|
---|
Category:Decommissioning Funding Plan DKTs 30
MONTHYEARML23095A0572023-03-29029 March 2023 NRC Decommissioning Funding Status Report December 31, 2022 ML21362A4062021-12-17017 December 2021 Independent Spent Fuel Storage Installation (Isfsi), Submittal of Decommissioning Funding Plan Update PLA-7972, Independent Spent Fuel Storage Installation (Isfsi), Decommissioning Funding Plan, Updated2021-12-13013 December 2021 Independent Spent Fuel Storage Installation (Isfsi), Decommissioning Funding Plan, Updated PLA-7923, NRC Decommissioning Funding Status Report2021-03-31031 March 2021 NRC Decommissioning Funding Status Report ML21099A1082021-03-29029 March 2021 NRC Decommissioning Funding Status Report PLA-7778, NRC Decommissioning Funding Status Report2019-04-0101 April 2019 NRC Decommissioning Funding Status Report ML19107A0312019-03-29029 March 2019 NRC Decommissioning Funding Status Report ML18354A7442018-12-17017 December 2018 Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Funding Plan, Updated PLA-7761, Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Funding Plan, Updated (PLA-7761)2018-12-13013 December 2018 Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Funding Plan, Updated (PLA-7761) PLA-7584, NRC Decommissioning Funding Status Report for 12/31/20162017-03-30030 March 2017 NRC Decommissioning Funding Status Report for 12/31/2016 ML17089A6562017-03-30030 March 2017 NRC Decommissioning Fund Status Report ML17102B4162017-03-29029 March 2017 NRC Decommissioning Funding Status Report ML16032A3392016-01-0808 January 2016 ISFSI - Decommissioning Funding Plan, Updated PLA-7424, ISFSI Decommissioning Funding Plan2015-12-16016 December 2015 ISFSI Decommissioning Funding Plan ML15091A3072015-03-25025 March 2015 NRC Decommissioning Funding Status Report PLA-7293, NRC Decommissioning Funding Status Report2015-03-20020 March 2015 NRC Decommissioning Funding Status Report ML13095A0102013-03-28028 March 2013 NRC Decommissioning Funding Status Report PLA-6979, NRC Decommissioning Funding Status Report2013-03-25025 March 2013 NRC Decommissioning Funding Status Report PLA-6951, Decommissioning Funding Plan for the Independent Spent Fuel Storage Installation2012-12-15015 December 2012 Decommissioning Funding Plan for the Independent Spent Fuel Storage Installation ML11109A0462011-04-11011 April 2011 Decommissioning Report of Financial Assurance ML0909206012009-03-26026 March 2009 Susquehanna Steam Electric Station, Decommissioning Report of Financial Assurance, PLA-6491 PLA-6491, Attachment 2 to PLA-6491, Affidavit and Site-Specific Decommissioning Cost Analysis Schedules2009-03-26026 March 2009 Attachment 2 to PLA-6491, Affidavit and Site-Specific Decommissioning Cost Analysis Schedules ML0909104062009-03-25025 March 2009 Decommissioning Report of Financial Assurance PLA-6171, Decommissioning Report of Financial Assurance2007-03-23023 March 2007 Decommissioning Report of Financial Assurance ML0709402772007-03-21021 March 2007 Decommissioning Report of Financial Assurance ML0510301712005-03-31031 March 2005 Decommissioning Report of Financial, Assurance ML0309300662003-03-28028 March 2003 Decommissioning Report of Financial Assurance ML0309300352003-03-28028 March 2003 Decommissioning Report of Financial Assurance ML0309300322003-03-28028 March 2003 Decommissioning Report of Financial Assurance ML0309300292003-03-28028 March 2003 Decommissioning Report of Financial Assurance ML0309300212003-03-28028 March 2003 Decommissioning Report of Financial Assurance PLA-5596, Decommissioning Report of Financial Assurance, PLA-55962003-03-21021 March 2003 Decommissioning Report of Financial Assurance, PLA-5596 2023-03-29
[Table view] Category:40
MONTHYEARML23095A0572023-03-29029 March 2023 NRC Decommissioning Funding Status Report December 31, 2022 ML21362A4062021-12-17017 December 2021 Independent Spent Fuel Storage Installation (Isfsi), Submittal of Decommissioning Funding Plan Update PLA-7972, Independent Spent Fuel Storage Installation (Isfsi), Decommissioning Funding Plan, Updated2021-12-13013 December 2021 Independent Spent Fuel Storage Installation (Isfsi), Decommissioning Funding Plan, Updated PLA-7923, NRC Decommissioning Funding Status Report2021-03-31031 March 2021 NRC Decommissioning Funding Status Report ML21099A1082021-03-29029 March 2021 NRC Decommissioning Funding Status Report PLA-7778, NRC Decommissioning Funding Status Report2019-04-0101 April 2019 NRC Decommissioning Funding Status Report ML19107A0312019-03-29029 March 2019 NRC Decommissioning Funding Status Report ML18354A7442018-12-17017 December 2018 Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Funding Plan, Updated PLA-7761, Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Funding Plan, Updated (PLA-7761)2018-12-13013 December 2018 Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Funding Plan, Updated (PLA-7761) PLA-7584, NRC Decommissioning Funding Status Report for 12/31/20162017-03-30030 March 2017 NRC Decommissioning Funding Status Report for 12/31/2016 ML17089A6562017-03-30030 March 2017 NRC Decommissioning Fund Status Report ML17102B4162017-03-29029 March 2017 NRC Decommissioning Funding Status Report ML16032A3392016-01-0808 January 2016 ISFSI - Decommissioning Funding Plan, Updated PLA-7424, ISFSI Decommissioning Funding Plan2015-12-16016 December 2015 ISFSI Decommissioning Funding Plan ML15091A3072015-03-25025 March 2015 NRC Decommissioning Funding Status Report PLA-7293, NRC Decommissioning Funding Status Report2015-03-20020 