Category:Inspection Report
MONTHYEARIR 05000368/20253012024-09-0909 September 2024 Notification of NRC Initial Operator Licensing Examination 05000368/2025301 IR 05000313/20240112024-09-0505 September 2024 Comprehensive Engineering Team Inspection Report 05000313/2024011 and 05000368/2024011 IR 05000313/20240052024-08-21021 August 2024 Updated Inspection Plan for Arkansas Nuclear One – Units 1 and 2 (Report 05000313/2024005, 05000368/2024005) IR 05000313/20240022024-08-0606 August 2024 Integrated Inspection Report 05000313/2024002 and 05000368/2024002 IR 05000313/20240012024-05-0808 May 2024 Integrated Inspection Report 05000313/2024001 and 05000368/2024001 IR 05000313/20244042024-04-0808 April 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection (05000313/2024404 and 05000368/2024404) IR 05000313/20244022024-04-0808 April 2024 Security Baseline Inspection Report 05000313/2024402 and 05000368/2024402 (Full Report) IR 05000313/20230062024-02-28028 February 2024 Annual Assessment Letter for Arkansas Nuclear One- Units 1 and 2 Report 05000313/2023006 and 05000368/2023006 IR 05000313/20230042024-02-0808 February 2024 Integrated Inspection Report 05000313/2023004 and 05000368/2023004 and Independent Spent Fuel Storage Installation Inspection Report 07200013/2023002 IR 05000313/20234202024-01-10010 January 2024 Security Baseline Inspection Report 05000313/2023420 and 05000368/2023420 IR 05000313/20234022024-01-0202 January 2024 Security Baseline Inspection Report 05000313/2023402 and 05000368/2023402 IR 05000313/20234052023-12-12012 December 2023 – Security Baseline Inspection Report 05000313/2023405 and 05000368/2023405 IR 05000313/20230032023-11-21021 November 2023 Revised - ANO Revised Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/ 2023001 ML23313A0962023-11-13013 November 2023 Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/2023001 IR 05000313/20230112023-10-10010 October 2023 Commercial Grade Dedication Inspection Report 05000313/2023011 and 05000368/2023011 IR 05000313/20230102023-09-20020 September 2023 – Biennial Problem Identification and Resolution Inspection Report 05000313/2023010 and 05000368/2023010 IR 05000313/20230052023-08-21021 August 2023 Updated Inspection Plan for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2023005 and 05000368/2023005) - Mid Cycle IR 05000313/20243012023-08-14014 August 2023 Notification of NRC Initial Operator Licensing Examination 05000313/2024301 IR 05000313/20230022023-08-11011 August 2023 Integrated Inspection Report 05000313/2023002 and 05000368/2023002 and Notice of Violation IR 05000416/20230022023-08-0808 August 2023 Integrated Inspection Report 05000416/2023002 and Independent Spent Fuel Storage Installation Inspection Report 07200050/2023001 IR 05000313/20234032023-06-28028 June 2023 – Security Baseline Inspection Report 05000313/2023403 and 05000368/2023403 IR 05000313/20234012023-06-13013 June 2023 – Cyber Security Inspection Report 05000313/2023401 and 05000368/2023401 IR 05000313/20230012023-05-0909 May 2023 Integrated Inspection Report 05000313/2023001 and 05000368/2023001 IR 05000368/20233012023-05-0101 May 2023 NRC Examination Report 05000368/2023301 IR 05000313/20220062023-03-0101 March 2023 Annual Assessment Letter for Arkansas Nuclear One – Units 1 and 2 (Report 05000313/2022006 and 05000368/2022006) IR 05000313/20220042023-01-26026 January 2023 Integrated Inspection Report 05000313/2022004 and 05000368/2022004 - 4th Quarter IR 05000313/20220032022-11-0909 November 2022 Integrated Inspection Report 05000313/2022003 and 05000368/2022003 and Exercise of Enforcement Discretion ML22301A1532022-11-0909 November 2022 Notice of Violation NRC Inspection Report 05000313/2022011 and 05000368/2022011 IR 05000313/20220112022-11-0909 November 2022 Notice of Violation NRC Inspection Report 05000313/2022011 and 05000368/2022011 