MONTHYEARML13121A4592013-06-0505 June 2013 Order Designating an Interim Class of NRC Licensed Facilities That Are Eligible to Apply to the Commission for Authorization to Use the Authority Granted Under the Provisions of Section 161A of the Atomic Energy Act of 1954, as Amended Project stage: Other ML13234A0692013-08-13013 August 2013 Relief Request Serial #13-MN-002, Risk-Informed Inservice Inspection Program Fourth Inservice Inspection Interval Project stage: Request ML13228A2652013-08-14014 August 2013 Independent Spent Fuel Storage Installations Application for Preemption Authority Pursuant to Section 161A of the Atomic Energy Act & License Amendment Request Project stage: Request ML13242A2772013-08-28028 August 2013 Independent Spent Fuel Storage Installation - Amendment Applications 264 and 249, Section 161A Preemption Authority Project stage: Other JAFP-13-0036, Application for Preemption Authority Pursuant to Section 161A of the Atomic Energy Act and License Amendment Request2013-08-30030 August 2013 Application for Preemption Authority Pursuant to Section 161A of the Atomic Energy Act and License Amendment Request Project stage: Request DCL-13-074, ISFSI - License Amendment Request 13-04, Application for U.S. NRC Authorization to Use Preemption Authority Granted Under Provisions of Section 161A of the Atomic Energy Act of 1954, as Amended2013-09-24024 September 2013 ISFSI - License Amendment Request 13-04, Application for U.S. NRC Authorization to Use Preemption Authority Granted Under Provisions of Section 161A of the Atomic Energy Act of 1954, as Amended Project stage: Request ML13277A6762013-10-17017 October 2013 Acceptance of Requested Licensing Action Relief Request 13-MN-002 Risk Informed Inservice Inspection Program, Fourth Inservice Inspection Interval Project stage: Acceptance Review ML14023A8062014-01-30030 January 2014 Request for Additional Information Regarding Relief Request 13-MN-002, Risk-Informed Inservice Inspection Program, Fourth Inservice Inspection Interval (TAC Nos. MF2609&10) Project stage: RAI MNS-14-026, Risk-Informed Inservice Inspection Program Response to Request for Additional Information2014-03-0303 March 2014 Risk-Informed Inservice Inspection Program Response to Request for Additional Information Project stage: Response to RAI ML14093A6772014-05-0101 May 2014 SONGS - Request for Additional Information Concerning Pre-Emption Authority Project stage: RAI NL-14-070, Response to Request for Information for Preemption Authority Pursuant to Section 161A of the Atomic Energy Act and License Amendment Request2014-05-13013 May 2014 Response to Request for Information for Preemption Authority Pursuant to Section 161A of the Atomic Energy Act and License Amendment Request Project stage: Response to RAI ML14188C3482014-07-14014 July 2014 Proposed Relief Request 13-MN-002 Project stage: Other NL-14-077, Revised Response to Request for Information Regarding Entergy'S Application for Section 161A Preemption Authority at Indian Point Energy Center and License Amendment Request (TAC Nos. MF2603, 2604, and 2605)2014-07-24024 July 2014 Revised Response to Request for Information Regarding Entergy'S Application for Section 161A Preemption Authority at Indian Point Energy Center and License Amendment Request (TAC Nos. MF2603, 2604, and 2605) Project stage: Response to RAI NL-15-007, Unit Numbers 1, 2, and 3 - Consent to Confirmatory Orders EA-14-135 and EA-14-136 and Hearing Waiver Form2015-01-16016 January 2015 Unit Numbers 1, 2, and 3 - Consent to Confirmatory Orders EA-14-135 and EA-14-136 and Hearing Waiver Form Project stage: Other ML15182A0172015-10-22022 October 2015 Draft Environmental Assessment (TAC Nos. MF2603-MF2605 and MF2637 - MF2639) Project stage: Draft Other ML14259A2182016-01-0505 January 2016 Issuance of Order and Conforming Amendments Concerning Stand Alone Weapons Preemption Authority Project stage: Approval ML14259A2292016-01-0505 January 2016 Safety Evaluation (Weapons Preemption Authority) Project stage: Approval 2014-01-30
