MONTHYEARND-24-0103, Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests2024-04-26026 April 2024 Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests ND-24-0114, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-04-0101 April 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-24-0046, (Vegp), Unit 3, Condition Prohibited by Technical Specification Limiting Condition of Operation 3.1.6 Control Bank Overlap Limits Exceeded Due to Inadequate Procedure Guidance2024-03-18018 March 2024 (Vegp), Unit 3, Condition Prohibited by Technical Specification Limiting Condition of Operation 3.1.6 Control Bank Overlap Limits Exceeded Due to Inadequate Procedure Guidance ND-24-0059, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-03-0404 March 2024 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0693, Combined License (COL) License Condition 2.D.(4)(d) Completion of Initial Criticality and Low-Power Tests2024-02-15015 February 2024 Combined License (COL) License Condition 2.D.(4)(d) Completion of Initial Criticality and Low-Power Tests ND-23-0690, Combined License (COL) License Condition 2.D.(3)(e) Completion of Pre-Critical Tests2024-02-0808 February 2024 Combined License (COL) License Condition 2.D.(3)(e) Completion of Pre-Critical Tests ND-24-0019, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-02-0101 February 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0912, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-01-0202 January 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0881, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-12-0404 December 2023 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0817, Report of UFSAR Chapter 14 Changes to the Initial Test Program in Accordance with License Condition 2.D.(7)(a)2023-11-17017 November 2023 Report of UFSAR Chapter 14 Changes to the Initial Test Program in Accordance with License Condition 2.D.(7)(a) ND-23-0823, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-11-0303 November 2023 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0723, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-10-0404 October 2023 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0697, Submittal of Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-09-0505 September 2023 Submittal of Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0669, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-08-0707 August 2023 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0205, Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests2023-07-28028 July 2023 Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests ND-23-0608, ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72) ND-23-0618, Resubmittal of ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.07c.ii.a (Index Number 797)2023-07-20020 July 2023 Resubmittal of ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.07c.ii.a (Index Number 797) ND-23-0609, Notification of Completion of All ITAAC2023-07-20020 July 2023 Notification of Completion of All ITAAC ND-23-0607, ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13) ND-22-0796, ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.08 (Index Number 813)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.08 (Index Number 813) ND-23-0459, ITAAC Closure Notification on Completion of ITAAC 2.6.01.04d (Index Number 587)2023-07-19019 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.01.04d (Index Number 587) ND-23-0162, ITAAC Closure Notification on Completion of ITAAC 2.2.03.05a.i (Index Number 165)2023-07-19019 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.05a.i (Index Number 165) ND-23-0575, ITAAC Closure Notification on Completion of ITAAC 2.6.01.04e (Index Number 588)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.01.04e (Index Number 588) ND-23-0439, ITAAC Closure Notification on Completion of ITAAC 2.2.05.07a.i (Index Number 265)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.05.07a.i (Index Number 265) ND-23-0552, Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Unit 4, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02c (Index Number 624)2023-07-18018 July 2023 Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Unit 4, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02c (Index Number 624) ND-23-0483, ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4) ND-23-0586, ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159)2023-07-17017 July 2023 ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159) ND-23-0610, ITAAC Closure Notification on Completion of ITAAC Item 2.6.03.04c (Index Number 603)2023-07-17017 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.6.03.04c (Index Number 603) ND-23-0573, ITAAC Closure Notification on Completion of 2.4.02.02a (Index Number 497)2023-07-16016 July 2023 ITAAC Closure Notification on Completion of 2.4.02.02a (Index Number 497) ND-23-0406, ITAAC Closure Notification on Completion of ITAAC Item 2.4.02.02b (Index Number 498)2023-07-16016 