ML22308A1912022-11-0606 November 2022 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000313/2023401 and 05000368/2023401 IR 05000313/20224012022-10-20020 October 2022 Security Baseline Inspection Report 05000313/2022401 and 05000368/2022401 IR 05000313/20220502022-09-26026 September 2022 Special Inspection Reactive Report 05000313 2022050 and 05000368 2022050 Cover Letter Only ML22208A1282022-08-0404 August 2022 (2nd Quarter) Inspection Report 2022 002 IR 05000313/20210132022-05-17017 May 2022 License Renewal Phase 4 Inspection Report 05000313/2021013 IR 05000313/20220012022-05-10010 May 2022 Integrated Inspection Report 05000313/2022001 and 05000368/2022001 IR 05000313/20223012022-03-30030 March 2022 NRC Initial Operator Licensing Operating Test Approval 05000313/2022301 IR 05000313/20220102022-03-14014 March 2022 Triennial Fire Protection Inspection Report 05000313/2022010 and 05000368/2022010 IR 05000313/20210062022-03-0202 March 2022 Annual Assessment Letter for Arkansas Nuclear One, Units 1 & 2 (Report 05000313/2021006 and 05000368/2021006) IR 05000313/20224032022-02-23023 February 2022 Security Baseline Inspection Report 05000313/2022403 and 05000368/2022403 IR 05000313/20210042022-02-0404 February 2022 Integrated Inspection Report 05000313/2021004 and 05000368/2021004 ML22011A0992022-01-14014 January 2022 IR 2021012 EOI CO3 IR 05000313/20210102022-01-13013 January 2022 Biennial Problem Identification and Resolution Inspection Report 05000313/2021010 and 05000368/2021010 IR 05000313/20210032021-11-0505 November 2021 Integrated Inspection Report 05000313/2021003 and 05000368/2021003 IR 05000313/20210112021-09-23023 September 2021 Design Basis Assurance Inspection (Teams) Inspection Report 05000313/2021011 and 05000368/2021011 IR 05000313/20214012021-08-10010 August 2021 Security Baseline Inspection Report 05000313/2021401 and 05000368/2021401 IR 05000313/20210022021-08-0909 August 2021 Integrated Inspection Report 05000313/2021002 and 05000368/2021002 IR 05000368/20213012021-05-17017 May 2021 NRC Examination Report 05000368/2021301 IR 05000313/20210012021-05-0606 May 2021 Integrated Inspection Report 05000313/2021001 and 05000368/2021001 ML21095A3162021-04-13013 April 2021 ANO 2021402-Non SGI Rcl IR 05000313/20200062021-03-0303 March 2021 Annual Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2020006 and 05000368/2020006) 2024-09-09
[Table view] Category:Letter
MONTHYEARML24295A1202024-10-21021 October 2024 Relief Request ANO2-RR-24-001, Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 71 ML24185A2602024-10-0404 October 2024 Issuance of Amendment No. 335 to Revise Typographical Errors in Technical Specifications IR 05000368/20253012024-09-0909 September 2024 Notification of NRC Initial Operator Licensing Examination 05000368/2025301 ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification IR 05000313/20240112024-09-0505 September 2024 Comprehensive Engineering Team Inspection Report 05000313/2024011 and 05000368/2024011 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000313/20240052024-08-21021 August 2024 Updated Inspection Plan for Arkansas Nuclear One – Units 1 and 2 (Report 05000313/2024005, 05000368/2024005) ML24198A0722024-08-21021 August 2024 Correction to Issuance of Amendment No. 333 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24220A2642024-08-20020 August 2024 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML24185A1522024-08-13013 August 2024 Issuance of Amendment Nos. 334, 235, and 215, Respectively, to Revise TSs to Adopt TSTF-205 IR 05000313/20240022024-08-0606 August 2024 Integrated Inspection Report 05000313/2024002 and 05000368/2024002 ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification 05000313/LER-2024-001, Source Range Nuclear Instrument Failure Resulting in Condition Prohibited by Technical Specifications2024-07-0101 July 2024 Source