ND-18-0489, Unit 4, Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.07c.ii.a (Index Number 797)

From kanterella
(Redirected from ML18100A030)
Jump to navigation Jump to search
Unit 4, Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.07c.ii.a (Index Number 797)
ML18100A030
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 04/09/2018
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of New Reactors
References
ITAAC 3.3.00.07c.ii.a, ND-18-0489
Download: ML18100A030 (7)


Text

^

Southern Nuclear APR 0 9 2018 Docket Nos.52-025 52-026 Michael J. Yox Regulatory AffairsDirector Vogtle 3 &4 7825 River Road Waynesboro, GA 30830 706-848-6459 tei 410-474-8587 ceii myox@southernco.com ND-18-0489 10CFR 52.99(c)(3)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 and Unit 4 Notice of Uncomoleted ITAAC 225-davs Prior to Initial Fuel Load Item 3.3.00.07c.ii.a [Index Number 797]

Ladies and Gentlemen:

Pursuant to 10 CFR 52.99(c)(3), Southern Nuclear Operating Company hereby notifies the NRC thatas of April 5, 2018, Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Uncompleted Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 3.3.00.07c.ii.a [Index Number 797] has notbeen completed greaterthan 225-days prior to initial fuel load. The Enclosure describesthe plan for completing this ITAAC. Southern Nuclear Operating Company will, at a later date, provide additional notifications for ITAAC that have not beencompleted 225-days prior to initial fuel load.

This notification is informed bythe guidancedescribed in NEI 08-01, Industry Guideline forthe ITAACClosure Process Under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215. In accordance with NEI 08-01, this notification includes ITAAC for which required inspections, tests, oranalyses have not been performed orhave beenonly partially completed. All ITAAC will be fully completed and all Section 52.99(c)(1) ITAAC Closure Notifications will be submitted to NRC to support the Commission finding that all acceptance criteria are met prior to plant operation, as required by 10 CFR 52.103(g).

This letter contains no new NRC regulatory commitments.

If there are any questions, please contact Tom Petrak at 706-848-1575.

Respectfully submitted, l-Michael J. Yox Regulatory Affairs Director Vogtle 3 &4

Enclosure:

Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 3.3.00.07c.ii.a[Index Number797]

MJY/LBP/amw

U.S. Nuclear Regulatory Commission ND-18-0489 Page 2 of 3 To:

Southern Nuclear Operating Company/ Georgia Power Company M

M M

M M

M M

M M

M D. A. Bost (w/o enclosures)

M. D. Rauckhorst (w/o enclosures)

M. D. Meier D. H. Jones (w/o enclosures)

D. L. McKinney M. J. Yox D. L. Fulton

. J. B. Klecha G. Chick F. H. Willis Ms. A. L. Pugh

. A. 8. Parton

. W. A. Sparkman C. E. Morrow Ms. K. M. Stacy

. M. K. Washington

. J. P. Redd Ms. A. C. Chamberlain

. D. R. Culver

. T. G. Petrak Document Services RTYPE: VND.LI.L06 File AR.01.02.06 M

M M

M M

M M

cc:

Nuclear Reouiatorv Commission Mr. W. Jones (w/o enclosures)

Ms. J. M. Heisserer Mr. C. P. Patel Mr. M. E. Ernstes Mr. G. J. Khouri Mr. T. E. Chandler Ms. S. E. Temple Ms. P. Braxton Mr. N. D. Karlovich Mr. A. J. Lerch Mr. C. J. Even Mr. F. D. Brown Mr. B. J. Kemker Ms. A. E. Rivera-Varona Ms. L. A. Kent Mr. P. B. Donnelly Ms. N. C. Coovert Oalethoroe Power Corporation Mr. R. B. Brinkman

U.S. Nuclear Regulatory Commission ND-18-0489 Page 3 of 3 Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. 8. M. Jackson Dalton Utilities Mr. T. Bundros Westinahouse Electric Company. LLC Dr. L. Orlani (w/o enclosures)

Mr. D. C. Durham (w/o enclosures)

Mr. M. M. CorlettI Ms. L. G. Iller Mr. D. Hawkins Ms. J. Monahan Mr. J. L. Coward Ms. N. E. Deangelis Other Mr.J. E. Hesler, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., CDS Associates, inc.