[Table View] |
|
---|
Category:Letter type:NL
MONTHYEARNL-21-034, Notification of Expected Date of Transfer of Ownership of Nuclear Units to Holtec Indian Point 2, LLC and Holtec Indian Point 3, LLC; and Notification of Receipt of All Required Regulatory Approvals2021-05-26026 May 2021 Notification of Expected Date of Transfer of Ownership of Nuclear Units to Holtec Indian Point 2, LLC and Holtec Indian Point 3, LLC; and Notification of Receipt of All Required Regulatory Approvals NL-21-039, Response to Request for Additional Information - License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary2021-05-20020 May 2021 Response to Request for Additional Information - License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary NL-21-033, Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel2021-05-11011 May 2021 Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel NL-21-032, Termination of Emergency Response Data System Feed to the U.S. Nuclear Regulatory Commission at Indian Point Energy Center2021-05-11011 May 2021 Termination of Emergency Response Data System Feed to the U.S. Nuclear Regulatory Commission at Indian Point Energy Center NL-21-005, Cancellation of Commitments Related to Beyond-Design-Basis External Events Seismic and Flooding Actions2021-05-11011 May 2021 Cancellation of Commitments Related to Beyond-Design-Basis External Events Seismic and Flooding Actions NL-21-030, Submittal of 2020 Annual Radiological Environmental Operating Report2021-05-0606 May 2021 Submittal of 2020 Annual Radiological Environmental Operating Report NL-21-027, Registration of Spent Fuel Cask Use2021-04-20020 April 2021 Registration of Spent Fuel Cask Use NL-21-021, Registration of Spent Fuel Cask Use2021-04-19019 April 2021 Registration of Spent Fuel Cask Use NL-21-017, Pre-Notice of Disbursement from Decommissioning Trusts2021-04-0808 April 2021 Pre-Notice of Disbursement from Decommissioning Trusts NL-21-010, Submittal of 2020 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report2021-02-17017 February 2021 Submittal of 2020 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report NL-21-006, Relief Request IP3-ISI-RR-16, Proposed Alternative to American Society of Mechanical Engineers Code Case N-513-4 Inspection Requirement2021-02-10010 February 2021 Relief Request IP3-ISI-RR-16, Proposed Alternative to American Society of Mechanical Engineers Code Case N-513-4 Inspection Requirement NL-21-014, Response to 2nd Round Request for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2021-01-26026 January 2021 Response to 2nd Round Request for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device NL-20-082, Notice of Planned Transfer of Decommissioning Funds2020-12-14014 December 2020 Notice of Planned Transfer of Decommissioning Funds NL-20-081, Pre-Notice of Disbursement from Decommissioning Trusts2020-12-0909 December 2020 Pre-Notice of Disbursement from Decommissioning Trusts NL-20-080, Report in Accordance with 10 CFR 71.95(a) for Failure to Comply with Certificate of Compliance No. 71-93212020-11-19019 November 2020 Report in Accordance with 10 CFR 71.95(a) for Failure to Comply with Certificate of Compliance No. 71-9321 NL-20-079, (IP2 and IP3) - Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic2020-11-12012 November 2020 (IP2 and IP3) - Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic NL-20-077, Submittal of Quality Assurance Program Manual Revision 22020-11-0909 November 2020 Submittal of Quality Assurance Program Manual Revision 2 NL-20-078, Response to Requests for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2020-11-0909 November 2020 Response to Requests for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device NL-20-076, Revision of Commitment Related to Nuclear Reactor Safeguards Interim Compensatory Measure - Section