MONTHYEARML13154A3682013-06-0404 June 2013 Request for Additional Information Regarding Reactor Pressure Vessel Surveillance Capsule Withdrawal Schedule Revision Project stage: RAI ML13192A0342013-07-0303 July 2013 Response to NRC Request for Additional Information Regarding Reactor Pressure Vessel Surveillance Capsule Withdrawal Schedule Revision Project stage: Response to RAI ML13240A3202013-09-27027 September 2013 Revise the Reactor Pressure Vessel Material Surveillance Capsule Withdrawal Schedule Due to License Renewal Amendment (TAC Nos. MF0631 and MF0632) Project stage: Other CNL-16-111, Capsule Withdrawal Schedule Revision2016-12-23023 December 2016 Capsule Withdrawal Schedule Revision Project stage: Other 2013-07-03
[Table View] |
|
---|
Category:Letter type:CNL
MONTHYEARCNL-24-074, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-10-23023 October 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description CNL-24-047, Decommitment of Flood Mode Mitigation Improvement Systems2024-09-24024 September 2024 Decommitment of Flood Mode Mitigation Improvement Systems CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-24-061, Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08),2024-08-19019 August 2024 Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08), CNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-24-037, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 422024-04-22022 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 42 CNL-24-024, Hydrologic Engineering Center River Analysis System Project Milestone Status Update2024-04-17017 April 2024 Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-23-006, Application to Modify Technical Specifications 3.8.1, AC Sources – Operating, and 3.8.2, AC Sources – Shutdown, for Sequoyah Nuclear Plant (SQN-TSC-22-03)2024-04-15015 April 2024 Application to Modify Technical Specifications 3.8.1, AC Sources – Operating, and 3.8.2, AC Sources – Shutdown, for Sequoyah Nuclear Plant (SQN-TSC-22-03) CNL-24-020, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements2024-04-0101 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements CNL-24-007, Annual Insurance Status Report2024-03-27027 March 2024 Annual Insurance Status Report CNL-24-008, Guarantee of Payment of Deferred Premiums - 2023 Annual Report2024-03-27027 March 2024 Guarantee of Payment of Deferred Premiums - 2023 Annual Report CNL-24-027, Response to Request for Additional Information Regarding Sequoyah Nuclear Plant, Units 1 and 2, Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2024-03-14014 March 2024 Response to Request for Additional Information Regarding Sequoyah Nuclear Plant, Units 1 and 2, Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation CNL-24-029, Response to Request for Additional Information Regarding Tennessee Valley Authority - Request for Exemption from Specific Requirements of 10 CFR Part 372024-03-14014 March 2024 Response to Request for Additional Information Regarding Tennessee Valley Authority - Request for Exemption from Specific Requirements of 10 CFR Part 37 CNL-24-023, Central Emergency Control Center Emergency Plan Implementing Procedure Revision. Includes CECC EPIP-17, Revision 252024-02-20020 February 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revision. Includes CECC EPIP-17, Revision 25 CNL-24-017, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions2024-01-17017 January 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions CNL-23-068, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-21021 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation CNL-23-036, Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08)2023-12-18018 December 2023 Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08) CNL-23-067, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-11-27027 November 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-23-061, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-09-20020 September 2023 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision CNL-23-059, Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-2023-09-20020 September 2023 Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 CNL-23-057, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 642023-09-0505 September 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 64 CNL-23-028, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06)2023-08-0202 August 2023 Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06) CNL-23-055, Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills2023-07-25025 July 2023 Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills CNL-23-053, Tennessee Valley Authority - Radiological Emergency Plan Revisions2023-07-18018 July 2023 Tennessee Valley Authority - Radiological Emergency Plan Revisions CNL-23-049, Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan .2023-06-26026 June 2023 Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan . CNL-23-042, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-05-16016 May 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-23-032, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 412023-04-27027 April 2023 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 41 CNL-23-030, Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update2023-04-27027 April 2023 Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-23-033, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-04-24024 April 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision CNL-23-029, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-04-11011 April 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-23-012, Revision to the Application to Revise Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis, (TS-19-02)2023-04-11011 