Range Nuclear Instrument Failure Resulting in Condition Prohibited by Technical Specifications ML24101A1792024-06-25025 June 2024 Issuance of Amendment No. 333 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24143A0632024-05-22022 May 2024 Notification of Inspection (NRC Inspection Report 05000368/2024003) and Request for Information IR 05000313/20240012024-05-0808 May 2024 Integrated Inspection Report 05000313/2024001 and 05000368/2024001 ML24128A2472024-05-0808 May 2024 Project Manager Assignment ML24017A2982024-04-18018 April 2024 Summary of Regulatory Audit Regarding the License Amendment Request to Revise Technical Specifications to Adopt TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b ML24107A0282024-04-17017 April 2024 Notification of Comprehensive Engineering Team Inspection (05000313/2024011 and 05000368/2024011) and Request for Information ML24086A5412024-04-10010 April 2024 Authorization of Request for Alternative ANO1-ISI-037 Regarding Extension of Reactor Vessel Inservice Inspection Interval IR 05000313/20244022024-04-0808 April 2024 Security Baseline Inspection Report 05000313/2024402 and 05000368/2024402 (Full Report) IR 05000313/20244042024-04-0808 April 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection (05000313/2024404 and 05000368/2024404) ML24089A2262024-03-29029 March 2024 Entergy Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Exams ML24075A1712024-03-15015 March 2024 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) ML24031A6442024-03-14014 March 2024 Issuance of Amendment No. 282 to Modify Technical Specification 3.3.1, Reactor Pressure System (RPS) Instrumentation, Turbine Trip Function on Low Control Oil Pressure ML24074A2892024-03-14014 March 2024 Proof of Financial Protection (10 CFR 140.15) ML24102A1342024-03-12012 March 2024 AN1-2024-03 Post Exam Submittal IR 05000313/20230062024-02-28028 February 2024 Annual Assessment Letter for Arkansas Nuclear One- Units 1 and 2 Report 05000313/2023006 and 05000368/2023006 IR 05000313/20230042024-02-0808 February 2024 Integrated Inspection Report 05000313/2023004 and 05000368/2023004 and Independent Spent Fuel Storage Installation Inspection Report 07200013/2023002 ML24012A0502024-02-0202 February 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0054 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23326A0392024-01-24024 January 2024 Issuance of Amendment No. 281 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24017A1582024-01-17017 January 2024 Submittal of Emergency Plan Revision 50 IR 05000313/20234202024-01-10010 January 2024 Security Baseline Inspection Report 05000313/2023420 and 05000368/2023420 IR 05000313/20234022024-01-0202 January 2024 Security Baseline Inspection Report 05000313/2023402 and 05000368/2023402 ML23354A0022023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology – Slides and Affidavit for Pre-Submittal Meeting ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment IR 05000313/20234052023-12-12012 December 2023 – Security Baseline Inspection Report 05000313/2023405 and 05000368/2023405 ML23341A0832023-12-11011 December 2023 – Material Control and Accounting Program Inspection Report 05000313/368/2023404- Cover Letter ML23305A0922023-12-0707 December 2023 – Summary of Regulatory Audit Regarding License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b ML23333A1362023-11-29029 November 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23275A2072023-11-28028 November 2023 Issuance of Amendment No. 280 Removal of Technical Specification Condition Allowing Two Reactor Coolant Pump Operation ML23325A1412023-11-21021 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000313/20230032023-11-21021 November 2023 Revised - ANO Revised Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/ 2023001 ML23324A0172023-11-16016 November 2023 Submittal of Amendment 31 to Safety Analysis Report ML23313A0962023-11-13013 November 2023 Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/2023001 ML23243B0452023-11-13013 November 2023 Request for Withholding Information from Public Disclosure ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV 2024-09-09