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.4.02.02b (Index Number 498) ND-22-0816, ITAAC Closure Notification of Completion of ITAAC 2.1.02.05a (Index Number 19)2023-07-15015 July 2023 ITAAC Closure Notification of Completion of ITAAC 2.1.02.05a (Index Number 19) ND-23-0603, ITAAC Closure Notification on Completion of ITAAC Item 3.5.00.06 (Index Number 831)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 3.5.00.06 (Index Number 831) ND-23-0446, ITAAC Closure Notification on Completion of ITAAC 2.2.04.12a.iii (Index Number 250)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.04.12a.iii (Index Number 250) ND-23-0594, ITAAC Closure Notification on Completion of ITAAC 2.6.05.02.ii (Index Number 629)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.05.02.ii (Index Number 629) ND-23-0601, ITAAC Closure Notification on Completion of ITAAC Item 2.7.05.02.i (Index Number 719)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.7.05.02.i (Index Number 719) ND-23-0606, ITAAC Closure Notification on Completion of ITAAC 2.5.04.02.i (Index Number 557)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.5.04.02.i (Index Number 557) ND-23-0499, ITAAC Closure Notification on Completion of ITAAC 2.7.01.14 (Index Number 700)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.01.14 (Index Number 700) ND-23-0476, ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355) ND-23-0588, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78) ND-23-0121, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.07 (Index Number 667)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.07 (Index Number 667) ND-23-0122, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.08a (Index Number 668)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.08a (Index Number 668) ND-23-0597, ITAAC Closure Notification on Completion of ITAAC 2.5.02.06a.ii (Index Number 530)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.5.02.06a.ii (Index Number 530) ND-23-0002, ITAAC Closure Notification on Completion of ITAAC 2.2.05.07c (Index Number 270)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.05.07c (Index Number 270) ND-23-0543, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02a (Index Number 622)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02a (Index Number 622) ND-23-0394, ITAAC Closure Notification on Completion of ITAAC 2.7.02.03a (Index Number 703)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.02.03a (Index Number 703) ND-23-0461, ITAAC Closure Notification on Completion of ITAAC 2.6.09.13a (Index Number 652)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.09.13a (Index Number 652) ND-22-0980, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.06.i (Index Number 75)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.06.i (Index Number 75) ND-23-0111, ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646) ND-23-0587, ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595) ND-23-0589, ITAAC Closure Notification on Completion of ITAAC 2.6.03.04a (Index Number 601)2023-07-12012 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.03.04a (Index Number 601) 2024-04-26
[Table view] Category:Response to Request for Additional Information (RAI)
MONTHYEARNL-24-0392, Response to Requests for Additional Information Related to Proposed Alternative GEN-ISI-AL T-2024-0022024-10-28028 October 2024 Response to Requests for Additional Information Related to Proposed Alternative GEN-ISI-AL T-2024-002 NL-24-0386, License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Air Storage Tanks Response to Request for Additional Information2024-10-28028 October 2024 License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Air Storage Tanks Response to Request for Additional Information NL-24-0299, Exemption Request: Final Safety Analysis Report Update Schedule, Response to Request for Additional Information2024-08-14014 August 2024 Exemption Request: Final Safety Analysis Report Update Schedule, Response to Request for Additional Information NL-24-0194, Revised Request for Relief and Alternative Requirements for Squib Valves First Test Interval (V34-IST-ALT-03-R1)2024-05-0707 May 2024 Revised Request for Relief and Alternative Requirements for Squib Valves First Test Interval (V34-IST-ALT-03-R1) NL-24-0170, Responses to Second Round NRC Request for Additional Information for Refueling Outage 1 R24 Steam Generator Tube Inspection Report2024-04-25025 April 2024 Responses to Second Round NRC Request for Additional Information for Refueling Outage 1 R24 Steam Generator Tube Inspection Report NL-24-0042, Response to Request for Additional Information Exemption Requests for Physical Barriers2024-02-13013 February 2024 Response to Request for Additional Information Exemption Requests for Physical Barriers NL-24-0045, Supplement to Response to Requests for Additional Information for Proposed Alternative ALT-VR-022024-02-0808 February 2024 Supplement to Response to Requests for Additional Information for Proposed Alternative ALT-VR-02 NL-24-0033, Response