B.5.b Issue Regarding Spent Fuel Dispersal2020-11-0202 November 2020 Revision of Commitment Related to Nuclear Reactor Safeguards Interim Compensatory Measure - Section B.5.b Issue Regarding Spent Fuel Dispersal NL-20-069, One-time Scheduler Exemption Request from 10 CFR 50, Appendix E Biennial Emergency Preparedness Exercise Requirements Due to COVID-19 Public Health Emergency2020-10-0808 October 2020 One-time Scheduler Exemption Request from 10 CFR 50, Appendix E Biennial Emergency Preparedness Exercise Requirements Due to COVID-19 Public Health Emergency NL-20-070, Response to Requests for Additional Information, License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2020-10-0202 October 2020 Response to Requests for Additional Information, License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device NL-20-067, Redacted Version of Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline2020-09-16016 September 2020 Redacted Version of Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline NL-20-064, 10 CFR 50.59(d)(2) Summary Report of Changes, Tests and Experiments2020-09-0101 September 2020 10 CFR 50.59(d)(2) Summary Report of Changes, Tests and Experiments NL-20-060, Status of Remaining Actions for Generic Letter 2004-022020-08-11011 August 2020 Status of Remaining Actions for Generic Letter 2004-02 NL-20-057, Cancellation of Commitment Related to Large Break LOCA Reanalysis2020-07-30030 July 2020 Cancellation of Commitment Related to Large Break LOCA Reanalysis NL-20-0851, 30-Day 10 CFR 21 Notification - Continuously Energized Eaton D26 Relays Could Fail to Deenergize Because of an Organic C3 Insulating Material2020-07-22022 July 2020 30-Day 10 CFR 21 Notification - Continuously Energized Eaton D26 Relays Could Fail to Deenergize Because of an Organic C3 Insulating Material NL-20-051, Submittal of Quality Assurance Program Manual, Revision 1 for the Indian Point Energy Center2020-07-0707 July 2020 Submittal of Quality Assurance Program Manual, Revision 1 for the Indian Point Energy Center NL-20-052, Unsatisfactory 10 CFR 26 Fitness-For-Duty Blind Performance Testing Results2020-07-0707 July 2020 Unsatisfactory 10 CFR 26 Fitness-For-Duty Blind Performance Testing Results NL-20-012, Application to Revise Provisional Operating License and Technical Specifications2020-06-30030 June 2020 Application to Revise Provisional Operating License and Technical Specifications NL-20-050, Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline2020-06-24024 June 2020 Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline NL-20-041, Registration of Unit 3 Spent Fuel Cask Use2020-05-13013 May 2020 Registration of Unit 3 Spent Fuel Cask Use NL-20-042, Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel2020-05-12012 May 2020 Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel NL-20-033, Technical Specifications Proposed Change - Permanently Defueled Technical Specifications2020-04-28028 April 2020 Technical Specifications Proposed Change - Permanently Defueled Technical Specifications NL-20-038, Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline2020-04-23023 April 2020 Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline NL-20-035, Response to Request for Additional Information - Temporary Exemption Request from 10 CFR Appendix R, Section Iii.H Due to COVID-19 Pandemic2020-04-16016 April 2020 Response to Request for Additional Information - Temporary Exemption Request from 10 CFR Appendix R, Section Iii.H Due to COVID-19 Pandemic NL-20-034, Temporary Exemption Request from 10 CFR Appendix R, Section Iii.H Due to COVID-19 Pandemic2020-04-13013 April 2020 Temporary Exemption Request from 10 CFR Appendix R, Section Iii.H Due to COVID-19 Pandemic NL-20-021, Proposed License Amendment to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2020-03-24024 March 2020 Proposed License Amendment to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device