[Table view] Category:Notice of Violation
MONTHYEARIR 05000313/20230022023-08-11011 August 2023 Integrated Inspection Report 05000313/2023002 and 05000368/2023002 and Notice of Violation ML22346A2052022-12-14014 December 2022 Acknowledgment of Response to NRC Inspection Report 05000313/2022011 and 05000368/2022011 and Notice of Violation ML22301A1532022-11-0909 November 2022 Notice of Violation NRC Inspection Report 05000313/2022011 and 05000368/2022011 IR 05000313/20220112022-11-0909 November 2022 Notice of Violation NRC Inspection Report 05000313/2022011 and 05000368/2022011 IA-20-030, Notice of Violation, NRC Investigation Report 4-2019-009 - Lee2020-09-24024 September 2020 Notice of Violation, NRC Investigation Report 4-2019-009 - Lee ML20267A5592020-09-23023 September 2020 Notice of Violation, NRC Investigation Report 4-2019-Hegeman IR 05000313/20204042020-09-23023 September 2020 Notice of Violation; NRC Inspection Report 05000313/2020404 and 05000368/2020404 and NRC Investigation Report 4-2019-009 ML19330E5482019-11-22022 November 2019 Notice of Violation - NRC Investigation Report 4-2018-019 IR 05000313/20170142017-02-27027 February 2017 EA-16-247 Entergy Operations, Inc., Arkansas Nuclear One Arkansas Nuclear One, Unit 2 - Final Significance Determination of a White Finding and Notice of Violation, NRC Inspection Report 05000368/2017014 IR 05000368/20170142017-02-27027 February 2017 EA-16-247 Entergy Operations, Inc., Arkansas Nuclear One Arkansas Nuclear One, Unit 2 - Final Significance Determination of a White Finding and Notice of Violation, NRC Inspection Report 05000368/2017014 IR 05000313/20140102016-02-10010 February 2016 EA-14-088 Arkansas Nuclear One - Revised Notice of Violation; NRC Inspection Report 05000313/2014010 and 05000368/2014010 ML15023A0762015-01-22022 January 2015 Final Significance Determination of Yellow Finding and Notice of Violation: NRC Inspection Report 05000313/2014010 and 05000368/2014010 IR 05000313/20140082014-06-23023 June 2014 EA-14-008_Arkansas Nuclear One, Units 1 and 2 - Final Significance Determination of Two Yellow Findings and Notice of Violation; NRC Inspection Report 05000313/2014008 and 05000368/2014008 ML14174A8322014-06-23023 June 2014 EA-14-008_Arkansas Nuclear One, Units 1 and 2 - Final Significance Determination of Two Yellow Findings and Notice of Violation; NRC Inspection Report 05000313/2014008 and 05000368/2014008 IR 05000313/20135042013-06-10010 June 2013 IR 05000313-13-504, 05000368-13-504, and Notice of Violation, on 12/14/2012 & 03/11/2013, Arkansas Nuclear One, NRC Emergency Preparedness Inspection and NRC Investigation Report 4-2012-024 IR 05000333/20110092012-01-26026 January 2012 EA-10-090, EA10-248, EA-11-106 Fitzpatrick/Entergy - Confirmatory Order (Effective Immediately) and Notice of Violation, Investigation Report Nos. 1-2009-041, 1-2010-019 and 1-2010-031, Inspection Repot No. 05000333-11-009 IR 05000313/20100042010-11-12012 November 2010 IR 05000313-10-004 & 05000368-10-004, and Notice of Violation, on 07/01/10 - 09/30/10, Arkansas Nuclear One - NRC Integrated Inspection ML0509001812005-03-29029 March 2005 Draft Ltr to Arkansas Nuclear One from Mallet, Arkansas Nuclear One, Unit 1 - Final Significance Determination for a White Finding and Notice of Violation ML0409901002004-04-0707 April 2004 EA-03-016 Entergy Operations, Inc., Final Significance Determination for a White Finding & Notice of Violation (NRC Inspection Report No. 50-313/01-06; 368/01-06, Arkansas Nuclear One) 2023-08-11
[Table view] |
Text
UNITED STATES ary 27, 2017
SUBJECT:
