ND-18-0335, Vogtie, Units 3 and 4 - Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.7.06.01 (Index Number 723)

From kanterella
(Redirected from ML18072A244)
Jump to navigation Jump to search
Vogtie, Units 3 and 4 - Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.7.06.01 (Index Number 723)
ML18072A244
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 03/13/2018
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of New Reactors
References
ITAAC 2.7.06.01, ND-18-0335
Download: ML18072A244 (6)


Text

Michael J. Yox 7825 River Road Regulatory Affairs Director Waynesboro, GA 30830 Southern Nuclear Vogtie 3 & 4 706-848-6459 tel 410-474-8587 celi myox @southernco. com mar 1 3 2018 Docket Nos.: 52-025 52-026 ND-18-0335 10CFR 52.99(c)(3)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtie Electric Generating Plant Unit 3 and Unit 4 Notice of Uncompleted ITAAC 225-davs Prior to Initial Fuel Load Item 2.7.06.01 [Index Number 7231 Ladies and Gentlemen:

Pursuant to 10 CFR 52.99(c)(3), Southern Nuclear Operating Company hereby notifies the NRC that as of March 8, 2018, Vogtie Electric Generating Plant (VEGP) Unit 3 and Unit 4 Uncompleted Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 2.7.06.01 [Index Number 723]

has not been completed greater than 225-days priorto initial fuel load. The Enclosure describes the plan for completing this ITAAC. Southern Nuclear Operating Company will, at a later date, provide additional notifications for ITAAC that have not been completed 225-days prior to initial fuel load.

This notification is informed by the guidance described in NEI 08-01, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215. In accordance with NEI 08-01, this notification includes ITAAC for which required inspections, tests, or analyses have not been performed or have been only partially completed. All ITAAC will be fully completed and all Section 52.99(c)(1) ITAAC Closure Notifications will be submitted to NRC to support the Commission finding that all acceptance criteria are met priorto plant operation, as required by 10 CFR 52.103(g).

This letter contains no new NRC regulatory commitments.

If there are any questions, please contact Tom Petrak at 706-848-1575.

Respectfully submitted.

Michael J. Yox Regulatory Affairs Director Vogtie 3 &4

Enclosure:

Vogtie Electric Generating Plant (VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 2.7.06.01 [Index Number 723]

MJY/RAS/amw

U.S. Nuclear Regulatory Commission ND-18-0335 Page 2 of 3 To:

Southern Nuclear Operating Companv/ Georgia Power Company Mr. D. A. Bost (w/o enclosures)

Mr. M. D. Rauckhorst (w/o enclosures)

Mr. J. B. Klecha Mr. M. D. Meier Mr. D. H. Jones (w/o enclosures)

Mr. D. L. McKinney Mr. M. J. Yox Mr. D. L. Fulton Mr. F. H. Willis Ms. A. L. Pugh Mr. A. 8. Parton Mr. W. A. Sparkman Mr. C. E. Morrow Ms. K. M. Stacy Mr. M. K. Washington Mr. J. P. Redd Ms. A. 0. Chamberlain Mr. D. R. Culver Mr. T. G. Petrak Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:

Nuclear Regulatory Commission Mr. W. Jones (w/o enclosures)

Ms. J. M. Heisserer Mr. C. P. Patel Mr. M. E. Ernstes Mr. G. J. Khouri Mr. T. E. Chandler Ms. S. E. Temple Ms. P. Braxton Mr. N. D. Karlovich Mr. A. J. Lerch Mr. C. J. Even Mr. F. D. Brown Mr. B. J. Kemker Ms. A. E. Rivera-Varona Ms. L. A. Kent Mr. P. B. Donnelly Oalethoroe Power Corporation Mr. R. B. Brinkman Municipal Electric Authoritv of Georgia Mr. J. E. Fuller Mr. S. M. Jackson

U.S. Nuclear Regulatory Commission ND-18-0335 Page 3 of 3 Dalton Utilities Mr. T. Bundros Westinqhouse Electric Company. LLC Dr. L. Oriani (w/o enclosures)

Mr. D. 0. Durham (w/o enclosures)

Mr. M. M. Corletti Ms. L G. IHer Mr. D. Hawkins Ms. J. Monahan Mr. J. L. Coward Ms. N. E. Deangelis Other Mr. J. E. Hosier, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., CDS Associates, inc.

Mr. S. Roetger, Georgia Public Service Commission Ms. 8. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Baich Bingham

U.S. Nuclear Regulatory Commission ND-18-0335 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-18-0335 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 2.7.06.01 [Index Number 723]

U.S. Nuclear Regulatory Commission ND-18-0335 Enclosure Page 3 of 3 ITAAC Statement Desion Commitment

1. The functional arrangement of the VPS is as described in the Design Description of this Section 2.7.6.

Insoections/Tests/Analvses Inspection of the as-built system will be performed.

Acceotance Criteria The as-built VPS conforms with the functional arrangement described in the Design Description of this Section 2.7.6.

iTAAC Completion Description An inspection of the as-built Containment Air Piltration System (VPS) is conducted after completion of constructionto confirm that the functional arrangement of the VPS is as described in the Design Description of Combined License (COL) Appendix C, Section 2.7.6. This inspection encompasses the structures, systems, and components (SSCs) identified inthe COL Appendix C, Section 2.7.6 Design Description, including those in Table 2.7.6-3 and Pigure 2.7.6-1.

The inspection (walkdown) is completed in accordance with APP-GW-ITY-004, Punctional Arrangement ITAAC Guideline (Reference 1), which requires the preparation of a detailed inspection plan. This inspection plan includes the use of detailed drawings such as Piping and Instrumentation Drawings (P&IDs) or Single Line Elementary Drawings to perform visual observations and compare the as-built system to the Design Description.

The inspection results are documented in the Unit 3 and Unit 4 Principal Closure Documents XXX and YYY (References 2 and 3, respectively) supporting the Unit 3 and Unit 4 ITAAC 2.7.06.01 Completion Packages (References 4 and 5, respectively) and verify that the SSCs are physically arranged and locatedto perform the functions described in the Design Description and referenced table and figure. The inspection results confirm that the as-built VPS conforms with the functional arrangement as described in the COLAppendix C, Section 2.7.6, Design Description.

The Unit 3 and Unit 4 Principal Closure Documents XXX and YYY are available for NRC inspection as part of the Unit 3 and Unit 4 ITAAC 2.7.06.01 Completion Packages.

List of ITAAC Findings In accordance with plant procedures for ITAAC completion. Southern Nuclear Operating Company (SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC.

U.S. Nuclear Regulatory Commission ND-18-0335 Enclosure Page 3 of 3 References ^available for NRC inspection)

1. APP-GW-ITY-004, Functional Arrangement Guideline
2. Principal Closure Document XXX (Unit 3)
3. Principal Closure Document YYY (Unit 4)
4. ITAAC 2.7.06.01 Completion Package (Unit 3)
5. ITAAC 2.7.06.01 Completion Package (Unit 4)
6. NEI 08-01, "Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52"