March 2015 NRC Decommissioning Funding Status Report ML13095A0102013-03-28028 March 2013 NRC Decommissioning Funding Status Report PLA-6979, NRC Decommissioning Funding Status Report2013-03-25025 March 2013 NRC Decommissioning Funding Status Report ML13032A0562012-12-17017 December 2012 Amended Susquehanna Steam Electric Station Decommissioning Funding Plan for the Independent Spent Fuel Storage Installation PLA-6951, Decommissioning Funding Plan for the Independent Spent Fuel Storage Installation2012-12-15015 December 2012 Decommissioning Funding Plan for the Independent Spent Fuel Storage Installation ML11109A0462011-04-11011 April 2011 Decommissioning Report of Financial Assurance ML0909206012009-03-26026 March 2009 Susquehanna Steam Electric Station, Decommissioning Report of Financial Assurance, PLA-6491 PLA-6491, Attachment 2 to PLA-6491, Affidavit and Site-Specific Decommissioning Cost Analysis Schedules2009-03-26026 March 2009 Attachment 2 to PLA-6491, Affidavit and Site-Specific Decommissioning Cost Analysis Schedules ML0909104062009-03-25025 March 2009 Decommissioning Report of Financial Assurance PLA-6171, Decommissioning Report of Financial Assurance2007-03-23023 March 2007 Decommissioning Report of Financial Assurance ML0709402772007-03-21021 March 2007 Decommissioning Report of Financial Assurance ML0510301712005-03-31031 March 2005 Decommissioning Report of Financial, Assurance PLA-5774, Decommissioning Survey Report for Ppl'S Former Corporate Dosimety Laboratory Location PLA-57742004-06-29029 June 2004 Decommissioning Survey Report for Ppl'S Former Corporate Dosimety Laboratory Location PLA-5774 ML0309300662003-03-28028 March 2003 Decommissioning Report of Financial Assurance ML0309300352003-03-28028 March 2003 Decommissioning Report of Financial Assurance ML0309300322003-03-28028 March 2003 Decommissioning Report of Financial Assurance ML0309300292003-03-28028 March 2003 Decommissioning Report of Financial Assurance ML0309300212003-03-28028 March 2003 Decommissioning Report of Financial Assurance PLA-5596, Decommissioning Report of Financial Assurance, PLA-55962003-03-21021 March 2003 Decommissioning Report of Financial Assurance, PLA-5596 ML0315305472003-02-28028 February 2003 Decommissioning Plan for the Quehanna, Pennsylvania Site, Pennsylvania Historical & Museum Commission Attachment 2023-03-29
[Table view] Category:50
MONTHYEARML23095A0572023-03-29029 March 2023 NRC Decommissioning Funding Status Report December 31, 2022 ML21362A4062021-12-17017 December 2021 Independent Spent Fuel Storage Installation (Isfsi), Submittal of Decommissioning Funding Plan Update PLA-7972, Independent Spent Fuel Storage Installation (Isfsi), Decommissioning Funding Plan, Updated2021-12-13013 December 2021 Independent Spent Fuel Storage Installation (Isfsi), Decommissioning Funding Plan, Updated PLA-7923, NRC Decommissioning Funding Status Report2021-03-31031 March 2021 NRC Decommissioning Funding Status Report ML21099A1082021-03-29029 March 2021 NRC Decommissioning Funding Status Report PLA-7778, NRC Decommissioning Funding Status Report2019-04-0101 April 2019 NRC Decommissioning Funding Status Report ML19107A0312019-03-29029 March 2019 NRC Decommissioning Funding Status Report ML18354A7442018-12-17017 December 2018 Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Funding Plan, Updated PLA-7761, Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Funding Plan, Updated (PLA-7761)2018-12-13013 December 2018 Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Funding Plan, Updated (PLA-7761) PLA-7584, NRC Decommissioning Funding Status Report for 12/31/20162017-03-30030 March 2017 NRC Decommissioning Funding Status Report for 12/31/2016 ML17089A6562017-03-30030 March 2017 NRC Decommissioning Fund Status Report ML17102B4162017-03-29029 March 2017 NRC Decommissioning Funding Status Report ML16032A3392016-01-0808 January 2016 ISFSI - Decommissioning Funding Plan, Updated PLA-7424, ISFSI Decommissioning Funding Plan2015-12-16016 December 2015 ISFSI Decommissioning Funding Plan ML15091A3072015-03-25025 March 2015 NRC Decommissioning Funding Status Report PLA-7293, NRC Decommissioning Funding Status Report2015-03-20020 March 2015 NRC Decommissioning Funding Status Report ML13095A0102013-03-28028 March 2013 NRC Decommissioning Funding Status Report PLA-6979, NRC Decommissioning Funding Status Report2013-03-25025 March 2013 NRC Decommissioning Funding Status Report ML13032A0562012-12-17017 December 2012 Amended Susquehanna Steam Electric Station Decommissioning Funding Plan for the Independent Spent Fuel Storage Installation PLA-6951, Decommissioning Funding Plan for the Independent Spent Fuel Storage Installation2012-12-15015 December 2012 Decommissioning Funding Plan for the Independent Spent Fuel Storage Installation ML11109A0462011-04-11011 April 2011 Decommissioning Report of Financial Assurance ML0909206012009-03-26026 March 2009 Susquehanna Steam Electric Station, Decommissioning Report of Financial Assurance, PLA-6491 PLA-6491, Attachment 2 to PLA-6491, Affidavit and Site-Specific Decommissioning Cost Analysis Schedules2009-03-26026 March 2009 Attachment 2 to PLA-6491, Affidavit and Site-Specific Decommissioning Cost Analysis Schedules ML0909104062009-03-25025 March 2009 Decommissioning Report of Financial Assurance PLA-6171, Decommissioning Report of Financial Assurance2007-03-23023 March 2007 Decommissioning Report of Financial Assurance ML0709402772007-03-21021 March 2007 Decommissioning Report of Financial