LR-N13-0031, PSEG Nuclear LLC - Overall Integrated Plan for Hope Creek in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12

From kanterella
(Redirected from ML13059A272)
Jump to navigation Jump to search
PSEG Nuclear LLC - Overall Integrated Plan for Hope Creek in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-04
ML13059A272
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 02/27/2013
From: Jamila Perry
Public Service Enterprise Group
To:
Office of Nuclear Reactor Regulation, Document Control Desk
References
LR-N13-0031, EA-12-049
Download: ML13059A272 (3)


Text

PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, NJ 08038-0236 FEB 2 7 2013 Order EA-12-049 LR-N13-0031 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Hope Creek Generating Station Renewed Facility Operating License No. NPF-57 NRC Docket No. 50-354

Subject:

PSEG Nuclear LLC's Overall Integrated Plan for the Hope Creek Generating Station in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)

References:

1. NRC Order Number EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," dated March 12, 2012.
2. NRC Interim Staff Guidance JLD-ISG-2012-01, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," .

Revision 0, dated August 29, 2012.

3. NEI 12-06, "Diverse and Flexible Coping Strategies (FLEX)

Implementation Guide," Revision 0, dated August, 2012.

4. PSEG Letter LR-N12-0329, "PSEG Nuclear LLC's Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)," dated October 31, 2012.

On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued an order (Reference 1) to PSEG Nuclear LLC (PSEG). Reference 1 was immediately effective and directs PSEG to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in

LR-N 13-0031 Order EA-12-049 Page2 the event of a beyond-design-basis external event. Specific requirements are outlined in Attachment 2 of Reference 1.

Reference 1 requires submission of an Overall Integrated Plan by February 28, 2013.

The NRC Interim Staff Guidance (ISG) (Reference 2) was issued August 29, 2012, and endorses industry guidance document NEI 12-06, Revision 0 (Reference 3) with clarifications and exceptions identified in Reference 2. Reference 3 provides direction regarding the content of this Overall Integrated Plan.

Reference 4 provided PSEG's initial status report regarding mitigation strategies, as required by Reference 1.

The purpose of this letter is to provide the Overall Integrated Plan pursuant to Section IV, Condition C.1, of Reference 1. This letter confirms that PSEG has received Reference 2 and has an Overall Integrated Plan for the Hope Creek Generating Station, developed in accordance with the guidance for defining and deploying strategies that will enhance the ability to cope with conditions resulting from beyond-design-basis external events.

The information in Enclosure 1 provides the Hope Creek Generating Station Overall Integrated Plan for mitigation strategies pursuant to Reference 3. The attached Overall Integrated Plan is based on conceptual design information. Final design details and associated procedure guidance, as well as any revisions to the information contained in Enclosure 1, will be provided in the 6-month Integrated Plan updates required by Reference 1.

There are no regulatory commitments contained in this letter.

If you have* any questions or require additional information, please do not hesitate to contact Mrs. Emily Bauer at 856-339-1023.

I declare under penalty of perjury that the foregoing is true and correct.

Executed on J - '7 ~1 (Date)

Sincerely, cJr!!- F.~

John F. Perry U Site Vice President Hope Creek Generating Station

FEB 2 7 2013 LR-N13-0031 Order EA-12-049 Page 3 Enclosure 1 - PSEG Nuclear LLC Mitigation Strategies for Beyond Design Basis External Events, EA-12-049 Overall Integrated Plan Response, Hope Creek Generating Station cc: Mr. E. Leeds, Director of Office of Nuclear Reactor Regulation Mr. W. Dean, Administrator, Region I, NRC Mr. J. Hughey, Project Manager, NRC NRC Senior Resident Inspector, Hope Creek Mr. P. Mulligan, Manager IV, NJBNE Hope Creek Commitment Tracking Coordinator PSEG Corporate Commitment Coordinator