to Question for Withholding Information from Public Disclosure Exemption Requests for Physical Barriers2024-02-0505 February 2024 Response to Question for Withholding Information from Public Disclosure Exemption Requests for Physical Barriers NL-24-0020, Plan, Unit 1 Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report2024-01-22022 January 2024 Plan, Unit 1 Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report NL-23-0827, Response to Requests for Additional Information for a License Amendment Request and a Proposed Alternative Related to TS 3.4.142023-11-17017 November 2023 Response to Requests for Additional Information for a License Amendment Request and a Proposed Alternative Related to TS 3.4.14 NL-23-0750, Response to Second Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the Colr2023-10-0404 October 2023 Response to Second Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the Colr NL-23-0695, Response to Round 2 Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters – Operating, Completion Time Extension (LAR-22-002S2)2023-08-31031 August 2023 Response to Round 2 Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters – Operating, Completion Time Extension (LAR-22-002S2) NL-23-0658, Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal2023-08-11011 August 2023 Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal NL-23-0670, Response to Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-144832023-08-11011 August 2023 Response to Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-14483 NL-23-0339, Response to Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters - Operating, Completion Time Extension (LAR-22-002S1)2023-06-13013 June 2023 Response to Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters - Operating, Completion Time Extension (LAR-22-002S1) NL-23-0467, Response to Request for Additional Information Regarding License Amendment Request: Timing of Unit 4 Technical Specifications Effectiveness Prior to Initial Criticality (LAR-23-005S1)2023-06-0909 June 2023 Response to Request for Additional Information Regarding License Amendment Request: Timing of Unit 4 Technical Specifications Effectiveness Prior to Initial Criticality (LAR-23-005S1) NL-23-0196, Response to Request for Additional Information Regarding License Amendment Request for Alternative Source Term, TSTF-51, TSTF-471, and TSTF-4902023-03-24024 March 2023 Response to Request for Additional Information Regarding License Amendment Request for Alternative Source Term, TSTF-51, TSTF-471, and TSTF-490 NL-23-0010, Response to Request for Additional Information Regarding License Amendment Request for Alternative Source Term, TSTF-51, TSTF-471, and TSTF-4902023-02-0606 February 2023 Response to Request for Additional Information Regarding License Amendment Request for Alternative Source Term, TSTF-51, TSTF-471, and TSTF-490 NL-23-0013, Response to Request for Additional Information Related to 10CFR 50.75 Decommissioning Funding Assurance Requirements2023-01-30030 January 2023 Response to Request for Additional Information Related to 10CFR 50.75 Decommissioning Funding Assurance Requirements NL-23-0068, Responses to NRC Request for Additional Information Related to the Refueling Outage 2R22 Steam Generator Tube Inspection Report2023-01-27027 January 2023 Responses to NRC Request for Additional Information Related to the Refueling Outage 2R22 Steam Generator Tube Inspection Report NL-23-0012, Post-Audit Supplement to License Amendment Request and Exemptions to Allow Use of Lead Test Assemblies for Accident-Tolerant Fuel2023-01-20020 January 2023 Post-Audit Supplement to License Amendment Request and Exemptions to Allow Use of Lead Test Assemblies for Accident-Tolerant Fuel NL-22-0609, Response to NRC Requests for Information License Amendment Request and Exemptions to Allow Use of Lead Test Assemblies for Accident-Tolerant Fuel2022-09-13013 September 2022 Response to NRC Requests for Information License Amendment Request and Exemptions to Allow Use of Lead Test Assemblies for Accident-Tolerant Fuel NL-22-0549, Responses to NRC Request for Additional Information for Refueling Outage 1R23 Steam Generator Tube Inspection Report2022-07-19019 July 2022 Responses to NRC Request for Additional Information for Refueling Outage 1R23 Steam Generator Tube Inspection Report ND-22-0328, Enclosuvogtle Electric Generating Plant, Units 3 & 4 - Fukushima Response NEI 12-01 On-Shift Staffing Analysis Phase 2 Report, Revision 3.0, Standard Emergency Plan Annex, Revision 6.02022-06-29029 June 2022 Enclosuvogtle Electric Generating Plant, Units 3 & 4 - Fukushima Response NEI 12-01 On-Shift Staffing Analysis Phase 2 Report, Revision 3.0, Standard Emergency Plan Annex, Revision 6.0 NL-22-0055, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.7.2 Limiting Condition for Operation to Remove One Main Steam Isolation Valve System2022-02-28028 February 2022 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.7.2 Limiting Condition for Operation to