License Amendment Request - LAR-13-01414, License Amendment Request to Change the Completion Date of Implementation Milestone 8 Response to Request for Additional Information
ML13358A308
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 12/20/2013
From: Gatlin T
SCANA Corp, South Carolina Electric & Gas Co
To: Shawn Williams
Document Control Desk, Office of Nuclear Reactor Regulation
References
LAR-13-01414, RC-13-0188, TAC ME2899
Download: ML13358A308 (2)


Text

Security - Related Information -

Thomas D. Gatlin Withhold Under 10 CFR 2.390 Vice President, Nuclear Operations "Cyber Sensitive" 803.345.4342 A SCANA COMPANY December 20, 2013 RC-13-0188 U.S. Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555-0001 Attn: S. A. Williams

Dear Sir or Madam:

Subject:

VIRGIL C. SUMMER NUCLEAR STATION (VCSNS) UNIT I DOCKET NO. 50-395 OPERATING LICENSE NO. NPF-12 LICENSE AMENDMENT REQUEST - LAR-1 3-01414 LICENSE AMENDMENT REQUEST TO CHANGE THE COMPLETION DATE OF IMPLEMENTATION MILESTONE 8 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION

References:

1. Thomas D. Gatlin, SCE&G, Letter to the Document Control Desk, "Change of the Completion Date of Implementation Milestone 8" dated October 3, 2013 (RC-13-0134) [ML13281A193]
2. Shawn Williams, NRC, Letter to Thomas D. Gatlin, SCE&G, "Virgil C. Summer Nuclear Station, Unit No. 1 (VCSNS) - Request for Additional Information, Issuance of Amendment Regarding Cyber Security Plan" dated November 21, 2013 [TAC NO. ME2899]

South Carolina Electric & Gas Company (SCE&G), acting for itself and as agent for South Carolina Public Service Authority pursuant to 10 CFR 50.90, submitted a License Amendment Request (LAR) per Reference 1 to request a change of the completion date of Implementation Milestone 8. NRC review and audit of this request determined that additional information was required and a Request for Additional Information (RAI) was issued per Reference 2. Attachment 1 of this letter provides SCE&G's response to the RAIs.

If you have any questions about this submittal, please contact Mr. Bruce L. Thompson at (803) 931-5042.

Attachments transmitted herewith contain security related information to be withheld under 10 CFR 2.390. When separated from these Attachments, this transmittal Document is decontrolled.

Virgil C. Summer Station - Post Office Box 88 -Jenkinsville, SC. 29065. F (803) 941-9776

Document Control Desk CR-I13-01414 RC-13-0188 Page 2 of 2 I certify under penalty of perjury that the foregoing is correct and true.

12 0 -ze;,/ 3 2,41, it, JIR-Executed on Thomas D. Gatlin RLP/TDG/

Attachments:

1.

Request for Additional Information (RAI), Issuance of Amendment Regarding Cyber Security Plan

2.

Cyber Security Related Corrective Action Program Entries List c:

Without Attachments unless noted K. B. Marsh S. A. Byrne J. B. Archie N. S. Cams J. H. Hamilton J. W. Williams W. M. Cherry V. M. McCree (with Attachments)

S. A. Williams (with Attachments)

NRC Resident Inspector S. E. Jenkins Paulette Ledbetter K. M. Sutton NSRC RTS (CR-13-01414)

File (813.20)

PRSF (RC-13-0188) (with Attachments)