April 2023 Revision to the Application to Revise Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis, (TS-19-02) CNL-23-023, Annual Insurance Status Report2023-03-30030 March 2023 Annual Insurance Status Report CNL-23-024, TVA Guarantee of Payment of Deferred Premiums - 2022 Annual Report2023-03-29029 March 2023 TVA Guarantee of Payment of Deferred Premiums - 2022 Annual Report CNL-23-022, Decommissioning Funding Status Report2023-03-29029 March 2023 Decommissioning Funding Status Report CNL-23-021, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-03-0808 March 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-22-037, Application to Revise Technical Specifications to Adopt TSTF-541-A, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position (BFN TS-533)2023-01-31031 January 2023 Application to Revise Technical Specifications to Adopt TSTF-541-A, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position (BFN TS-533) CNL-23-003, Browns Nuclear Plant, Units 1, 2 & 3; Sequoyah Nuclear Plant, Units 1 & 2; and Watts Bar Nuclear Plant, Units 1 & 2 - Organizational Topic Report TVA-NPOD89-A2023-01-30030 January 2023 Browns Nuclear Plant, Units 1, 2 & 3; Sequoyah Nuclear Plant, Units 1 & 2; and Watts Bar Nuclear Plant, Units 1 & 2 - Organizational Topic Report TVA-NPOD89-A CNL-23-011, Steam Generator Tube Inspection Report to Reflect TSTF-577 Reporting Requirements2023-01-18018 January 2023 Steam Generator Tube Inspection Report to Reflect TSTF-577 Reporting Requirements CNL-23-009, Response to Request for Additional Information Request to Revise Technical Specification 3.4.122023-01-0404 January 2023 Response to Request for Additional Information Request to Revise Technical Specification 3.4.12 CNL-23-008, Tennessee Valley Authority Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2022-12-22022 December 2022 Tennessee Valley Authority Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-22-106, Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision. Includes CECC EPIP-14, Revision 38, Nuclear Emergency Public Information Organization and Operat2022-11-28028 November 2022 Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision. Includes CECC EPIP-14, Revision 38, Nuclear Emergency Public Information Organization and Operatio CNL-22-099, Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update2022-10-31031 October 2022 Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-22-104, Correction to Response to Request for Additional Information Regarding Sequoyah Nuclear Plant, Units 1 and 2, American Society of Mechanical Engineers Operation and Maintenance Code, Request for Alternative RV-022022-10-31031 October 2022 Correction to Response to Request for Additional Information Regarding Sequoyah Nuclear Plant, Units 1 and 2, American Society of Mechanical Engineers Operation and Maintenance Code, Request for Alternative RV-02 CNL-22-098, Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC EPIP-7, Rev. 45 & CECC EPIP-8, Rev. 552022-10-17017 October 2022 Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC EPIP-7, Rev. 45 & CECC EPIP-8, Rev. 55 CNL-22-084, Response to Request for Additional Information Regarding License Amendment Request to License Amendment Request to Modify Approved 10 CFR 50.69 Categorization Process (SQN-TS-21-07)2022-09-16016 September 2022 Response to Request for Additional Information Regarding License Amendment Request to License Amendment Request to Modify Approved 10 CFR 50.69 Categorization Process (SQN-TS-21-07) CNL-22-085, Response to Request for Additional Information Regarding Sequoyah Nuclear Plant (Sqn), Units 1 and 2 and Watts Bar Nuclear Plant (Wbn), Units 1 and 2, American Society of Mechanical Engineers Operation and Maintenance Code, Request for Al2022-09-0202 September 2022 Response to Request for Additional Information Regarding Sequoyah Nuclear Plant (Sqn), Units 1 and 2 and Watts Bar Nuclear Plant (Wbn), Units 1 and 2, American Society of Mechanical Engineers Operation and Maintenance Code, Request for Alte CNL-22-053, Response to Request for Additional Information Regarding Application to Revise Sequoyah Nuclear Plant Units 1 and 2 Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis - Second Partial Response to Additional Requ2022-08-22022 August 2022 Response to Request for Additional Information Regarding Application to Revise Sequoyah Nuclear Plant Units 1 and 2 Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis - Second Partial Response to Additional Reques CNL-22-077, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2022-08-11011 August 2022 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 2024-09-24
[Table view] |
Text
Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 CNL-16-111 December 23, 2016 10 CFR 50.4 10 CFR 50, Appendix H ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Sequoyah Nuclear Plant, Unit 2 Renewed Facility Operating License No. DPR-79 NRC Docket No. 50-328
Subject:
SEQUOYAH NUCLEAR PLANT - REQUEST TO REVISE THE REACTOR PRESSURE VESSEL SURVEILLANCE CAPSULE WITHDRAWAL SCHEDULE FOR U N I T 2
References:
- 1. NRC letter to TVA, Sequoyah Nuclear Plant, Units 1 and 2 - Revise the Reactor Pressure Vessel Material Surveillance Capsule Withdrawal Schedule due to License Renewal Amendment (TAC Nos. MF0631 and MF0632), dated September 27, 2013
- 2. TVA letter to NRC, Sequoyah Reactor Pressure Vessel Surveillance Capsule Withdrawal Schedule Revision Due to License Renewal Amendment, dated January 10, 2013 The purpose of this letter is to request approval to replace the Sequoyah Nuclear Plant (SQN) Unit 2 S capsule with the SQN Unit 2 W capsule in the approved SQN Unit 2 reactor vessel surveillance capsule withdrawal schedule.