Remove One Main Steam Isolation Valve System NL-21-1015, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.7.2 Limiting Condition for Operation to Remove One Main Steam Isolation Valve System2022-01-13013 January 2022 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.7.2 Limiting Condition for Operation to Remove One Main Steam Isolation Valve System ND-21-0618, Response to Request for Additional Information Regarding Request for Alternative: Alternative Requirements for ASME Section Ill Remediation of Containment Vessel Unistrut Welding (VEGP 3-ALT-16)2021-07-0202 July 2021 Response to Request for Additional Information Regarding Request for Alternative: Alternative Requirements for ASME Section Ill Remediation of Containment Vessel Unistrut Welding (VEGP 3-ALT-16) NL-21-0208, Response to Request for Additional Information Related to Refueling Outage 1R22 Steam Generator Tube Inspection Report2021-03-0202 March 2021 Response to Request for Additional Information Related to Refueling Outage 1R22 Steam Generator Tube Inspection Report NL-20-1417, Vogltle, Units 1 and 2, Response to Request for Additional Information Regarding Risk-Informed Resolution to GSI-1912020-12-17017 December 2020 Vogltle, Units 1 and 2, Response to Request for Additional Information Regarding Risk-Informed Resolution to GSI-191 NL-20-1312, Response to Request for Additional Information Related to Proposed Inservice Inspection Alternative VEGP-ISI-ALT-04-04 Version 2.02020-11-23023 November 2020 Response to Request for Additional Information Related to Proposed Inservice Inspection Alternative VEGP-ISI-ALT-04-04 Version 2.0 NL-20-1273, Response to NRC Requests for Information License Amendment Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for2020-11-20020 November 2020 Response to NRC Requests for Information License Amendment Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for ND-20-1005, Supplement to Request for License Amendment: Vacuum Relief Valve Technical Specification Changes (LAR-20-005S1)2020-09-18018 September 2020 Supplement to Request for License Amendment: Vacuum Relief Valve Technical Specification Changes (LAR-20-005S1) NL-20-0640, Response to Request for Additional Information for Exemption Request2020-05-27027 May 2020 Response to Request for Additional Information for Exemption Request ND-19-1097, Response to Request for Additional Information - LAR-19-013R12019-11-0101 November 2019 Response to Request for Additional Information - LAR-19-013R1 NL-19-1183, Response to Request for Additional Information Regarding End State Revision from Hot Shutdown to Cold Shutdown2019-10-17017 October 2019 Response to Request for Additional Information Regarding End State Revision from Hot Shutdown to Cold Shutdown ND-19-1023, Enclosure 7 - Response to Draft Request for Additional Information (LAR-19-005R1)2019-10-10010 October 2019 Enclosure 7 - Response to Draft Request for Additional Information (LAR-19-005R1) ND-19-1129, Supplement to the Request for License Amendment Regarding Protection and Safety Monitoring System Surveillance Requirement Reduction Technical Specification ...2019-10-0707 October 2019 Supplement to the Request for License Amendment Regarding Protection and Safety Monitoring System Surveillance Requirement Reduction Technical Specification ... ND-19-1177, Supplement to Request for License Amendment and Exemption: Addition of In-Containment Refueling Water Storage Tank to Radiation Analyses (LAR-19-003S1)2019-10-0303 October 2019 Supplement to Request for License Amendment and Exemption: Addition of In-Containment Refueling Water Storage Tank to Radiation Analyses (LAR-19-003S1) NL-19-0709, Core Operating Limits Report, Cycle 21, Version 1, SNC Response to NRC Request for Additional Information2019-06-17017 June 2019 Core Operating Limits Report, Cycle 21, Version 1, SNC Response to NRC Request for Additional Information NL-19-0498, License Amendment Request for Technical Specification Improvement to Revise Actions for One Steam Supply to Turbine Driven Auxiliary Feedwater Pump Inoperable SNC Response to NRC Request for ...2019-04-30030 April 2019 License Amendment Request for Technical Specification Improvement to Revise Actions for One Steam Supply to Turbine Driven Auxiliary Feedwater Pump Inoperable SNC Response to NRC Request for ... ND-19-0289, Enclosure 1 - Revised Response to Request for Additional Information Question 1b Related to Request for Exemption from Operator Written Examination and Operating Test2019-04-16016 April 2019 Enclosure 1 - Revised Response to Request for Additional Information Question 1b Related to Request for Exemption from Operator Written Examination and Operating Test ND-19-0178, Supplement to Request for Exemption: 10 CFR Part 26 Visitor Access Requirements (Supplement 1)2019-03-0808 March 2019 Supplement to Request for Exemption: 10 CFR Part 26 Visitor Access Requirements (Supplement 1) ND-19-0216, Response to Request for Additional Information Related to Request for Exemption from