NL-20-020, Submittal of 2019 Annual Fitness for Duty Performance Data Report Update2020-02-26026 February 2020 Submittal of 2019 Annual Fitness for Duty Performance Data Report Update NL-20-015, Submittal of 2019 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report2020-02-10010 February 2020 Submittal of 2019 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report NL-20-008, Transmittal of Presentation Slides for Partially Closed Pre-Submittal Meeting to Discuss a Planned License Amendment Request to Replace the Fuel Handling Building Crane2020-01-0606 January 2020 Transmittal of Presentation Slides for Partially Closed Pre-Submittal Meeting to Discuss a Planned License Amendment Request to Replace the Fuel Handling Building Crane NL-19-094, 2018 Annual 10 CFR 50.46 Emergency Core Cooling System Evaluation Changes Report2019-12-16016 December 2019 2018 Annual 10 CFR 50.46 Emergency Core Cooling System Evaluation Changes Report NL-19-084, Application for Order Consenting to Transfers of Control of Licenses and Approving Conforming License Amendments2019-11-21021 November 2019 Application for Order Consenting to Transfers of Control of Licenses and Approving Conforming License Amendments NL-19-093, Proposed Technical Specifications (TS) Changes - Indian Point Nuclear Generating Unit 3 TS SR 3.7.7.2 and TS 3.7.6, Required Action A.12019-11-21021 November 2019 Proposed Technical Specifications (TS) Changes - Indian Point Nuclear Generating Unit 3 TS SR 3.7.7.2 and TS 3.7.6, Required Action A.1 NL-19-092, Request for Rescission of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2019-11-20020 November 2019 Request for Rescission of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) NL-19-043, Request for Partial Exemption from Record Retention Requirements in 10 CFR 50.122019-10-22022 October 2019 Request for Partial Exemption from Record Retention Requirements in 10 CFR 50.12 NL-19-073, Request for Relaxation of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2019-10-22022 October 2019 Request for Relaxation of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) NL-19-078, Supplement to Technical Specifications Proposed Change - Permanently Defueled Technical Specifications2019-10-22022 October 2019 Supplement to Technical Specifications Proposed Change - Permanently Defueled Technical Specifications NL-19-091, Independent Spent Fuel Storage Installation (Isfsi), Registration of Spent Fuel Cask Use2019-10-17017 October 2019 Independent Spent Fuel Storage Installation (Isfsi), Registration of Spent Fuel Cask Use NL-19-090, Registration of Unit 2 Spent Fuel Cask Use2019-10-0909 October 2019 Registration of Unit 2 Spent Fuel Cask Use NL-19-079, 50.59(d)(2) Summary Report of Changes, Tests and Experiments2019-09-26026 September 2019 50.59(d)(2) Summary Report of Changes, Tests and Experiments 2021-05-06
[Table view] |
Text
Enteraqy Nuclear Northeast Indian Point Energy Center Entergy 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249 Tel 914 254 6700 John A Ventosa Site Vice President NL-14-070 May 13, 2014 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk 11545 Rockville Pike, TWFN-2F1 Rockville, MD 20852-2738
SUBJECT:
Response to Request for Information for Preemption Authority Pursuant to Section 161A of the Atomic Energy Act and License Amendment Request (TAC No. MF2603, 2604, and 2605)
Indian Point Unit Numbers 1, 2, and 3 Docket Nos. 50-03, 50-247, 50-286, and 72-51 License Nos. DPR-5, DPR-26 and DPR-64
REFERENCE:
- 1. Entergy Letter, Supplement to Entergy's Application for Section 161A Preemption Authority at Indian Point Energy Center (NL 091), Dated August 20, 2013
- 2. NRC letter, Calvert Cliffs Nuclear Power Plant, Units 1 and 2, Diablo Canyon Nuclear Power Plant, Units 1 and 2, Indian Point Nuclear Generating Unit Nos. 1, 2, and 3, James A. FitzPatrick Nuclear Power Plant, Nine Mile Point Nuclear Power Plant,. Units 1 and 2, R.