Assurance ML0510301712005-03-31031 March 2005 Decommissioning Report of Financial, Assurance PLA-5774, Decommissioning Survey Report for Ppl'S Former Corporate Dosimety Laboratory Location PLA-57742004-06-29029 June 2004 Decommissioning Survey Report for Ppl'S Former Corporate Dosimety Laboratory Location PLA-5774 ML0309300662003-03-28028 March 2003 Decommissioning Report of Financial Assurance ML0309300352003-03-28028 March 2003 Decommissioning Report of Financial Assurance ML0309300322003-03-28028 March 2003 Decommissioning Report of Financial Assurance ML0309300292003-03-28028 March 2003 Decommissioning Report of Financial Assurance ML0309300212003-03-28028 March 2003 Decommissioning Report of Financial Assurance PLA-5596, Decommissioning Report of Financial Assurance, PLA-55962003-03-21021 March 2003 Decommissioning Report of Financial Assurance, PLA-5596 ML0315305472003-02-28028 February 2003 Decommissioning Plan for the Quehanna, Pennsylvania Site, Pennsylvania Historical & Museum Commission Attachment 2023-03-29
[Table view] Category:70
MONTHYEARML23095A0572023-03-29029 March 2023 NRC Decommissioning Funding Status Report December 31, 2022 ML21362A4062021-12-17017 December 2021 Independent Spent Fuel Storage Installation (Isfsi), Submittal of Decommissioning Funding Plan Update PLA-7972, Independent Spent Fuel Storage Installation (Isfsi), Decommissioning Funding Plan, Updated2021-12-13013 December 2021 Independent Spent Fuel Storage Installation (Isfsi), Decommissioning Funding Plan, Updated PLA-7923, NRC Decommissioning Funding Status Report2021-03-31031 March 2021 NRC Decommissioning Funding Status Report ML21099A1082021-03-29029 March 2021 NRC Decommissioning Funding Status Report PLA-7778, NRC Decommissioning Funding Status Report2019-04-0101 April 2019 NRC Decommissioning Funding Status Report ML19107A0312019-03-29029 March 2019 NRC Decommissioning Funding Status Report ML18354A7442018-12-17017 December 2018 Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Funding Plan, Updated PLA-7761, Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Funding Plan, Updated (PLA-7761)2018-12-13013 December 2018 Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Funding Plan, Updated (PLA-7761) PLA-7584, NRC Decommissioning Funding Status Report for 12/31/20162017-03-30030 March 2017 NRC Decommissioning Funding Status Report for 12/31/2016 ML17089A6562017-03-30030 March 2017 NRC Decommissioning Fund Status Report ML17102B4162017-03-29029 March 2017 NRC Decommissioning Funding Status Report ML16032A3392016-01-0808 January 2016 ISFSI - Decommissioning Funding Plan, Updated PLA-7424, ISFSI Decommissioning Funding Plan2015-12-16016 December 2015 ISFSI Decommissioning Funding Plan ML15091A3072015-03-25025 March 2015 NRC Decommissioning Funding Status Report PLA-7293, NRC Decommissioning Funding Status Report2015-03-20020 March 2015 NRC Decommissioning Funding Status Report ML13095A0102013-03-28028 March 2013 NRC Decommissioning Funding Status Report PLA-6979, NRC Decommissioning Funding Status Report2013-03-25025 March 2013 NRC Decommissioning Funding Status Report ML13032A0562012-12-17017 December 2012 Amended Susquehanna Steam Electric Station Decommissioning Funding Plan for the Independent Spent Fuel Storage Installation PLA-6951, Decommissioning Funding Plan for the Independent Spent Fuel Storage Installation2012-12-15015 December 2012 Decommissioning Funding Plan for the Independent Spent Fuel Storage Installation ML11109A0462011-04-11011 April 2011 Decommissioning Report of Financial Assurance ML0909206012009-03-26026 March 2009 Susquehanna Steam Electric Station, Decommissioning Report of Financial Assurance, PLA-6491 PLA-6491, Attachment 2 to PLA-6491, Affidavit and Site-Specific Decommissioning Cost Analysis Schedules2009-03-26026 March 2009 Attachment 2 to PLA-6491, Affidavit and Site-Specific Decommissioning Cost Analysis Schedules ML0909104062009-03-25025 March 2009 Decommissioning Report of Financial Assurance PLA-6171, Decommissioning Report of Financial Assurance2007-03-23023 March 2007 Decommissioning Report of Financial Assurance ML0709402772007-03-21021 March 2007 Decommissioning Report of Financial Assurance ML0510301712005-03-31031 March 2005 Decommissioning Report of Financial, Assurance PLA-5774, Decommissioning Survey Report for Ppl'S Former Corporate Dosimety Laboratory Location PLA-57742004-06-29029 June 2004 Decommissioning Survey Report for Ppl'S Former Corporate Dosimety Laboratory Location PLA-5774 ML0309300662003-03-28028 March 2003 Decommissioning Report of Financial Assurance ML0309300352003-03-28028 March 2003 Decommissioning Report of Financial Assurance ML0309300322003-03-28028 March 2003 Decommissioning Report of Financial Assurance ML0309300292003-03-28028 March 2003 Decommissioning Report of Financial Assurance ML0309300212003-03-28028 March 2003 Decommissioning Report of Financial Assurance PLA-5596, Decommissioning Report of Financial Assurance, PLA-55962003-03-21021 March 2003 Decommissioning Report of Financial Assurance, PLA-5596 ML0315305472003-02-28028 February 2003 Decommissioning Plan for the Quehanna, Pennsylvania Site, Pennsylvania Historical & Museum Commission Attachment 2023-03-29
[Table view] Category:Letter type:PLA