Operator Written Examination and Operating Test2019-03-0404 March 2019 Response to Request for Additional Information Related to Request for Exemption from Operator Written Examination and Operating Test NL-18-1514, Response to Request for Information Regarding License Amendment Request to Revise Technical Specification 5.2.2.g and Update Emergency Plan Minimum On-Shift.2019-01-31031 January 2019 Response to Request for Information Regarding License Amendment Request to Revise Technical Specification 5.2.2.g and Update Emergency Plan Minimum On-Shift. ND-19-0007, Supplement to Request for Alternative: Preservice and Inservice Inspection Requirements for Specific Valve-to-Pipe Welds (VEGP 3&4-PSI/ISI-ALT-06S1)2019-01-28028 January 2019 Supplement to Request for Alternative: Preservice and Inservice Inspection Requirements for Specific Valve-to-Pipe Welds (VEGP 3&4-PSI/ISI-ALT-06S1) ND-18-1439, Revised Request for License Amendment: Technical Specification Changes for Spent Fuel Pool Level - Low 2 and In-containment Refueling Water Storage Tank (IRWST) Wide Range Level - Low Operability (LAR-18-017R1)2018-12-0303 December 2018 Revised Request for License Amendment: Technical Specification Changes for Spent Fuel Pool Level - Low 2 and In-containment Refueling Water Storage Tank (IRWST) Wide Range Level - Low Operability (LAR-18-017R1) NL-18-1181, Relief Requests VEGP-ISI-RR-05 and VEGP-ISI-RR-06, SNC Response to NRC Request for Additional Information2018-10-17017 October 2018 Relief Requests VEGP-ISI-RR-05 and VEGP-ISI-RR-06, SNC Response to NRC Request for Additional Information ND-18-1058, Supplement to Request for License Amendment and Exemption: Containment Pressure Analysis (LAR-17-043S1)2018-09-28028 September 2018 Supplement to Request for License Amendment and Exemption: Containment Pressure Analysis (LAR-17-043S1) NL-18-1130, Units 1 and 2 - Relief Request VEGP-ISI-RR-03: SNC Response to NRC Request for Additional Information2018-09-26026 September 2018 Units 1 and 2 - Relief Request VEGP-ISI-RR-03: SNC Response to NRC Request for Additional Information NL-18-1179, Response to NRC Request for Additional Information Tornado Missile Risk Evaluator SNC Supplemental2018-09-14014 September 2018 Response to NRC Request for Additional Information Tornado Missile Risk Evaluator SNC Supplemental 2024-08-14
[Table view] |
Text
B. H. Whitley Southern Nuclear Director Operating Company, Inc.
Regulatory Affairs 42 Inverness Center Parkway Birmingham, AL 35242 Tel 205.992.7079 Fax 205.992.5296 March 23, 2018 Docket Nos.: 52-025 ND-18-0364 52-026 10 CFR 50.90 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Units 3 and 4 Supplement to Request for License Amendment:
Technical Specification Updates for Reactivity Controls and other Miscellaneous Changes (LAR-17-024S2)
Ladies and Gentlemen:
Pursuant to 10 CFR 52.98(c) and in accordance with 10 CFR 50.90, Southern Nuclear Operating Company (SNC) previously requested an amendment to the combined licenses (COLs) for Vogtle Electric Generating Plant (VEGP) Units 3 and 4 (License Numbers NPF-91 and NPF-92, respectively). The requested amendment proposes to depart from approved COL Appendix A, Technical Specifications.
SNC originally submitted this request by SNC letter ND-17-1279, dated July 28, 2017 [ADAMS Accession No. ML17209A755] and supplemented by SNC letter ND-18-0058, dated January 23, 2018 [ADAMS Accession No. ML18023A440].
Enclosures 1 through 3 were provided with the original LAR and Enclosures 4 and 5 were provided with the first LAR supplement. Enclosure 6 provides responses to NRC Staff requests for additional information dated February 23, 2018 [ADAMS Accession No. ML18054B559]. provides the applicable revised markups depicting the requested change to the licensing basis documents requiring NRC staff approval. provides the applicable revised conforming Technical Specifications Bases changes for information only.
The supplemental information provided in this LAR supplement does not expand the scope of the request, or alter the conclusions of the Significant Hazards Consideration Determination or Environmental Considerations submitted in LAR-17-024.
This letter contains no regulatory commitments. This letter has been reviewed and determined not to contain security related information.
U.S. Nuclear Regulatory Commission ND-18-0364 Page 2 of4 SNC now requests NRC staff review and approval of the license amendment by April 23, 2018, to support Operator training updates. Delayed approval of this license amendment could result in a delay in Operator training updates. SNC expects to implement the proposed amendment within thirty days of approval.
In accordance with 10 CFR 50.91, SNC is notifying the State of Georgia of this LAR supplement by transmitting a copy of this letter and its enclosures to the designated State Official.
Should you have any questions, please contact Mr. Ryan D. Henderson at (205) 992-6426.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 23rd day of March 2018.