By the Reference 1 letter, NRC provided acceptance of the Tennessee Valley Authority (TVA) revised reactor pressure vessel (RPV) material surveillance specimen withdrawal schedule for SQN, Units 1 and 2. The revised withdrawal schedule was submitted by TVA's Reference 2 letter and supported renewal of SQN, Units 1 and 2 operating licenses for an additional 20 years. The revised schedule was based on relocation of the "S" and "W" surveillance capsules for Unit 2.
The capsule relocations were completed during the Unit 2 end of cycle (EOC) R19. The objective of these relocations was to place surveillance capsules in a leading fluence location
U.S. Nuclear Regulatory Commission CNL-16-111 Page2 December 23, 2016 so that the revised surveillance specimen withdrawal schedule would comply with the expectations of American Society for Testing and Materials (ASTM) E 185-82, NUREG-1801, Revision 2, "Generic Aging Lessons Learned (GALL) Report," and the requirements of 10 CFR 50, Appendix H.
As discussed with NRC staff on November 27, 2015, inspection of the Unit 2 relocated "S" and "W" reactor vessel surveillance capsules identified that the cap of the "S" capsule was damaged and not seated as designed. The "W" capsule was found to be installed as designed with no observable damage. As a result of this inspection, the Unit 2 "S" capsule was removed and stored in the spent fuel pool for potential later re-insertion in the reactor vessel pending examination and repair of the capsule, if needed. TVA proposes that the Unit 2 "W" capsule replace the Unit 2 "S" capsule in the Unit 2 reactor vessel surveillance capsule withdrawal schedule. Technical justification for this change is provided in the Enclosure.
The withdrawal schedule approved by the NRC staff in Reference 1 is unchanged and continues to meet the provisions of the specific regulatory requirements for the License Renewal Rule, 10 CFR Part 54, (i.e., ASTM E 185-82, NUREG-1801 , Revision 2, "Generic Aging Lessons Learned (GALL) Report," and the requirements of 10 CFR 50, Appendix H).
TVA requests approval of this revised schedule by January 31, 2018. If you have any questions regarding this submittal, please contact Mr. Mike McBrearty, Sequoyah Site Licensing Manager at (423) 843-7170.
I declare under penalty of perjury that the foregoing is true and correct. Executed on this 23th day of December 2016.
J. W . Shea Vice President, Nuclear Licensing
Enclosure:
Revision of the Reactor Vessel Material Surveillance Capsule Identified in the Sequoyah Unit 2 Withdrawal Schedule cc: NRC Regional Administrator - Region II NRC Senior Resident Inspector - Sequoyah Nuclear Plant NRR Project Manager - Sequoyah Nuclear Plant
Enclosure Tennessee Valley Authority Sequoyah Nuclear Plant Unit 2 Revision of the Reactor Vessel Material Surveillance Capsule Identified in the Sequoyah Unit 2 Withdrawal Schedule
1. Background
In Reference 1, Tennessee Valley Authority (TVA) proposed a revision to the Sequoyah Nuclear Plant (SQN) Unit 2 Reactor Vessel Surveillance Capsule withdrawal schedule to support renewal of the SQN Unit 2 operating license for an additional 20 years. In Reference 2, TVA responded to an NRC Request for Additional Information (RAI) regarding the Reference 1 proposed schedule change. In Reference 3, the NRC approved the proposed revised reactor vessel material surveillance capsule withdrawal schedule. The NRC review concluded, given that the relocation of the Capsule S and W occurs during the 19th or 20th refueling outage, the revised withdrawal schedule date of the end of cycle (EOC) 27 for the Unit 2 surveillance capsule S is acceptable.
At EOC 19 on Unit 2, Sequoyah relocated Capsules S and W to higher fluence locations. Capsule S was repositioned in accordance with the relocation plan established in Reference 1. The Reference 1 Capsule W relocation plan proposed repositioning the capsule to the location formerly occupied by Capsule X (220-degree location). At EOC 19, Capsule W was repositioned to the location formerly occupied by Capsule U (140-degree location), which is radiologically equivalent to the proposed 220-degree location formerly occupied by the X capsule. Inspection of the Unit 2 reactor vessel at EOC 20 revealed that the cap of the S capsule was damaged.
Consequently, the S capsule was removed from the Unit 2 reactor vessel and stored in the spent fuel pool for potential re-insertion at a later date.
