Forwards Revs 1 & 2 to Qualification Guide, Reactivity Manipulations Documentation Guide & Page from Training Procedure NC.TQ-TP.ZZ-0302, Nuclear Control Operator Training Program.
ML18106A825
Person / Time
Site: Salem, Hope Creek  PSEG icon.png
Issue date: 08/10/1998
From: Mcmahon J
Public Service Enterprise Group
To: Conte R
NRC
Shared Package
ML18106A827 List:
References
50-354-98-03, 50-354-98-3, LR-N980331, NUDOCS 9808260118
Download: ML18106A825 (2)


Text

e 1 ;; ).,

OPS~G f:"' "' 1; I" cc r: f :/' 1 J "'v

~Public ~ervice Electric and Gas Company P.O. Box 236 Hancocks Bridge, New Jersey 08038-0236  ?)~!

Nuclear Business Unit ~vJ)~

Cc:. 1)6{/° L) ~ v I ) )-<.

AUG 1 0 1999 LR-N980331 Mr. Richard J. Conte, Chief Operator Licensing and Human Performance Branch Division of Reactor Safety U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406

Dear Mr. Conte:

FOLLOW-UP TO JUNE 29, 1998 MEETING SALEM GENERATING STATION UNITS 1AND2 AND HOPE CREEK GENERATING STATION DOCKET NOS. 50-272, 50-311, AND 50-354 On June 29, 1998, Public Service Electric and Gas (PSE&G) met with the NRC to discuss concerns identified by the NRC in "Hope Creek Examination Report 50-354/98-03 (OL) Supplement" dated June 16, 1998..

As discussed during the meeting, PSE&G is forwarding the enclosed copies of the Salem and Hope Creek qualification guides entitled, "Reactivity Manipulations Documentation Guide," for your review. As stated at the meeting, PSE&G will be providing copies of the completed qualification guides for the current license classes with the NRC-Form 398 License Applications as documentation for the completion of the required significant control manipulations.

Also enclosed is a page from training procedure, NC.TQ-TP.ZZ-0302, "Nuclear Control Operator (NCO) Training Program," concerning the amount of time that an initial license candidate must spend on-shift in training. The current procedure .clearly identifies that the trainee will spend a minimum of 13 weeks on-shift comprised of a minimum of 520 hours0.00602 days <br />0.144 hours <br />8.597884e-4 weeks <br />1.9786e-4 months <br />. The time spent on-shift is documented on the 'Qualification Checkout Card" (copy enclosed).

J

--* L 9808260118 980810 PDR ADOCK 05000272 V PDR

.95-2168 REV. 6194

Document Control Desk 2 AUG 10 1998

.LR-N9,80331 If you have any questions concerning the above information, please contact Brian Thomas at 609-339-2022.

Sincerely,

~!f:!

Director- QA/Nuc. Training/EP Enclosures (4)

C .

  • Mr. H.J. Miller, Administrator- Region I USNRC Region I 475 Allendale Road King of Prussia, PA 19406 Mr. P. Milano, Licensing Project Manager - Salem U. S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Mail Stop 14E21 Rockville, MD 20852 Mr. R. Ennis, Licensing Project Manager - Hope Creek U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Mail Step 14E21 Rockville, MD 20852 Mr. S. Morris (X24)

USNRC Senior Resident Inspector Mr. S. Pindale (X24)

USNRC Senior Resident Inspector Mr. K. Tosch, Manager, IV Bureau of Nuclear Engineering P.O. Box 415 .

Trenton, NJ 08625