MONTHYEARPLA-8096, Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval2024-01-0404 January 2024 Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval PLA-8077, Emergency Plan Revision 67 (PLA-8077)2023-12-27027 December 2023 Emergency Plan Revision 67 (PLA-8077) PLA-8089, Submittal of Revision to Inservice Testing Program Plan2023-12-0505 December 2023 Submittal of Revision to Inservice Testing Program Plan PLA-8084, Application to Revise Technical Specifications to Adopt TSTF-568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.22023-11-29029 November 2023 Application to Revise Technical Specifications to Adopt TSTF-568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 PLA-8091, Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inseervice Inspection Interval (PLA-8091)2023-11-0808 November 2023 Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inseervice Inspection Interval (PLA-8091) PLA-8082, Proposed Amendment to Licenses NPF-14 and NPF-22: Application to Revise Technical Specifications to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program2023-11-0202 November 2023 Proposed Amendment to Licenses NPF-14 and NPF-22: Application to Revise Technical Specifications to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program PLA-8080, Proposed Relief for Valve 251130 (PLA-8080)2023-08-14014 August 2023 Proposed Relief for Valve 251130 (PLA-8080) PLA-8074, Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval2023-08-0303 August 2023 Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval PLA-8076, Unit 2 - 21st Refueling Outage Owner'S Activity Report (PLA-8076)2023-07-20020 July 2023 Unit 2 - 21st Refueling Outage Owner'S Activity Report (PLA-8076) PLA-8078, Submittal of Unit 2 Cycle 22 Core Operating Limits Report, Revision 1, PLA-80782023-07-0505 July 2023 Submittal of Unit 2 Cycle 22 Core Operating Limits Report, Revision 1, PLA-8078 PLA-8054, Proposed Amendment to Licenses NPF-14 and NPF-22: Remove Control Rod Operability Separation Criteria and Replace Reference to Banked Position Withdrawal Sequence with the Analyzed Rod Position Sequence2023-06-0808 June 2023 Proposed Amendment to Licenses NPF-14 and NPF-22: Remove Control Rod Operability Separation Criteria and Replace Reference to Banked Position Withdrawal Sequence with the Analyzed Rod Position Sequence PLA-8073, Proposed Relief Request for the Fifth 10-Year Inservice Inspection Interval2023-06-0101 June 2023 Proposed Relief Request for the Fifth 10-Year Inservice Inspection Interval PLA-8067, Notification of Completion of Emergence from Bankruptcy (PLA-8067)2023-05-17017 May 2023 Notification of Completion of Emergence from Bankruptcy (PLA-8067) PLA-8064, Response to NRC Regulatory Issue Summary 2023-01 (PLA-8064)2023-05-17017 May 2023 Response to NRC Regulatory Issue Summary 2023-01 (PLA-8064) PLA-8066, Notification of Planned Closing Date and Information Identified in March 30, 2023 Order, PLA-80662023-05-0808 May 2023 Notification of Planned Closing Date and Information Identified in March 30, 2023 Order, PLA-8066 PLA-8053, Radiation Exposure Information and Reporting System2023-04-27027 April 2023 Radiation Exposure Information and Reporting System PLA-8058, Annual Radiological Environmental Operating Report (PLA-8058)2023-04-26026 April 2023 Annual Radiological Environmental Operating Report (PLA-8058) PLA-8041, Radioactive Effluent Release Report and Offsite Dose Calculation Manual (PLA-8041)2023-04-25025 April 2023 Radioactive Effluent Release Report and Offsite Dose Calculation Manual (PLA-8041) PLA-8047, 2022 Annual Environmental Operating Report (Nonradiological), PLA-80472023-04-19019 April 2023 2022 Annual Environmental Operating Report (Nonradiological), PLA-8047 PLA-8062, Supplement to Relief Request 4RR-10 Relief from Code Seal Weld Requirement for Valve 252F007B, PLA-80622023-04-11011 April 2023 Supplement to Relief Request 4RR-10 Relief from Code Seal Weld Requirement for Valve 252F007B, PLA-8062 PLA-8061, Relief Request 4RR-10 Relief from Code Seal Weld Requirement for Valve 25F007B, PLA-80612023-04-10010 April 2023 Relief Request 4RR-10 Relief from Code Seal Weld Requirement for Valve 25F007B, PLA-8061 PLA-8060, Submittal of Unit 2 Cycle 22 Core Operating Limits Report (PLA-8060)2023-03-30030 March 2023 Submittal of Unit 2 Cycle 22 Core Operating Limits Report (PLA-8060) PLA-8057, Application for Order Approving Indirect Transfer of Control of Licenses and Approving Conforming License Amendments- Supplemental Information, PLA-80572023-03-15015 March 2023 Application for Order Approving Indirect Transfer of Control of Licenses and Approving Conforming License Amendments- Supplemental Information, PLA-8057 PLA-8052, (Sses), Proof of Financial Protection and Guarantee of Payment of Deferred Premiums2023-02-13013 February 2023 (Sses), Proof of Financial Protection and Guarantee of Payment of Deferred Premiums PLA-8048, Response to Request for Additional Information Regarding License Amendment Requesting Temporary Addition of Analyzed Rod Position Sequence2023-01-14014 January 2023 Response to Request for Additional Information Regarding License Amendment Requesting Temporary Addition of Analyzed Rod Position Sequence PLA-8042, Proposed Emergency Amendment to License NPF-22: Temporary Addition of Analyzed Rod Position Sequence2023-01-10010 January 2023 Proposed Emergency Amendment to License NPF-22: Temporary Addition of Analyzed Rod Position Sequence PLA-8039, Application for Order Approving Indirect Transfer of Control of License Amendments - Supplemental Information2022-12-22022 December 2022 Application for Order Approving Indirect Transfer of Control of License Amendments - Supplemental Information PLA-8038, Notification of Petition for Bankruptcy (PLA-8038)2022-12-14014 December 2022 Notification of Petition for Bankruptcy (PLA-8038) PLA-8036, Registration for the Use of Spent Fuel Storage Casks 203, 202, and 204, PLA-80362022-11-30030 November 2022 Registration for the Use of Spent Fuel Storage Casks 203, 202, and 204, PLA-8036 PLA-8035, Registration for the Use of Spent Fuel Storage Casks 205, 200, and 201, PLA-80352022-11-0808 November 2022 Registration for the Use of Spent Fuel Storage Casks 205, 200, and 201, PLA-8035 PLA-8031, Emergency Plan Revision 66 (PLA-8031)2022-11-0707 November 2022 Emergency Plan Revision 66 (PLA-8031) PLA-8032, Application for Order Approving Indirect Transfer of Control of Licenses and Approving Conforming License Amendments - Supplemental Information (PLA-8032)2022-10-28028 October 2022 Application for Order Approving Indirect Transfer of Control of Licenses and Approving Conforming License Amendments - Supplemental Information (PLA-8032) PLA-8026, Biennial 10 Crf 50.59 and 72.48 Summary Report and Changes to Regulatory Commitment (PLA-8026)2022-10-19019 October 2022 Biennial 10 Crf 50.59 and 72.48 Summary Report and Changes to Regulatory Commitment (PLA-8026) PLA-8015, Application for Order Approving Indirect Transfer of Control of Licenses2022-09-29029 September 2022 Application for Order Approving Indirect Transfer of Control of Licenses PLA-8030, Evacuation Time Estimate Report PLA-80302022-09-15015 September 2022 Evacuation Time Estimate Report PLA-8030 PLA-8025, Supplement to License Amendment to Revise Reactor Steam Dome Pressure - Low Instrumentation Function Allowable Value2022-08-10010 August 2022 Supplement to License Amendment to Revise Reactor Steam Dome Pressure - Low Instrumentation Function Allowable Value PLA-8019, Nd Refueling Outage Owner'S Activity Report, PLA-80192022-07-13013 July 2022 Nd Refueling Outage Owner'S Activity Report, PLA-8019 PLA-8013, Response to Request for Additional Information Regarding License Amendment Requesting Adoption of TSTF-505, Revision 2 PLA-80132022-06-27027 June 2022 Response to Request for Additional Information Regarding License Amendment Requesting Adoption of TSTF-505, Revision 2 PLA-8013 PLA-8012, 10 CFR 50.46 Annual Report2022-06-10010 June 2022 10 CFR 50.46 Annual Report PLA-8005, Response to Request for Additional Information Regarding License Amendment to Revise Reactor Steam Dome Pressure - Low Instrumentation Function Allowable Value (PLA-8005)2022-05-23023 May 2022 Response to Request for Additional Information Regarding License Amendment to Revise Reactor Steam Dome Pressure - Low Instrumentation Function Allowable Value (PLA-8005) PLA-8001, Radiation Exposure Information and Reporting System - PLA-80012022-04-28028 April 2022 Radiation Exposure Information and Reporting System - PLA-8001 PLA-7987, Radioactive Effluent Release Report and Offsite Dose Calculation Manual - (PLA-7987)2022-04-26026 April 2022 Radioactive Effluent Release Report and Offsite Dose Calculation Manual - (PLA-7987) PLA-7986, 2021 Annual Environmental Operating Report (Nonradiological) Docket No. 50-387, PLA-79862022-04-26026 April 2022 2021 Annual Environmental Operating Report (Nonradiological) Docket No. 50-387, PLA-7986 PLA-7985, Annual Radiological Environmental Operating Report2022-04-22022 April 2022 Annual Radiological Environmental Operating Report PLA-7883, Proposed Amendment to Licenses NPF-14 and NPF-22: Relocate Technical Specification Unit Staff Qualification Requirements to Quality Assurance Program (PLA-7883)2022-03-31031 March 2022 Proposed Amendment to Licenses NPF-14 and NPF-22: Relocate Technical Specification Unit Staff Qualification Requirements to Quality Assurance Program (PLA-7883) PLA-7995, Property Insurance Program (PLA-7995)2022-03-30030 March 2022 Property Insurance Program (PLA-7995) PLA-7998, Submittal of Unit 1 Cycle 23 Core Operating Limits Report and Reload Safety Analysis Report2022-03-29029 March 2022 Submittal of Unit 1 Cycle 23 Core Operating Limits Report and Reload Safety Analysis Report PLA-7991, Proof of Financial Protection and Guarantee of Payment of Deferred Premium2022-03-24024 March 2022 Proof of Financial Protection and Guarantee of Payment of Deferred Premium PLA-7984, Supplement to License Amendment Requesting Adoption of TSTF-505, Revision 22022-03-0808 March 2022 Supplement to License Amendment Requesting Adoption of TSTF-505, Revision 2 PLA-7962, Application to Revise Technical Specifications to Adopt TSTF-564, Safety Limit MCPR PLA-79622022-01-0505 January 2022 Application to Revise Technical Specifications to Adopt TSTF-564, Safety Limit MCPR PLA-7962 2024-01-04
[Table view] |
Text
Jeffrey M. Helsel PPL Susquehanna, LLC Nuclear Plant Manager 769 Salem Boulevard \ I I Berwick, PA 18603 \ l I I I Tel. 570.542.3510 Fax 570.542.1504 ' ~ t If # ~
jmhelsel@ pplweb.com ~ ~' "
.P * ~
~ ~,
~, TM U.S. Nuclear Regulatory Commission Attn: Document Control Desk
. W(lshington, DC: 20555~0001 SUSQUEHANNA STEAM ELECTRIC STATION DECOMMISSIONING FUNDING PLAN FOR THE INDEPENDENT SPENT FUEL STORAGE INSTALLATION Docket Nos. 50-387 PLA-6951 and 50-388 PPL Susquehanna, LLC (PPL) is submitting the enclosed Decommissioning Funding Plan for the PPL Independent Spent Fuel Storage Installation (ISFSI) in accordance with 10 CFR 72.30(b). Enclosure 1 addresses each of the six criteria contained in 10 CFR 72.30(b) and references Enclosure 2, which provides details concerning the PPL ISFSI decommissioning cost estimate that was prepared by TLG Services, Inc.