E. Ginna Nuclear Power Plant, and San Onofre Nuclear Generating Station, Unites 2 and 3 - Request for Additional Information Concerning Pre-Emption Authority (TAC Nos. MF2621, MF2622, MF2809, MF2810, MF2603, MF2604, MF2605, MF2702, MF2662, MF2663, MF2664, MF2624, MF2625, and MF2623, dated May 1, 2014
Dear Sir or Madam:
In Reference (1), Entergy Nuclear Operations, Inc. (Entergy) submitted an Application to the U.S.
Nuclear Regulatory Commission (NRC) for the Commission to exercise Section 161A preemption authority under 42 U.S.C. 2201 a to expressly permit the use by Entergy security personnel of the
NL-14-070 Docket Nos.50-003, 50-247, 50-286, and 72-51 Page 2 of 2 standard weapons described in Reference 1 at the Indian Point Energy Center (IPEC). In reviewing the application, the NRC determined that additional information was required to complete processing the application (Reference 2). The attachment to this letter provides a response to this request.
There are no new commitments contained in this submittal. If you have any questions regarding this confirmation of receipt, please contact Mr. Robert Walpole, Manager, Regulatory Assurance at (914) 254-6710.
I declare under penalty of perjury that the foregoing is true and correct. Executed on May ._, 2014.
Respectfully, JAV/sp
Attachment:
Response to Request for Additional Information Regarding Pre-emption Authority cc: Mr. Douglas Pickett, Senior Project Manager, NRC NRR DORL Mr. William M. Dean, Regional Administrator, NRC Region 1 NRC Resident Inspectors Office Mr. John B. Rhodes, President and CEO, NYSERDA Ms. Bridget Frymire, New York State Dept. of Public Service
ATTACHMENT TO NL-14-070 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION REGARDING PRE-EMPTION AUTHORITY ENTERGY NUCLEAR OPERATIONS, INC.
INDIAN POINT NUCLEAR GENERATING UNIT NOS. 1, 2, AND 3 DOCKET Nos. 50-03, 50-247, 50-286, and 72-51
NL-14-070 Docket Nos.50-003, 50-247, 50-286, and 72-51 Attachment Page 1 of 3 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION REGARDING PRE-EMPTION AUTHORITY NRC Question 1 On June 5, 2013, the NRC issued Order EA-13-092 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML13121A459) (the Order) designating certain NRC licensed facilities as eligible to request pre-emption authority. Attachment 3 of the.Order contained requirements in support of conducting firearms background checks. Verification that these items are complete or will be completed prior to implementation of pre-emption authority, should it be granted, is required.
- a. Address whether the site training and qualification program has been revised, or is being revised, to provide each individual with instructions on identifying events or status that would disqualify the individual from possession or use of firearms and the continuing responsibility of each individual to promptly notify the licensee of the occurrence of any such event or status. If the training and qualification program is not being revised, provide an explanation why and/or identify the existing security plan or site procedure that contains the appropriate instructions.
- b. Verify that either the security plan and/or associated security procedures currently require or shall require, for the purpose of assuring correct and complete information, that the licensee shall provide to each individual the contents of records obtained from the Federal Bureau of Investigation (FBI) before making any final adverse determination. If the security plan and/or associated security procedures are not being revised, provide an explanation why and/or identify the existing security plan or site procedure that contains the appropriate instructions.
- c. Verify that either the security plan and/or associated security procedures currently require or shall require that confirmation of receipt by the individual of the contents of records obtained from the FBI must be maintained by the licensee for a period of 5 years from the date of the notification. If the security plan and/or associated security procedures are not being revised, provide an explanation why and/or identify the existing security plan or site procedure that contains the appropriate instructions.
- d. Verify that either the security plan and/or associated security procedures currently require or shall require the retention of a copy of all information submitted and received for firearms background checks for a minimum of 5 years after the information is superseded through periodic reinvestigation or the termination of an individual's access to firearms. If the security plan and/or associated security procedures are not being revised, provide an explanation why and/or identify the existing security plan or site procedure that contains the appropriate instructions.
