LR-N16-0016, Implementation Schedule Change for License Amendment Request Regarding Replacement of Source Range and Intermediate Range Neutron Monitoring Systems
| ML16034A277 | |
| Person / Time | |
|---|---|
| Site: | Salem |
| Issue date: | 02/03/2016 |
| From: | Jamila Perry Public Service Enterprise Group |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| CAC MF6065, CAC MF6066, LAR S15-02, LR-N16-0016 | |
| Download: ML16034A277 (2) | |
Text
PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, NJ 08038-0236 FEB 3 2016 LR-N16-0016 LAR S15-02 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Salem Nuclear Generating Station Units 1 and 2 Renewed Facility Operating License Nos. DPR-70 and 75 NRC Docket Nos. 50-272 and 50-311 Ps:<i Nuclear 10 CFR 50.90
Subject:
Implementation Schedule Change for License Amendment Request Regarding Replacement Of Source Range And Intermediate Range Neutron Monitoring Systems (CAC NOS. MF6065 AND MF6066)
References
- 1. PSEG letter to NRC, "License Amendment Request Regarding Replacement of Source Range and Intermediate Range Neutron Monitoring Systems,"
dated April 3, 2015 (ADAMS Accession No. ML15093A291)
In the Reference 1 letter, PSEG Nuclear LLC (PSEG) submitted a license amendment request (LAR) for Salem Nuclear Generating Station (Salem), Units 1 and 2. The proposed amendment would revise Technical Specifications (TS) 3/4.3.1, Reactor Trip System, to support the replacement of the existing source range (SR) and intermediate range (IR) nuclear instrumentation.
PSEG requested NRC approval of the proposed LAR by April 3, 2016, to support planned modifications to replace the existing SR and IR nuclear instrumentation. PSEG also requested a staggered implementation with the Salem Unit 1 implementation during the spring 2016 refueling outage (1 R24) and the Salem Unit 2 implementation during the spring 2017 refueling outage (2R22).
PSEG has re-assessed the work scope for the Salem 1 R24 outage and determined that the replacement of the source range and intermediate detectors is going to be moved from the 1 R24 outage to the fall 2017 (1 R25) refueling outage. Based on this decision PSEG is updating the implementation schedule requested in Reference 1.
PSEG is requesting a staggered implementation with the Salem Unit 1 implementation during the fall 2017 refueling outage (1 R25) and the Salem Unit 2 implementation during the spring 2017 refueling outage (2R22).
Page 2 LR-N16-0016
}here are no regulatory commitments contained in this letter.
10 CFR 50.90 If you have any questions or require additional information, please contact Mr. Brian Thomas at 856-339-2022.
I declare under penalty of perjury that the foregoing is true and correct.
FEB S 2016 Executed on (date)
Respectfully, r1Lr:
?oh F. Perry U
Site Vice President Salem Nuclear Generating Station cc:
Mr. D. Dorman, Administrator, Region I, NRC Ms. C. Parker, NRC Project Manager, Salem NRC Senior Resident Inspector, Salem Mr. P. Mulligan, Chief, NJBNE Mr. L. Marabella, Corporate Commitment Tracking Coordinator Mr. T. Cachaza, Salem Commitment Tracking Coordinator