ARKANSAS NUCLEAR ONE, UNIT 2 - FINAL SIGNIFICANCE DETERMINATION OF A WHITE FINDING AND NOTICE OF VIOLATION, NRC INSPECTION REPORT 05000368/2017014
Dear Mr. Anderson:
This letter provides you the final significance determination of the preliminary White finding discussed in the U.S. Nuclear Regulatory Commissions (NRCs) Inspection Report 05000368/2016011 dated January 19, 2017 (Agencywide Document Access and Management System (ADAMS) ML17019A288). The finding involved a failure to ensure that an emergency diesel generator bearing was provided with adequate lubrication. As a result, the bearing overheated and caused the emergency diesel generator to fail on September 16, 2016, during a 24-hour endurance test. The extent of damage from the failure led to the decision to shut down Unit 2 to comply with technical specifications. This finding did not present an immediate safety concern because other normal and emergency sources of power remained available, and your plant walkdowns and our inspections confirmed that this condition did not exist on other safety-related equipment.
In a telephone conversation with Mr. Neil OKeefe, Chief, Reactor Projects Branch E, on January 20, 2017, you indicated that Entergy Operations, Inc., did not contest the characterization of the risk significance of this finding, and that you declined your opportunity to discuss this issue in a regulatory conference or to provide a written response. According to NRC Inspection Manual Chapter 0609, Attachment 1, Significance and Enforcement Review Panel (SERP) Process, by declining the opportunity to submit a written response or to request a Regulatory Conference, the licensee relinquishes its right to appeal the final significance determination.
After considering the information developed during the inspection, the NRC has concluded that the finding is appropriately characterized as White, a finding with low to moderate safety significance.
The NRC has also determined that failure to provide adequate work instructions ensuring proper lubrication to the inboard generator bearing is a violation of Arkansas Nuclear One, Unit 2, Technical Specification 6.4.1.a, as cited in the attached Notice of Violation (Notice). The circumstances surrounding the violation were described in NRC Inspection Report 05000368/2016011. In accordance with the NRC Enforcement Policy, the Notice is considered escalated enforcement action because it is associated with a White finding.
You are required to respond to this letter and should follow the instructions specified in the enclosed Notice when preparing your response. If you have additional information that you believe the NRC should consider, you may provide it in your response to the Notice. The NRC review of your response to the Notice will also determine whether further enforcement action is necessary to ensure compliance with regulatory requirements.
The NRC has reviewed this finding and its causal factors in context with the performance issues that contributed to Arkansas Nuclear One being placed into Column 4 of the NRCs Action Matrix and concluded that continued oversight in Column 4 remains appropriate. After reviewing your response to the information requested in the attached Notice, the staff will consider whether it is appropriate to amend the existing Confirmatory Action Letter (ML16169A193) to include any of your corrective actions for this finding.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice and Procedure, a copy of this letter, its enclosure, and your response, will be made available electronically for public inspection in the NRC Public Document Room or from the NRCs document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response should not include any personal privacy, proprietary, or safeguards information so that it can be made available to the Public without redaction.