Mr. 8. Roetger, Georgia PublicSen/ice Commission Ms. 8. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Balch Bingham

U.S. Nuclear Regulatory Commission ND-18-0489 Enclosure Page 1 of 4 Southern Nuclear Operating Company ND-18-0489 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 3.3.00.07c.ii.a [Index Number 797]

U.S. Nuclear Regulatory Commission ND-18-0489 Enclosure Page 2 of 4 ITAAC Statement Desion Commitment 7.c)Separation is maintained between Class 1Edivisions in accordance with the fire areas as identified in Table 3.3-3.

inspections/Tests/Anaivses ii) inspections ofthe as-builtfire barriers between the fire areas identified inTable 3.3-3 will be conducted.

Acceptance Criteria ii.a) Results of the inspection will confirm that fire barriers exist between fire areas identified in Table 3.3-3 inside the non-radiologically controlled area of the auxiliary building.

ITAAC Completion Description Multiple ITAAC are performed to demonstrate that separation is maintained between Class 1E divisions in accordance with the fire areas as identified in Table 3.3-3. The subject ITAAC requires inspections to be conducted of the as-built fire barriers between the fire areas identified in Table 3.3-3. The Class 1E divisions in Nuclear Island Fire Areas are described in Combined Operating License (COL) Appendix C Table 3.3-3 (Attachment A). The fire barriers between fire areas identified in Table 3.3-3 inside the non-radiologically controlled area of the auxiliary building are designed in accordance with APP-GW-E1-001 (Reference 1). Installation specifications provided to the constructor identify the fire barriers, consistent with the ITAAC commitment.

Fire barriers between the fire areas identified in the table are installed in accordance with design drawings, installation specifications issued for construction and work package requirements.

Completed fire barriers are inspected to ensure the fire barrier criteria in the installation specifications are satisfied. Inspections are performed in accordance with the Construction Quality Verification Program 26139-000-4MP-T81C-N7101 (Reference 2). The completed inspection records document that satisfactory fire barriers exist between fire areas identified in the table inside the non-radiologically controlled area of the auxiliary building.

Fire Barrier Reports (References 3 and 4) identify the inspection reports associated with the fire barrier inspections and confirm that fire barriers exist between fire areas identified in Table 3.3-3 inside the non-radiologically controlled area of the auxiliary building.

The Fire Barrier Reports (References 3 and 4) are available for NRC inspection as part of the Unit 3 and Unit 4 ITAAC Completion Packages (References 5 and 6, respectively).

List of ITAAC Findings In accordance with plant procedures for ITAAC completion. Southern Nuclear Operating Company (SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC.

U.S. Nuclear Regulatory Commission ND-18-0489 Enclosure Page 3 of 4 References ^available for NRC inspection)

1. APP-GW-E1 -001, Electrical Systems Design Criteria 2.

26139-000-4MP-T81C-N7101, Construction Quality Verification Program 3.

Unit 3 Fire Barrier Report XXX 4.

Unit 4 Fire Barrier Report XXX 5.

Unit 3 ITAAC 3.3.00.07c.ii.a Completion Package 6.

Unit 4 ITAAC 3.3.00.07c.ii.a Completion Package

7. NEI 08-01, "Industry Guideline for the ITAAC Closure Process Under 10CFR Part52"

U.S. Nuclear Regulatory Commission ND-18-0489 Enclosure Page 4 of 4 Attachment A Class 1E Divisions in Nuclear Island Fire Areas*

Fire Area Number Auxiliary Building Non-Radioiogically Controlled 1200 AF 03 1201 AF02 1201 AF03 1201 AF04 1201 AF05 1201 AF06 1202 AF 03 1202 AF 04 1220 AF01 1220 AF02 1230 AF 01 1230 AF 02 1240 AF 01 1242 AF 02 Notes:

  • Excerpt from COL Appendix C Table 3.3-3