Respectfully submitted, Brian H. Whitley Director, Regulatory Affairs Southern Nuclear Operating Company Enclosures 1)- 3) (previously submitted with the original LAR, LAR-17-024, in SNC letter ND-17-1279) 4)- 5) (previously submitted as supplemental information with LAR-17-024S1 in SNC letter ND-18-0058)
- 6) Vogtle Electric Generating Plant (VEGP) Units 3 and 4 - Response to NRC Request for Additional Information Regarding the LAR-17 -024 Review (LAR-17-024S2)
- 7) Vogtle Electric Generating Plant (VEGP) Units 3 and 4 - Supplement to Proposed Changes to Licensing Basis Documents (LAR-17 -024S2)
- 8) Vogtle Electric Generating Plant (VEGP) Units 3 and 4 - Supplement to Conforming Technical Specifications Bases Changes (For Information Only)
(LAR-17 -024S2)
U.S. Nuclear Regulatory Commission ND-18-0364 Page 3 of 4 cc:
Southern Nuclear Operating Company / Georgia Power Company Mr. S. E. Kuczynski (w/o enclosures)
Mr. M. D. Rauckhorst Mr. D. G. Bost (w/o enclosures)
Mr. M. D. Meier (w/o enclosures)
Mr. D. H. Jones (w/o enclosures)
Mr. J. B. Klecha Mr. G. Chick Mr. D. L. McKinney (w/o enclosures)
Mr. T. W. Yelverton (w/o enclosures)
Mr. B. H. Whitley Ms. C. A. Gayheart Mr. C. R. Pierce Ms. A. G. Aughtman Mr. D. L. Fulton Mr. M. J. Yox Mr. J. Tupik Mr. W. A. Sparkman Ms. A. C. Chamberlain Ms. A. L. Pugh Mr. F. J. Redwanz Document Services RTYPE: VND.LI.L00 File AR.01.02.06 Nuclear Regulatory Commission Mr. W. Jones (w/o enclosures)
Ms. J. Dixon-Herrity Mr. C. Patel Ms. J. M. Heisserer Mr. B. Kemker Mr. G. Khouri Ms. S. Temple Mr. F. Brown Mr. T.E. Chandler Ms. P. Braxton Mr. T. Brimfield Mr. C. J. Even Mr. A. Lerch State of Georgia Mr. R. Dunn
U.S. Nuclear Regulatory Commission ND-18-0364 Page 4 of 4 Oglethorpe Power Corporation Mr. M. W. Price Mr. K. T. Haynes Ms. A. Whaley Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Dalton Utilities Mr. T. Bundros Westinghouse Electric Company, LLC Mr. L. Oriani (w/o enclosures)
Mr. G. Koucheravy (w/o enclosures)
Mr. M. Corletti Mr. M. L. Clyde Ms. L. Iller Mr. D. Hawkins Mr. J. Coward Other Mr. S. W. Kline, Bechtel Power Corporation Ms. L. A. Matis, Tetra Tech NUS, Inc.
Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, Inc.
Mr. S. Roetger, Georgia Public Service Commission Ms. S. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. S. Blanton, Balch Bingham Mr. R. Grumbir, APOG NDDocumentinBox@duke-energy.com, Duke Energy Mr. S. Franzone, Florida Power & Light
Southern Nuclear Operating Company ND-18-0364 Enclosure 6 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Response to NRC Request for Additional Information Regarding the LAR-17-024 Review (LAR-17-024S2)
(This Enclosure consists of 5 pages, including this cover page.)
ND-18-0364 Response to NRC Request for Additional Information Regarding the LAR-17-024 Review (LAR-17-024S2)
Question 1:
The applicable criteria for reactivity and power distribution design requirements are found in 10 CFR 50, Appendix A, General Design Criterion (GDC) 10, Reactor Design, GDC 26, Reactivity Control System Redundancy and Protection, and 10 CFR 50.46, Acceptance Criteria for Emergency Core Cooling Systems for Light Water Nuclear Power Plants. Vogtle LAR-17-024 on pages 5 and 7 of Enclosure 1 proposes to remove the Axial Offset (AO) control bank rod cluster control assemblies (RCCAs) from Surveillance Requirement (SR) 3.1.4.2 for verification of rod freedom of movement. The rationale for this change is given on page 7 of Enclosure 1 stating:
Moving the AO control bank will significantly and inappropriately perturb the power distribution.
While the technical basis for SR 3.1.4.2 provided on page 6 of Enclosure 3 states that [m]oving each RCCA by 10 steps will not cause radial or axial power tilts, or oscillations, to occur, no technical basis revision is being proposed to state movement of the AO control bank RCCAs would cause a perturbation to the power distribution. Additionally, while the justification on page 7 of Enclosure 1 states that several steps of motion of the AO control bank RCCAs are expected during normal operations, several steps is not defined as being in line with the surveillance requirement of rod movement greater than or equal to 10 steps in either direction.
Additionally, in Section 7.7.1.1.2, Axial Offset Control, of Revision 6 of the Vogtle Updated Final Safety Analysis Report (UFSAR), it states, in part, To minimize the potential for interactions between the power and axial offset rod control subsystems, the power control subsystem takes precedence. This statement coupled with the statement made in Section 7.7.1.2, Rod Control System, that states, in part, For axial offset control, the rod speed demand signals are set to a fixed constant speed of 5 inches per minute (8 steps per minute). Therefore, the staff understands the power control subsystem takes priority over the AO rods such that the movement of the AO rods would be minimized when compared to the operational use of the power control rods and that, during normal operation, the AO rods would have to operate for 75 seconds (i.e., 10 steps per the current technical specification, for rods that travel at 8 steps per minute, thus 10 steps / 8 steps per minute = 1.25 minutes) to satisfy the current SR.