There are no new regulatory commitments contained in this letter.
Should you have any questions or require additional information, please contact Mr. John Tripoli, Manager- Nuclear Regulatory Affairs, at (570) 542-3100.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on: .J~ /S: Zol Z-J.
Enclosure 1: Decommissioning Funding Plan
- Enclosure 2: Decorti1llissionirtg Cost Estimate
Mr. W. M. Dean, NRC Region I Administrator Mr. P. W. Finney, NRC Sr. Resident Inspector Mr. J. A. Whited, NRC Project Manager Mr. L. J. Winker, PA DEP/BRP
Enclosure 1 to PLA-6951 Decommissioning Funding Plan
Enclosure to PLA-6951 Page 1 of2 PPL Susquehanna Decomissioning Funding Plan for the Independent Spent Fuel Storage Installation 10 CFR 72.30(b) requires each holder of, or applicant for, a license under Part 72 to submit for NRC review and approval a decommissioning funding plan (DFP). PPL Susquehanna, LLC (PPL) provides the following information required by 10 CFR 72.30(b) to beincluded in the DFP:
Requirement 1:
"( 1) Information on how reasonable assurance will be provided that funds will be available to decommission the ISFSI or MRS."
Information for Requirement 1:
Pursuant to 10 CFR 72.30(e)(5), since the Susquehanna Steam Electric Station is a power reactor licensee under 10 CFR 50, PPL utilizes the methods of 10 CFR 50.75(b), (e), and (h) to provide financial assurance associated with its 90 percent ownership of the PPL Independent Spent Fuel Storage Installation (ISFSI).
Requirement 2:
"(2) A detailed cost estimate for decommissioning, in an amount reflecting:
(i) The cost of an independent contractor to peiform all decommissioning activities; (ii) An adequate contingency factor; and (iii) The cost of meeting the§ 20.1402 of this chapter criteria for unrestricted use, provided that, if the applicant or licensee can demonstrate its ability to meet the provisions of§ 20.1403 of this chapter, the cost estimate may be based on meeting the
§ 20.1403 criteria. "
Information for Requirement 2:
This information is included in the report in Enclosure 2.
Requirement 3:
"(3) Identification of and justification for using the key assumptions contained in the DCE."
Information for Requirement 3:
This information is included in the report in Enclosure 2.
Enclosure to PLA-6951 Page 2 of2 Requirement 4:
"(4) A description of the method of assuring funds for decommissioning from paragraph (e) of this section, including means for adjusting cost estimates and associated funding levels periodically over the life of the facility. "
Information for Requirement 4:
The decommissioning cost estimate will be adjusted as necessary every three years; as required by 10 CFR 72.30(c). As indicated in the information for Requirement 1, PPL utilizes the methods of 10 CFR 50.75(b), (e), and (h) to provide financial assurance associated with its ownership share of the PPL ISFSI. PPL annually adjusts its 90 percent share of the amount of financial assurance required by 10 CFR 50.75(b) in accordance with paragraph (2) of that section, and further adjustment is required by 10 CFR 50.75(f)(3) and (5) at or about five years prior to the projected end of reactor operations.
Requirement 5:
"(5) The volume of onsite subsuiface material containing residual radioactivity that will require remediation to meet the criteria for license termination."
Information for Requirement 5:
This information is included in the report in Enclosure 2.
Requirement 6:
"(6) A certification that financial assurance for decommissioning has been provided in the amount of the cost estimate for decommissioning."
Information for Requirement 6:
PPL has provided financial assurance for decommissioning the SSES site in an amount that meets or exceeds its 90 percent ownership share of the amount required by 10 CFR 50.75(b), which pursuant to 10 CFR 72.30(e)(5), provides the requisite financial assurance for PPL' s share of the ISFSI decommissioning cost.
Enclosure 2 to PLA-6951 Decommissioning Cost Estimate
PPL Susquehanna, LLC PLA-6951; Enclosure 2 Susquehanna Steam Electric Station ISFSI Page 1 of7 10 CFR 72.30 ISFSI Decommissioning Cost Estimate
- 1. Background and Introduction The Nuclear Regulatory Commission (NRC) issued its final rule on Decommissioning Planning on June 17, 2011,[1] with the rule becoming effective on December 17, 2012.
Subpart 72.30, "Financial assurance and recordkeeping for decommissioning," requires that each holder of, or applicant for, a license under this part must submit for NRC review and approval a decommissioning funding plan that contains information on how reasonable assurance will be provided that funds will* be available to decommission the Independent Spent Fuel Storage Installation (ISFSI).
In accordance with the rule, this letter provides a detailed cost estimate for decommissioning the ISFSI at Susquehanna Steam Electric Station (Susquehanna) in an amount reflecting:
- 1. The work is performed by an independent contractor;
- 2. An adequate contingency factor; and
- 3. Release of the facility and dry storage systems for unrestricted use, as specified in 10 CFR Part 20.1402 This letter also provides:
- 1. Identification of the key assumptions contained in the cost estimate; and
- 2. The volume of onsite subsurface material containing residual radioactivity, if any, that will require remediation to meet the criteria for license termination.
- 2. Spent Fuel Management Strategy The operating licenses for the two Susquehanna units are currently set to expire on July 16, 2042 and March 22, 2044, respectively. Approximately 19,672 spent fuel assemblies are currently projected to be generated as a result of plant operations through the license expiration dates. Because of the breach by the Department of Energy (DOE) of its contract to remove fuel from the site, an ISFSI has been constructed and spent fuel transferred to dry storage modules located on the ISFSI, to support continued plant operations. It is likely, based upon the current projection of the DOE's ability to remove spent fuel from the. site, that the current ISFSI will be expanded to support continued U.S. Code of Federal Regulations, Title 10, Parts 20, 30, 40, 50, 70 and 72 "Decommissioning Planning,"
Nuclear Regulatory Commission, Federal Register Volume 76, Number 117 (p 35512 et seq.), June 17, 2011 TLG Services, Inc.
