Ms. N. E. Deangelis Other Mr. J. E. Hesler, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, inc.

Mr. 8. Roetger, Georgia Public Service Commission Ms. 8. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Baich Bingham

U.S. Nuclear Regulatory Commission ND-18-0807 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-18-0807 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 3 & Unit 4 Completion Plan for Uncompleted ITAAC 2.6.09.08 [Index Number 650]

U.S. Nuclear Regulatory Commission ND-18-0807 Enclosure Page 2 of 3 ITAAC Statement Desion Commitment

8. Isolation zones and exterior areas within the protected area are provided with illumination to permit observation of abnormal presence or activity of persons or vehicles.

Inspections. Tests. Analvses Inspection of the illumination in the isolation zones and external areas of the protected area will be performed.

Acceptance Criteria The illumination in isolation zones and exterior areas within the protected area is 0.2 foot candles measured horizontally at ground level or, alternatively, sufficient to permit observation.

ITAAC Completion Description An inspection is performed to verify the Vogtle Electric Generating Plant (VEGP) Unit 3 [Unit 4]

isolation zones and exterior areas within the protected area are provided with illumination to permit observation of abnormal presence or activity of persons or vehicles. The inspection confirms the illumination in isolation zones and external areas within the protected area is a minimum of 0.2 foot candles measured horizontally at ground level or, alternatively, sufficientto permit observation, and satisfy the applicable illumination requirements of the VEGP Unit 3 and Unit 4 Physical Security Plan associated with 10CFR 73.55(i)(6)(ii). The VEGP Unit 3 [Unit 4]

Plant Security System ITAACs only cover the Unit 3 [Unit 4] plant security system design commitment scope.

Procedure XXX, Unit 3 [Unit 4] Isolation Zone and Protected Area Lighting System Inspection, (Reference 1 [2]) measures the illumination in isolation zones and exterior areas within the protected area. The measurements are taken horizontally at ground level with a calibrated light meter during clear weather conditions at night with no full moon. Ground level is considered to be approximately 6 inches above the ground or surface being tested.

The VEGP Unit 3 [Unit 4] isolation zones and exterior areas of the protected area are divided into grid sections. Measurement of illumination levels in each section are taken at locations determined by Procedure XXX. Procedure criteria for selecting the measurement locations in each section include points on the extreme boundary ofthe section being measured, midpoints between the outdoorsecurity lighting luminaries, corners at the intersection of exterior building walls, isolation zone corners, exterior area access doors to vital areas, and other external areas within the protected area and isolation zone areas ofapparent low light within the section.

The results of the Unit 3 [Unit 4] isolation zone and protected area lighting system inspection are documented in Inspection Report YYY, Unit 3 [Unit 4] Isolation Zone and Protected Area Lighting System Inspection Report (Reference 3 [4]) and confirm that the illumination in isolation zones and exterior areas within the protected area is a minimum of 0.2 foot candles measured horizontally at ground level or, alternatively, sufficient to permit observation of abnormal presence oractivity of persons orvehicles, utilizing low-light technologies referenced in the VEGP Unit 3 and Unit 4 Physical Security Plan.

U.S. Nuclear Regulatory Commission ND-18-0807 Enclosure Page 3 of 3 References 1 and 3 [2 and 4] are available for NRG inspection as part of the ITAAC 2.6.09.08 Completion Package (Reference 5 [6]).

List of ITAAC Findings In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company (SNC) performed a review of all ITAAC findings pertaining to the subject ITAAC and associated corrective actions. This review found that there are no relevant ITAAC findings associated with this ITAAC.

References favaiiabie for NRC inspection)

1. Procedure XXX, Unit 3 Isolation Zone and Protected Area Lighting System Inspection
2. Procedure XXX, Unit 4 Isolation Zone and Protected Area Lighting System Inspection
3. Inspection Report YYY, Unit 3 Isolation Zone and Protected Area Lighting System Inspection Report
4. Inspection Report YYY, Unit 4 Isolation Zone and Protected Area Lighting System Inspection Report
5. 2.6.09.08-U3-CP-Rev0, ITAAC Completion Package
6. 2.6.09.08-U4-CP-Rev0, ITAAC Completion Package
7. NEI 08-01, "IndustryGuideline for the ITAAC Closure Process Under 10 CFR Part 52"