LR-N12-0369, Response to Recommendation 2.3: Flooding Walkdown of the Near-Term Task Force Review of Insights from the Fukushima Dai-lchi Accident
| ML12334A452 | |
| Person / Time | |
|---|---|
| Site: | Hope Creek |
| Issue date: | 11/26/2012 |
| From: | Jamila Perry Public Service Enterprise Group |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| LR-N12-0369 | |
| Download: ML12334A452 (3) | |
Text
PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, NJ 08038-0236 0 PSEG Nucletar LLC NOV 26 2012 10 CFR 50.54(f)
LR-N12-0369 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Hope Creek Generating Station Renewed Facility Operating License No. NPF-57 NRC Docket No. 50-354
Subject:
Hope Creek Generating Station Response to Recommendation 2.3:
Flooding Walkdown of the Near-Term Task Force Review of Insights from the Fukushima Dai-lchi Accident
References:
(1)
US Nuclear Regulatory Commission (NRC) letter dated March 12, 2012, "Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-lchi Accident" (2)
PSEG Letter LR-N12-0170 dated June 7, 2012, "PSEG Nuclear LLC's Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Flooding Aspects of Recommendations 2.1 and 2.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident" (3)
NEI 12-07 Revision 0-A dated May 2012, "Guidelines for Performing Verification Walkdowns of Plant Flood Protection Features" On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued a request for information (Reference 1) to PSEG Nuclear LLC (PSEG). Reference 1 includes a request for PSEG to perform flooding walkdowns using NRC-endorsed walkdown methodology. By "LR-N12-0170, PSEG Nuclear LLCs Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Flooding Aspects of Recommendations 2.1 and 2.3 of the Near-Term Task Force Review of Insights from the [[Topic" contains a listed "[" character as part of the property label and has therefore been classified as invalid. Accident|letter dated June 7, 2012]] (Reference 2) PSEG confirmed that it would use the NRC-endorsed flooding walkdown guidance in NEI 12-07, "Guidelines for Performing Verification Walkdowns of Plant Flood Protection Features" (Reference 3).
LR-N1 2-0369 10 CFR 50.54(f)
Page 2 provides the requested flooding walkdown report for the Hope Creek Generating Station.
There are no regulatory commitments contained in this transmittal. If you have any questions or require additional information, please do not hesitate to contact Mrs. Emily Bauer at 856-339-1023.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on
- / Z 4 - (*
(Date)
Sincerely, John F. Perry Site Vice President Hope Creek Generating Station Enclosure (1) cc:
Mr. E. Leeds, Director of Office of Nuclear Reactor Regulation Mr. W. Dean, Administrator, Region I, NRC Mr. J. Hughey, Project Manager, NRC NRC Senior Resident Inspector, Hope Creek Mr. P. Mulligan, Manager IV, NJBNE Hope Creek Commitment Tracking Coordinator PSEG Commitment Coordinator - Corporate LR-N12-0369 0
PSEG NUCLEAR LLC Hope Creek Generating Station HCGS Flood Walkdown Report 10 CFR 50.54(f) Section 2.3 (Flood) Response