The NRC requests that the licensee provide 1) additional technical justification for the exclusion of the AO control bank RCCAs explaining how applying the original surveillance requirement of 10 steps or more would result in radial or axial power tilts or oscillations to occur, and 2) documentation showing that during normal operations the expected movement of the AO control bank RCCAs would satisfy the 10 step requirement.
Page 2 of 5
ND-18-0364 Response to NRC Request for Additional Information Regarding the LAR-17-024 Review (LAR-17-024S2)
Response to Question 1:
SNC is removing the information from the LAR pertaining to the exclusion of the AO control bank RCCAs from Surveillance Requirement (SR) 3.1.4.2. Instead, the note will be deleted altogether from SR 3.1.4.2. As discussed on Page 7 of 39 of Enclosure 1 to ND-17-1279, [] the proposed change to the first SR 3.1.4.2 Note to delete GRCAs [is] consistent with the proposed LCO modification. The proposed LCO modification is as described throughout the remainder of discussion of change L02 on Pages 5 and 6 of Enclosure 1 to ND-17-1279 and the Significant Hazards Consideration for L02 on Pages 24-27 of Enclosure 1 to ND-17-1279. The deletion of the Note altogether uses the same logic and justification regarding the change from rod to RCCA throughout the LCO and is equivalent to deleting the GRCAs from the Note.
The portion of the LAR identified as change L02J on Page 5 of 39 and Page 25 of 39 of to ND-17-1279, as supplemented by Page 2 of 2 of Enclosure 4 to ND-18-0058, is revised to state Delete the Note to SR 3.1.4.2. Refer to Enclosure 7 of this letter for the revised markup of SR 3.1.4.2.
The justification in the top paragraph of Page 7 of 39 of Enclosure 1 to ND-17-1279 is revised as follows:
The proposed change from rod to RCCA in SR 3.1.4.2, the proposed change to the first deletion of SR 3.1.4.2 Note to delete GRCAs, the proposed deletion of SR 3.1.4.3 Note, and the proposed change to SR 3.1.4.3 RCCA instead of rod are consistent with the proposed LCO modification. The Note modification to SR 3.1.4.2 exception for the control rods of the AO control bank RCCAs is proposed to prevent perturbing the power distribution. Moving the AO control bank will significantly and inappropriately perturb the power distribution. Although moving the rods individually is an option that would perturb power distribution less over the 92 day frequency, several steps of motion of the AO control bank RCCAs are expected during normal operations. As a result, any malfunction of an AO control bank RCCA causing loss of mobility would be self-revealing to the operator.
Removing the note from SR 3.1.4.2 does not expand the scope of the request or alter the conclusions of the Significant Hazards Consideration Determination or Environmental Considerations submitted in LAR-17-024.
Conforming changes to the Technical Specifications Bases to reflect the deletion of the note are included in Enclosure 8 of this letter.
Page 3 of 5
ND-18-0364 Response to NRC Request for Additional Information Regarding the LAR-17-024 Review (LAR-17-024S2)
Question 2:
10 CFR Part 50.36, Technical Specifications, requires, in part, that Where a limiting safety system setting is specified for a variable on which a safety limit has been placed, the setting must be so chosen that automatic protective action will correct the abnormal situation before a safety limit is exceeded. The Protection and Safety Monitoring System (PMS), the instrumentation and controls (I&C) safety system for the AP1000 reactor, has been designed to assure safe operation of the reactor. This is achieved by specifying limiting safety system settings (LSSS) in terms of parameters directly monitored by the reactor trip system (RTS) portion of the PMS, as well as specifying limiting conditions for operation (LCOs) on other reactor system parameters and equipment performance. Technical Specifications (TSs) are required by 10 CFR 50.36 to include LSSS for variables that have significant safety functions.
Vogtle LAR-17-024 on pages 10 and 32 to 34 of Enclosure 1 proposes to amend TS 3.3.1, Reactor Trip System Instrumentation, Table 3.3.1-1 FUNCTION 12, Passive Residual Heat Removal Actuation (PRHR), by deleting the specification to SR 3.3.1.9, Channel Calibration. The licensee states that SR 3.3.1.9 is not applicable to the PRHR reactor trip actuation function, and therefore not needed as input to the PRHR RTS actuation. The licensee indicates that the proper adjustment of the valve position indication contact inputs to the breaker position are verified by performance of SR 3.3.1.10, Trip Actuating Device Operational Test (TADOT).