Sincerely,
/RA/
Kriss M. Kennedy Regional Administrator Docket No. 50-368 License No. NPF-6 Enclosure:
Notice of Violation cc w/encl: Electronic Distribution
SUNSI Review: ADAMS: Non-Publicly Available Non-Sensitive Keyword:
By:CFO Yes No Publicly Available Sensitive NRC-002 OFFICE PE: DRP/E C:DRP/E TL:ACES DD:DRP DD:DRS RC: ORA NAME BCorrell NOKeefe MHay TPruett AVegel KFuller SIGNATURE /RA/ /RA/ /RA/ /RA/ /RA/ /RA/
DATE 2/9/17 2/8/17 2/13/17 2/15/17 2/15/17 2/9/17 OFFICE OE RIV/RA NAME MMarshfield KKennedy SIGNATURE /RA/Email /RA/
DATE 2/17/17 2/27/17
NOTICE OF VIOLATION Entergy Operations, Inc. Docket No.: 50-368 Arkansas Nuclear One, Unit 2 License No.: NPF-6 EA-16-247 During an NRC inspection conducted from September 16 to December 21, 2016, a violation of NRC requirements was identified. In accordance with the NRC Enforcement Policy, the violation is listed below:
Technical Specification 6.4.1.a requires, in part, that written procedures shall be established, implemented, and maintained covering the applicable procedures recommended in Regulatory Guide 1.33, Quality Assurance Program Requirements, Revision 2, Appendix A, February 1978. Regulatory Guide 1.33, Appendix A, Section 9.a, states, in part, that maintenance that can affect the performance of safety-related equipment should be properly pre-planned and performed in accordance with written procedures, documented instructions, or drawings appropriate to the circumstances.
Contrary to the above, on November 11, 2014, and on June 22, 2016, the licensee failed to properly pre-plan and perform maintenance that can affect the performance of safety-related equipment in accordance with written procedures, documented instructions, or drawings appropriate to the circumstances. Specifically, on November 11, 2014, while performing Work Order 356569, and on June 22, 2016, while performing Work Order 52656389, the licensee failed to provide adequate documented work instructions for maintenance on the Unit 2 emergency diesel generator A inboard generator bearing, a safety-related component, such that the minimum bearing oil level was correctly marked and maintained to ensure adequate lubrication to the bearing. As a result, the Unit 2 emergency diesel generator A failed on September 16, 2016, during a 24-hour endurance test.
This violation is associated with a White significance determination process finding.
Pursuant to the provisions of 10 CFR 2.201, Entergy Operations, Inc., is hereby required to submit a written statement or explanation to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001, with a copy to the Regional Administrator, Region IV, 1600 East Lamar Boulevard, Arlington, Texas 76011-4511; and a copy to the NRC Resident Inspector at the Arkansas Nuclear One station, within 30 days of the date of the letter transmitting this Notice of Violation (Notice).
This reply should be clearly marked as a Reply to a Notice of Violation; EA-16-247 and should include: (1) the reason for the violation, or, if contested, the basis for disputing the violation, (2) the corrective steps that have been taken and the results achieved, (3) the corrective steps that will be taken, and (4) the date when full compliance will be achieved. Your response may reference or include previous docketed correspondence, if the correspondence adequately addresses the required response. If an adequate reply is not received within the time specified in this Notice, an order or a Demand for Information may be issued as to why the license should not be modified, suspended, or revoked, or why such other action as may be proper should not be taken. Where good cause is shown, consideration will be given to extending the response time.
Enclosure
If you contest this enforcement action, you should also provide a copy of your response, with the basis for your denial, to the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001.
Because your response will be made available electronically for public inspection in the NRC Public Document Room or from the NRCs document system (ADAMS), accessible from the NRC Website at www.nrc.gov/reading-rm/adams.html, to the extent possible, it should not include any personal privacy, proprietary, or safeguards information so that it can be made available to the public without redaction.
If personal privacy or proprietary information is necessary to provide an acceptable response, then please provide a bracketed copy of your response that identifies the information that should be protected, and a redacted copy of your response that deletes such information. If you request withholding of such material, you must specifically identify the portions of your response that you seek to have withheld and provide in detail the bases for your claim of withholding (e.g., explain why the disclosure of information will create an unwarranted invasion of personal privacy or provide the information required by 10 CFR 2.390(b) to support a request for withholding confidential commercial or financial information). If safeguards information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21.
Dated this 27th day of February 2017 2