- e. Verify that either the security plan and/or associated security procedures currently require or shall require that as of 180 days after the effective date of
NL-14-070 Docket Nos.50-003, 50-247, 50-286, and 72-51 Attachment Page 2 of 3 Commission Order EA-13-092, which was December 22, 2013, the licensee shall not assign any individual to any armed duties unless the individual has completed a satisfactory firearms background check. If the security plan and/or associated security procedures are not being revised, provide an explanation why and/or identify the existing security plan or site procedure that contains the appropriate instructions.
- f. Verify that either the security plan and/or associated security procedures currently require or shall require that the licensee remove from armed duties, without delay, any individual who has received a "denied" response from the FBI and that the licensee may return an individual to armed duties only after the individual receives a "proceed" response from the FBI, subsequent to receiving a "delayed" or "denied" response. If the security plan and/or associated security procedures are not being revised, provide an explanation why and/or identify the existing security plan or site procedure that contains the appropriate instructions.
- g. Verify that either the security plan and/or associated security procedures currently require or shall require that all personnel subject to a firearms background check be provided with instructions for appealing "delayed" or "denied" responses and that these instructions will continue to be provided to all personnel subject to a firearms background check. If the security plan and/or associated security procedures are not being revised, provide an explanation why and/or identify the existing security plan or site procedure that contains the appropriate instructions.
- h. Verify that either the security plan and/or associated security procedures currently require or shall require all personnel subject to a firearms background check to notify the licensee's security management within 3 working days of the occurrence or existence of any disqualifying event or status. If the security plan and/or associated security procedures are not being revised, provide an explanation why and/or identify the existing security plan or site procedure that contains the appropriate instructions.
Verify that either the security plan and/or associated security procedures currently require or shall require that the licensee remove from armed duties, without delay, any individual for whom disqualifying information has become known or where a satisfactory firearms background check re-investigation has not been completed. If the security plan and/or associated security procedures are not being revised, provide an explanation why and/or identify the existing security plan or site procedure that contains the appropriate instructions.
- j. Confirm that the removal from armed duties of any individual for whom disqualifying information has become known or where a satisfactory firearms background check re-investigation has not been completed, will be completed within the timeframe specified for reconstitution of the minimum security organization staffing levels described in the licensee's current NRC-approved security plans, or sooner if practicable. If the security plan and/or associated security procedures are not being revised, provide an explanation why and/or
NL-14-070 Docket Nos.50-003, 50-247, 50-286, and 72-51 Attachment Page 3 of 3 identify the existing security plan or site procedure that contains the appropriate instructions.
- k. Verify that either the security plan and/or associated security procedures currently require or shall require that all individuals who require access to firearms as part of their official duties complete a periodic firearms background check re-investigation at least once every 5 years, following the initial or most recent satisfactory firearms background check. If the security plan and/or associated security procedures are not being revised, provide an explanation why and/or identify the existing security plan or site procedure that contains the appropriate instructions.
- 1. Verify that either the security plan and/or associated security procedures currently require or shall require that the licensee shall complete a "new" firearms background check or reinvestigation for all individuals who have had a break in employment of greater than 7 consecutive calendar days or who have transferred to the employment of the licensee or the licensee's contractor. If the security plan and/or associated security procedures are not being revised, provide an explanation why and/or identify the existing security plan or site procedure that contains the appropriate instructions.
- m. Verify that either the security plan and/or associated security procedures currently require or shall require that the licensee will notify the NRC Headquarters Operations Center by telephone within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> after removing an individual from armed duties as a result of the discovery of any disqualifying status or event. If the security plan and/or associated security procedures are not being revised, provide an explanation why and/or identify the existing security plan or site procedure that contains the appropriate instructions.
Response
A new Indian Point Energy Center procedure is being developed to implement the preemption authority requirements in the NRC question. This new procedure will be formally implemented when NRC approves that preemption authority. Current requirements would cause IPEC to take some of the indicated actions prior to development of this procedure even though preemption has not been approved.