The NRC staff requests that the licensee provide, or make available by reference, the specific functional logic diagrams and other supporting documentation that demonstrate the execution of SR 3.3.1.9 and 3.3.1.10 as they pertain to the Passive Residual Heat Removal Actuation for the RTS in Table 3.3.1-1 (Function 12). This would enable the staff to better understand how the actions taken in SR 3.3.1.9 may be redundant to the actions taken in SR 3.3.1.10 and thus confirm that the requirement to undertake this activity as part of SR 3.3.1.9 in Table 3.3.1-1 is unnecessary.
Page 4 of 5
ND-18-0364 Response to NRC Request for Additional Information Regarding the LAR-17-024 Review (LAR-17-024S2)
Response to Question 2:
The TRIP ACTUATING DEVICE OPERATIONAL TEST (TADOT) for the PRHR HX Outlet Valve Reactor Trip function involves testing at shutdown/defueled condition by placing the relevant Component Interface Modules (CIMs) into REMOTE, opening valves PXS-V108A/B, confirming the receipt of a Not Closed signal for each valve contact and Partial Trip signal from each PMS division, closing the valves, and then placing the CIMs into LOCAL again. The TADOT confirms the signal path from the PXS-V108A/B valve contacts through the Bistable Processor Logic (BPL),
as well as the BPL outputs to the Local Coincidence Logic (LCL).
The CHANNEL CALIBRATION (CAL) for the PRHR HX Outlet Valve Reactor Trip function would be performed in the same manner by actuating the sensor, testing the inputs to the BPL, and then to the LCL; therefore, it would test the same signal path and be a redundant surveillance.
Given the description of the signal path provided above, inclusion of logic diagrams is not deemed necessary. If the NRC needs additional clarification, SNC will respond as necessary.
Page 5 of 5
Southern Nuclear Operating Company ND-18-0364 Enclosure 7 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Supplement to Proposed Changes to Licensing Basis Documents (LAR-17-024S2)
(This Enclosure consists of 2 pages, including this cover page.)
ND-18-0364 Supplement to Proposed Changes to Licensing Basis Documents (LAR-17-024S2)
Replace the markup shown as L02J-M on Page 2 of 2 of Enclosure 5 of ND-18-0058 as shown below.
Revised COL Appendix A (Technical specifications), TS 3.1.4, Rod Group Alignment Limits, as follows (L02J-M):
SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.1.4.2 -----------------------------------------------------------
- NOTE -
Not applicable to GRCAs.
Verify rod freedom of movement (trippability) by moving each rodRCCA not fully inserted in the core 10 steps in either direction.
SR 3.1.4.3 -----------------------------------------------------------
- NOTE -
Not applicable to GRCAs.
Verify rod drop time of each rodRCCA, from the fully withdrawn position, is 2.7 seconds from the beginning of decay of stationary gripper coil voltage to dashpot entry, with:
Page 2 of 2
Southern Nuclear Operating Company ND-18-0364 Enclosure 8 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Supplement to Conforming Technical Specifications Bases Changes (For Information Only)
(LAR-17-024S2)
(This Enclosure consists of 2 pages, including this cover page.)
ND-18-0364 Supplement to Conforming Technical Specifications Bases Changes (For Information Only)
(LAR-17-024S2)
Replace the markup shown on Page 7 of 12 of Enclosure 3 of ND-17-1279 as shown below.
1.0. In MODE 2 with keff <1.0, SR 3.1.4.2 is not applicable because GRCAs must be verified to be fully inserted to be credited in the calculation of SDM.
BASES SURVEILLANE REQUIREMENTS (continued)
SR 3.1.4.3 Verification of rodRCCA drop times allows the operator to determine that the maximum rodRCCA drop time permitted is consistent with the assumed rod drop time used in the safety analysis. Measuring rodRCCA drop times prior to reactor criticality, after each reactor vessel head removal and each earthquake requiring plant shutdown, ensures that the reactor internals and rod drive mechanism will not interfere with rodRCCA motion or rodRCCA drop time, and that no degradation in these systems has occurred that would adversely affect control rod motion or drop time.* *
- GRCA are excluded from this Surveillance because they are not considered in the calculation of SDM in MODES 1 and 2 with keff 1.0. In MODE 2 with keff
<1.0, SR 3.1.4.2 is not applicable because GRCAs must be verified to be fully inserted to be credited in the calculation of SDM.
Page 2 of 2