- 2. Proposed Revision To The SQN Unit 2 Reactor Vessel Specimen Withdrawal Plan In Reference 1, TVA proposed that the relocated Unit 2 Capsule S would be withdrawn in the EOC 27 outage with the relocated Unit 2 Capsule W remaining unchanged (Standby). As a result of the damage to the Unit 2 Capsule S, TVA proposes to withdraw Unit 2 Capsule W in the EOC 27 outage as a substitute for the Unit 2 Capsule S proposed in Reference 1. The revised Updated Final Safety Analysis Report (UFSAR) Reactor Vessel Capsule Removal Schedule for SQN Unit 2 is provided in Table 1.
Enclosure
- 3. Technical Justification The Unit 2 Capsule S (4-degree location) and W (184-degree location) were relocated to the locations formerly occupied by Capsules T (40-degree location) and U (140-degree location) respectively in Unit 2 EOC 19 (see SQN UFSAR Figure 5.4.3-3 for capsule location orientation). The 40-degree location and the140-degree location are considered to be radiologically equivalent for future plant operational fluence projections. Tables 2 and 3 presented in the Reference 2 Enclosure are unchanged and are applicable to Capsule W in the relocated position U (140-degree).
Removal of Capsule W at EOC 27 would produce a neutron fluence for Capsule W of 2.78 x 1019 n/cm2 (E>1 MeV) as provided in Reference 2 Table 3. The maximum fluence at the reactor pressure vessel inside diameter for the end of the license renewal period at SQN Unit 2 (52 EFPY) is estimated as 2.57 x 1019 n/cm2 (E>1 MeV) as provided in Reference 2 Table 2. Removal of Unit 2 Capsule W at EOC 27 will result in the fluence on Capsule W exceeding the peak reactor vessel neutron fluence at 60 years of operation, but will not be greater than twice the peak. This withdrawal schedule continues to meet the provisions of the specific regulatory requirements for the License Renewal Rule, 10 CFR Part 54, (i.e., ASTM E 185-82, NUREG-1801, Revision 2, "Generic Aging Lessons Learned (GALL) Report," and the requirements of 10 CFR 50, Appendix H). Therefore, substituting Capsule W for Capsule S in the reactor vessel material surveillance withdrawal plan for SQN Unit 2 is acceptable.
- 4. References
- 1. TVA letter to NRC, Sequoyah Reactor Pressure Vessel Surveillance Capsule Withdrawal Schedule Revision due to License Renewal Amendment, dated January 10, 2013
- 2. TVA letter to NRC, Response to NRC Request for Additional Information Regarding Reactor Pressure Vessel Surveillance Capsule Withdrawal Schedule Revision (TAC Nos. MF0631 and MF0632), dated July 3, 2013
- 3. NRC Letter to TVA, Sequoyah Nuclear Plant, Units 1 and 2 - Revise the Reactor Pressure Vessel Material Surveillance Capsule Withdrawal Schedule due to License Renewal Amendment (TAC Nos. MF0631 and MF0632), dated September 27, 2013
- 4. Westinghouse Report WCAP-17539-NP, Revision 0, Sequoyah Nuclear Plant Units 1 and 2 Time-Limited Aging Analysis on Reactor Vessel Integrity, March 2012
- 5. Westinghouse Report WCAP-17539-NP, Revision 1, Sequoyah Nuclear Plant Units 1 and 2 Time-Limited Aging Analysis on Reactor Vessel Integrity, May 2015
Enclosure Table 1 Proposed FSAR Reactor Vessel Capsule Removal Schedule for Unit 2 Capsule Vessel Location Lead Factor Withdrawal Neutron Number Note (d) Time (EFPY) Fluence (x 1019 n/cm2, E>1.0 MeV)
T 40o 3.11 1.07 (removed) 0.244 U 140o 3.17 2.91 (removed) 0.654 X 220o 3.18 5.36 (removed) 1.16 Y 320o 3.15 10.55 (removed) 2.02 S 4o Note (a) 3.11 Note (a) N/A V 176o 0.94 Standby N/A o
W 184 Note (c) 3.18 EOC 27 2.78 Note (b)
Z 356o 0.94 Standby N/A Notes:
a) Capsule S was relocated from the 4-degree location to the 40-degree location in the Unit 2 EOC 19. It was removed from the Unit 2 reactor vessel at EOC 20 and placed in the spent fuel pool.
b) Value taken from Reference 2, Enclosure Table 3 for Unit 2 EOC 19 relocation (The 40-degree location and the140-degree locations (with Capsule W) are considered to be radiologically equivalent).
c) Capsule W has been relocated from the 184-degree location to the 140-degree location at Unit 2 EOC 19.
d) Values taken from Reference 2, Table 4, except as noted.