ND-18-0580, Unit 4 - Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item E.3.9.09.00.01 (Index Number 873)

From kanterella
(Redirected from ML18117A349)
Jump to navigation Jump to search
Unit 4 - Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item E.3.9.09.00.01 (Index Number 873)
ML18117A349
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 04/26/2018
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of New Reactors
References
ND-18-0580
Download: ML18117A349 (6)


Text

Michael J. Yox 7825 River Road

^ Southern Nuclear Regulatory Affairs Director Vogtie 3 & 4 Waynesboro, GA 30830 706-848-6459 tei 410-474-8587 ceii myox@southernco.com APR 2 6 2018 Docket Nos.: 52-025 52-026 ND-18-0580 10 CFR 52.99(c)(3)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtie Electric Generating Plant Unit 3 and Unit 4 Notice of Uncompleted ITAAC 225-davs Prior to Initial Fuel Load Item E.3.9.09.00.01 [Index Number 8731 Ladles and Gentlemen:

Pursuant to 10 CFR 52.99(c)(3), Southern Nuclear Operating Company hereby notifies the NRC that as of April 20, 2018, Vogtie Electric Generating Plant (VEGP) Unit 3 and Unit 4 Uncompleted Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item E.9.09.00.01 [Index Number 873] has not been completed greater than 225-days prior to Initial fuel load. The Enclosure describes the plan for completing this ITAAC. Southern Nuclear Operating Company will, at a later date, provide additional notifications for ITAAC that have not been completed 225-days prior to Initial fuel load.

This notification Is Informed by the guidance described In NEI 08-01, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, which was endorsed by the NRC In Regulatory Guide 1.215. In accordance with NEI 08-01, this notification Includes ITAAC for which required Inspections, tests, or analyses have not been performed or have been only partially completed. All ITAAC will be fully completed and all Section 52.99(c)(1) ITAAC Closure Notifications will be submitted to NRC to support the Commission finding that all acceptance criteria are met priorto plant operation, as required by 10 CFR 52.103(g).

This letter contains no new NRC regulatory commitments.

If there are any questions, please contact Tom Petrak at 706-848-1575.

Respectfully submitted.

MIchaelJ. Yox \j Regulatory Affairs Director Vogtie 3 & 4

Enclosure:

Vogtie Electric Generating Plant (VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC E.3.9.09.00.01 [Index Number 873]

MJY/LBP/amw

U.S. Nuclear Regulatory Commission ND-18-0580 Page 2 of 3 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. D. A. Bost (w/o enclosures)

Mr. M. D. Rauckhorst (w/o enclosures)

Mr. M. D. Meier Mr. D. H. Jones (w/o enclosures)

Mr. D. L. McKinney Mr. M. J. Yox Mr. D. L. Fulton Mr. J. B. Klecha Mr. G. Chick Mr. F. H. Willis Ms. A. L. Pugh Mr. A. 8. Parton Mr. W. A. Sparkman Mr. C. E. Morrow Ms. K. M. Stacy Mr. M. K. Washington Mr. J. P. Redd Ms. A. C. Chamberlain Mr. D. R. Culver Mr. T. G. Petrak Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:

Nuclear Reaulatorv Commission Mr. W. Jones (w/o enclosures)

Ms. J. M. Heisserer Mr. C. P. Patel Mr. M. E. Ernstes Mr. G. J. Khouri Mr. T. E. Chandler Ms. S. E. Temple Ms. P. Braxton Mr. N. D. Karlovich Mr. A. J. Lerch Mr. C. J. Even Mr. F. D. Brown Mr. B. J. Kemker Ms. A. E. Rivera-Varona Ms. L. A. Kent Mr. P. B. Donnelly Ms. N. C. Coovert Oalethoroe Power Corporation Mr. R. B. Brinkman

U.S. Nuclear Regulatory Commission ND-18-0580 Page 3 of 3 Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. 8. M. Jackson Dalton Utilities Mr. T. Bundros Westinahouse Electric Company. LLC Dr. L. Oriani (w/o enclosures)

Mr. D. C. Durham (w/o enclosures)

Mr. M. M. Corletti Ms. L. G. Iller Mr. D. Hawkins Ms. J. Monahan Mr. J. L. Coward Ms. N. E. Deangelis Other Mr. J. E. Hesler, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, Inc.

Mr. 8. Roetger, Georgia Public Service Commission Ms. 8. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Balch Bingham

U.S. Nuclear Regulatory Commission ND-18-0580 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-18-0580 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC E.3.9.09.00.01 [Index Number 873]

U.S. Nuclear Regulatory Commission ND-18-0580 Enclosure Page 2 of 3 ITAAC Statement Program Commitment 9.1 The licensee has submitted detailed implementing procedures for its emergency plan no less than 180 days prior to fuel load.

Inspections. Tests. Analyses 9.1 An inspection of the submittal letter will be performed.

Acceptance Criteria 9.1 The licensee has submitted detailed emergency implementing procedures (EIPs) for the onsite emergency plan no less than 180 days prior to fuel load.

ITAAC Completion Description An inspection is performed to confirm a letter is transmitted to the NRC that documents submission of detailed emergency implementing procedures (EIPs) for the Vogtle Electric Generating Plant (VEGP) Units 3 and 4 onsite emergency plan no less than 180 days priorto fuel load.

The Southern Nuclear Operating Company (SNC) Standard Emergency Plan Annex for Vogtle Electric Generating Plant Units 3 and 4, Appendix D (Reference 1) identifies the emergency plan implementing procedures required to be submitted by the VEGP Units 3 and 4 to the NRC no less than 180 days prior to fuel load.

The submission of detailed EIPs for the onsite emergency plan no less than 180 days prior to fuel load is documented in submittal letters ND-XX-XXXX for Unit 3 and ND-YY-YYYY for Unit 4 (References 2 and 3, respectively).

References 2 and 3 are available for NRC inspection as part of the Unit 3 and Unit 4 ITAAC E.3.9.09.00.01 Completion Packages (References 4 and 5, respectively).

List of ITAAC Findings In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company performed a review of all ITAAC findings pertaining to the subject ITAAC and associated corrective actions. This finding review found no relevant ITAAC findings associated with this ITAAC.

U.S. Nuclear Regulatory Commission ND-18-0580 Enclosure Page 3 of 3 References (available for NRG inspection)

1. Southem Nuclear Operating Company Standard Emergency Plan Annex for Vogtle Electric Generating Plant Units 3 and 4
2. Unit 3 submittal letter ND-XX-XXXX
3. Unit 4 submittal letter ND-YY-YYYY
4. E.3.9.09.00.01-U3-CP-RevX, ITAAC Completion Package
5. E.3.9.09.00.01-U4-CP-RevX, ITAAC Completion Package
6. NEI 08-01, "Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52"