ND-18-0500, Enclosure 4 to ND-18-0500, Completion Plan for Uncompleted ITAAC 3.3.00.07d.v.b (Index Number 810)

From kanterella
(Redirected from ML18107A133)
Jump to navigation Jump to search
Enclosure 4 to ND-18-0500, Completion Plan for Uncompleted ITAAC 3.3.00.07d.v.b (Index Number 810)
ML18107A133
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 04/10/2018
From:
Southern Nuclear Operating Co
To:
Office of New Reactors
Shared Package
ML18107A128 List:
References
ND-18-0500
Download: ML18107A133 (3)


Text

U.S. Nuclear Regulatory Commission ND-18-0500 Enclosure 4 Page 1 of 3 Southern Nuclear Operating Company ND-18-0500 Enclosure 4 Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Docket No.: 52-025 & 52-026 Completion Plan for Uncompleted ITAAC 3.3.00.07d.v.b [Index Number 810]

U.S. Nuclear Regulatory Commission ND-18-0500 Enclosure 4 Page 2 of 3 ITAAC Statement Desion Commitment 7.d) Physical separation ismaintained between Class 1E divisions and between Class 1E divisions and non-Class 1E cables.

Insoections. Tests. Analvses Inspections of the as-built raceways that route Class 1E cables will be performed to confirm that the separation between raceways that route Class 1E cables of different divisions, and between raceways that route Class 1E cables and raceways that route non-Class 1E cables is consistent with the following:

v) Non-Class 1E wiring that is not separated from Class 1E orassociated wiring by the minimum separation distance or by a barrier or analyzed isconsidered as associated circuits and subject to Class 1E requirements.

Acceotance Criteria Results of the inspection will confirm that theseparation between raceways that route Class 1E cables of differentdivisions, and between raceways that route Class 1E cables and raceways that route non-Class 1E cables is consistent with the following:

v.b) For areas inside the non-radiologically controlled area of theauxiliary building, non-Class 1E wiring that is not separated from Class 1E orassociated wiring by the minimum separation distance or by a barrier or analyzed is treated as Class 1E wiring.

ITAAC Completion Description Multiple ITAAC are performed to ensure that physical separation is maintained between Class 1E divisions and between Class 1E divisions and non-Class 1E cables. In accordance with this ITAAC, non-Class 1Ewiring that is not separated from Class 1Eor associated wiring by the minimum separation distance andfor which no barrier oranalysis is provided is considered as associated circuits and subject to Class 1E requirements. The subject ITAAC requires inspections of the Class 1E and non-Class 1E raceways inside the non-radiologically controlled area ofthe auxiliary building to confirm that non-Class 1Ewiring that is not separatedfrom Class 1Eor associated wiring by the minimum separation distance or by a barrier or analyzed is considered as associated circuits and subject to Class 1E requirements. The Class 1E cables and raceways and non-Class 1E cables inside the non-radiologically controlled area of the auxiliary building are designed to beappropriately separated in accordance with APP-GW-E1-001 (Reference 1). Installation Specifications provided to the constructor identify separation criteria, consistent with the ITAAC commitment.

Class 1E electrical cables and raceways are installed in accordance with design drawings, installation specifications issued for construction and work package requirements. Completed raceway installation, in-progress cable installation, andcompleted cable terminations are inspected to ensure the separation installation specifications are satisfied. Inspections are performed in accordance with the Construction Quality Verification Program 26139-000-4MP-T81C-N7101 (Reference 2). The completed inspection records document the

U.S. Nuclear Regulatory Commission ND-18-0500 Enclosure 4 Page 3 of 3 satisfactory separation between raceways that route Class 1E cables of different divisions, and between racewaysthat route Class 1E cables and racewaysthat route non-Class 1E cables.

Cable Separation Reports XXX (References 3 and 4) identify the inspection reports associated with the raceway separation inspections and confirm that the separation between racewaysthat route Class 1E cables of different divisions, and between raceways that route Class 1E cables and raceways that route non-Class 1E cables is consistent with the following:

For areas inside the non-radiologically controlled area of the auxiliary building, non-Class 1E wiring that is not separated from Class 1E or associated wiring bythe minimum separation distance or by a barrier or analyzed is considered as associated circuits and subjectto Class 1E requirements.

The Cable Separation Reports (References 3 and 4) are available for NRC inspection as part of the Unit 3 and Unit 4ITAAC 3.3.00.07d.v.b Completion Packages (References 5 and 6, respectively).

List of ITAAC Findings In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company (SNC) performed a review of all ITAAC findings and associated corrective actions.

This review found no relevant ITAAC findings associated with this ITAAC.

References favailable for NRC inspection)

1. APP-GW-E1-001, Electrical Systems Design Criteria
2. 26139-000-4MP-T81C-N7101, Bechtel Construction Quality Verification Program
3. Unit 3 Cable Separation Report XXX
4. Unit 4 Cable Separation Report XXX
5. Unit 3 ITAAC 3.3.00.07d.v.b Completion Package
6. Unit 4 ITAAC 3.3.00.07d.v.b Completion Package
7. NEI 08-01, "Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52"