PPL Susquehanna, LLC PLA-6951; Enclosure 2 Susquehanna Steam Electric Station ISFSI Page 2 of7 operations and decommissioning. The ISFSI is operated under a Part 50 General License (in accordance with 10 CFR 72, Subpart K[ 2J).
All spent fuel for the entire operating life of the plant is expected to be packaged in dry storage containers (DSCs ), including spent fuel assemblies in the spent fuel pool at the time of final shutdown. Transferring the spent fuel from the pools to the ISFSI will permit decontamination and dismantling of the spent fuel pool systems and fuel pool areas or result in reduced operating expenses should the station be placed into a SAFSTOR dormancy configuration.
Completion of the ISFSI decommissioning process is dependent upon the DOE's ability to remove spent fuel from the site. However, with no progress by DOE in the removal of spent fuel from commercial generating sites, PPL Susquehanna's current spent fuel management plan, for purposes of this analysis, assumes "just-in-time" acceptance, i.e.,
the DOE will be able to complete the transfer of spent fuel so as not to impede a deferred decommissioning scenario (SAFSTOR) and the termination of the operating licenses within the required 60 year period (from the cessation of operations). To achieve this objective, based upon the oldest fuel receiving the highest priority, [3J and an annual maximum rate of transfer of 3,000 metric tons ofuranium/year/4] DOE would commence pickup of spent fuel from Susquehanna by 2082, with the completion of spent fuel receipt by year 2102.
PPL' s position is that the DOE has a contractual obligation to accept the spent fuel earlier than the projections set out above consistent with its contract commitments. No assumption made in this study should be interpreted to be inconsistent with this claim.
- 3. ISFSI Decommissioning Strategy At the conclusion of the spent fuel transfer process to DOE the ISFSI will be promptly decommissioned (similar to the power reactor DECON alternative). In this estimate the ISFSI decommissioning is considered an independent project, regardless of the decommissioning alternative identified for the nuclear power plant.
2 U.S. Code of Federal Regulations, Title 10, Part 72, Subpart K, "General License for Storage of Spent Fuel at Power Reactor Sites."
U.S. Code of Federal Regulations, Title 10, Part 961.11, Article IV- Responsibilities of the Parties, B. DOE Responsibilities, 5.(a) ... DOE shall issue an annual acceptance priority ranking for receipt of SNF and/or HLW at the DOE repository. This priority ranking shall be based on the age of SNF and/or HLW as calculated from the date of discharge of such materials from the civilian nuclear power reactor. The oldest fuel or waste will have the highest priority for acceptance, except as ... "
4 "Acceptance Priority Ranking & Annual Capacity Report," DOE/RW-0567, July 2004.
TLG Services, Inc.
PPL Susquehanna, LLC PLA-6951; Enclosure 2 Susquehanna Steam Electric Station ISFSI Page 3 of7
- 4. ISFSI Description The design and capacity of the Susquehanna ISFSI is based upon a NUHOMS dry storage system. The NUHOMS system is comprised of a dry storage canister (DSC),
with either a 52 or 61 spent fuel assembly capacity, and a horizontal storage module (HSM), Model102. The DSCs are assumed to be transferred directly to the DOE and not returned to the station. Some of the reinainingHSMs are assumed to have residual radioactivity due to some minor level of neutron-induced activation of steel components as a result of the long-term storage of the spent fuel. The cost to dispose of material with residual radioactivity, and verify that the remaining facility and surrounding environs meet the NRC's radiological limits established for unrestricted use, form the basis of the ISFSI decommissioning estimate.
PPL Susquehanna's current spent fuel management plan for the Susquehanna spent fuel would result in approximately 327 HSMs (27 DSCs containing 52 assemblies each and 300 DSCs containing a nominal 61 assemblies per DSC) being in position on the storage pad at the site after all spent fuel has been removed from the spent fuel pools. This represents 100% of the total spent fuel projected to be generated during the currently licensed operating period.
In addition to the spent fuel HSMs located on the ISFSI pad after shutdown there are projected to be additional HSMs that are expected to be used for Greater-than-Class-C (GTCC) storage. The HSMs used for the GTCC canisters (estimated quantity of 4 per unit) are not expected to have any interior contamination or residual activation and can be reused or disposed of by conventional means after a final status survey.
Table 1 provides the significant quantities and physical dimensions used as the basis in developing the ISFSI decommissioning estimate.
- 5. Key Assumptions I Estimating Approach The decommissioning estimate is based on the configuration of the ISFSI expected after all spent fuel and GTCC material has been removed from the site. The configuration of the ISFSI is based on the Susquehanna units operating until the end of their current licenses, July 16, 2042 and March 22, 2044, respectively, and the assumptions associated with DOE's spent fuel acceptance, as previously described.
For purposes of this analysis the current pad (221 feet by 224 feet) will be expanded to accommodate the 335 modules (including the 8 modules for storing GTCG).
The dry storage vendor, Transnuclear, Inc., does not expect the horizontal storage modules to have any interior or exterior radioactive surface contamination. [SJ Any neutron 5
Updated Final Safety Analysis Report for the Standardized NUHOMS Horizontal Modular Storage System for Irradiated Nuclear Fuel, Transnuclear Inc., NUH-003, Rev. 12, at page 3.5-1 TLG Services, Inc.
PPL Susquehanna, LLC PLA-6951; Enclosure 2 Susquehanna Steam Electric Station ISFSI Page 4 of7 activation of the steel and concrete is expected to be extremely small. [6] This assumption is adopted for this analysis.
The decommissioning estimate is based on the premise that some of the DSC support structure within some of the HSMs will contain low levels of neutron-induced residual radioactivity that would necessitate remediation at the time of decommissioning. As an allowance, 26 of the 327 HSMs are assumed to be affected, i.e., contain residual radioactivity. The allowance quantity is based upon the number of DSCs required for the final core off-load (i.e., 764 offloaded assemblies/unit, 61 assemblies per DSC) which results in a total of 13 HSMs/unit or 26 total that contain residual radioactivity. It is assumed that these are the final HSMs offloaded; consequently they have the least time for radioactive decay of the neutron activation products.
It is not expected that there will be any residual contamination left on the concrete ISFSI pad. Therefore, it is assumed for this analysis that the ISFSI pad will not be contaminated. As such, only verification surveys are included for the pad in the decommissioning estimate.
There is no known [?J subsurface material in the proximity of the ISFSI containing residual radioactivity that will require remediation to meet the criteria for license termination.
Decommissioning is assumed to be performed by an independent contractor. As such, essentially all labor, equipment, and material costs are based on national averages, i.e.,
costs from national publications such as R.S. Means' Building Construction Cost Data (adjusted for regional variations), and laboratory service costs are based on vendor price lists. Those craft labor positions that are expected to be provided locally, are consistent with fully burdened contractor labor rates used in the most recently developed Susquehanna decommissioning cost estimate, escalated to 2012 dollars. PPL, as licensee, will oversee the site activities; the estimate includes PPL' s labor and overhead costs.
Low-level radioactive waste packaging, transport and disposal costs are based on rates consistent with the most recently developed decommissioning cost estimate (year 2010 dollars), escalated to 2012 dollars.
Contingency has been added at an overall rate of 25%. This is consistent with the contingency evaluation criteria referenced by the NRC in NUREG-17 57. [SJ 6
Ibid. at page 9.6-1 7
Susquehanna Radiation Protection Manager "Consolidated Decommissioning Guidance, Financial Assurance, Recordkeeping, and Timeliness," U.S.
Nuclear Regulatory Commission's Office of Nuclear Material Safety and Safeguards, NUREG-1757, Volume 3, Revision 1, February 2012 TLG Services, Inc.
PPL Susquehanna, LLC PLA-6951; Enclosure 2 Susquehanna Steam Electric Station ISFSI Page 5 of7 Costs are reported in 2012 dollars and based upon a decommissioning analysis prepared for Susquehanna in 2010. Activity costs originally reported in 2010 dollars have been escalated to 2012 dollars using the Consumer Price Index, Services. [91 The estimate is limited to costs necessary to terminate the ISFSI' s NRC license and meet the §20.1402 criteria for unrestricted use. Disposition of released material and structures is outside the scope of the estimate.
- 6. Cost Estimate The estimated cost to decommission the ISFSI and release the facility for unrestricted use is provided in Table 2. The cost has been organized into three phases, including:
- An initial planning phase - empty HSMs are characterized and the specifications and work procedures for the decontamination developed.
- The remediation phase- material with residual radioactivity is removed, packaged in certified waste containers, transported to the low-level waste site, and disposed of at low-level waste.
- The final phase - license termination surveys, independent surveys are completed, and an application for license termination submitted.
In addition to the direct costs associated with a contractor providing the decommissioning services, the estimate also contains costs for the NRC (and NRC contractor to perform the verification survey), PPL's oversight staff, site security (industrial), and other site operating costs.
For estimating purposes it is conservatively assumed that all expenditures will be incurred in the year 2102, the year following all spent fuel removal.
9 Bureau of Labor Statistics, Consumer Price Index - All Urban Consumers, Services, Series ID: CUUROOOOSAS TLG Services, Inc.
PPL Susquehanna, LLC PLA-6951; Enclosure 2 Susquehanna Steam Electric Station ISFSI Page 6of7 Table 1 Significant Quantities and Physical Dimensions ISFSI Pad Item Length (ft) Width (ft) Residual Radioactivity I I
~C:l1rrent ISFSI Pacl_(nominal dimensions) 221 224 No ISFSI Horizontal Storage Module- Model 102 Item Value Notes (all dimensions are nominal)
Outside Height (inches) 180 Without vent cover Outside Length (inches) 238 Without shield walls Outside Width (inches) 116 Without shield walls Quantity (total) 335 Spent Fuel (327) + GTCC (8)
Equivalent to the number of HSMs used Quantity (with residual radioactivity) 26 to store last complete core offload)
HSM Internal Steel with Residual Radioactivity (pounds) 134,600 Low-Level Radioactive Waste (cubic feet) 3,005 Low-Level Radioactive Waste (packaged de~sity) (lbs/cubic feet) 47 .b-verag~.\Veight density__
Other Potentially Impacted Items Item Value Notes .I I
Number of HSMs used for GTCC storage 8 No residual radioactivity TLG Services, Inc.
PPL Susquehanna, LLC PLA-6951; Enclosure 2 Susquehanna Steam Electric Station ISFSI Page 7of7 Table 2 ISFSI Decommissioning Costs 1 and Waste Volumes Waste (thousands, 2012 dollars) Volume Person-Hours NRC/NRC Removal Packaging Transport Disposal Other Total (ft3) Contractor Licensee Contractor Decommissioning Contractor Planning (characterization,*
specs and grocedures) - - - - 517 517 - 25,530 - -
Remediation (activated metal removal) 1,009 15 35 621 222 1,902 3,005 - - -
License Termination (radiological surveys) - - - - 2,626 2,626 - 23,970 - -
Subtotal 1,009 15 35 621 3,364 5,044 3,005 49,500 - -
Supporting Costs NRC and NRC Contractor Fees and Costs - - - - 265 265 - - - 776 Insurance - - - - 169 169 - - - -
Security (industrial) - - - - 177 177 - 6,234 - -
PPL Oversight Staff - - - - 345 345 - 4,730 - -
Subtotal - - - - 956 956 - 10,964 - 776 Total (w/o contingency) 1,009 15 35 621 4,320 5,999 3,005 60,464 - 776 Total (w/25% contingency) 1,261 18 44 777 5,400 7,499 Note 1: for funding planning purposes decommissioning costs can be assumed to be incurred in year 2102 TLG Services, Inc.