NL-11-1543, Response to NRC Request for Additional Information Proposed Relief Request FNP-ISI-RR-01
| ML112232241 | |
| Person / Time | |
|---|---|
| Site: | Farley |
| Issue date: | 08/11/2011 |
| From: | Ajiuni M Southern Co, Southern Nuclear Operating Co |
| To: | Office of Nuclear Reactor Regulation, Document Control Desk |
| References | |
| FNP-ISI-RR-01, NL-11-1543 | |
| Download: ML112232241 (11) | |
Text
Mark J. Ajluni, P.E.
Southern Nuclear Nuclear Director Operating Company, Inc.
40 Inverness Center Parkway Post Office Box 1295 Birmingham, Alabama 35201 Tel 205.992.7673 Fax 205.9927885 August 11, 2011 SOUTHERN'\\
COMPANY Docket Nos.: 50-348 NL-11-1543 U. S. Nuclear Regulatory Commission ArrN: Document Control Desk Washington, D, C. 20555-0001 Joseph M. Farley Nuclear Plant - Unit 1 Response to NRC Request for Additional Information Proposed Relief Request FNP-ISI-RR-01 Ladies and Gentlemen:
By letter dated March 28, 2011, Southern Nuclear Operating Company (SNC) submitted proposed relief request FNP-ISI-RR-01 for Farley Nuclear Plant, Unit 1, that would allow the use of an alternate depth-sizing qualification for volumetric examinations of the reactor pressure vessel nozzle-to-safe end dissimilar metal welds from the inside surface. Subsequently, the NRC issued a request for additional information (RAI), by letter dated July 14,2011 (ML11173A047), to enable completion of the review. The responses to the NRC RAls are provided in the Enclosure.
This letter contains no NRC commitments. If you have any questions, please contact Jack Stringfellow at (205) 992-7037.
Sincerely,
~ ~ et--'
M. J. Ajluni Nuclear Licensing Director MJA/LPHllac
Enclosure:
Response to NRC RAI Regarding Proposed Relief Request FNP-ISI-RR-01 for Farley Nuclear Plant, Unit 1
U. S. Nuclear Regulatory Commission NL-11-1543 Page 2 cc:
Southern Nuclear Operating Company Mr. S. E. Kuczynski, Chairman, President &CEO Mr. J. T. Gasser, Executive Vice President Mr. L. M. Stinson, Vice President -- Farley Ms. P. M. Marino, Vice President - Engineering RTYPE: CFA04.054 U. S. Nuclear Regulatory Commission Mr. V. M. McCree, Regional Administrator Mr. R. E. Martin, NRR Project Manager - Farley Mr.
L. Crowe, Senior Resident Inspector - Farley Mr. P. G. Boyle, NRR Project Manager
Joseph M. Farley Nuclear Plant - Unit 1 Response to NRC Request for Additional Information Proposed Relief Request FNP-ISI-RR-01 Enclosure Response to NRC RAI Regarding Proposed Relief Request FNP-ISI-RR-01 for Farley Nuclear Plant, Unit 1
Enclosure to NL-11-1543 Response to NRC RAI Regarding Proposed Relief Request FNP-ISI-RR-01 for Farley Nuclear Plant, Unit 1
- 1.
NRC RAI Some details about the welds were not included in the relief request. Provide detailed cross-sectional diagrams including sketches of the weld area. These diagrams should identify the materials (stainless steel, carbon steel, nickel alloy) of the base metal, weld, and buttering and show dimensions (Nominal inside diameter (10), outside diameter (00), and wall thickness) for each of the welds.
SNC Response to NRC RAI 1 Figures 1 and 2 show the hot-leg and cold-leg drawings, respectively. The drawings show both configuration and materials.
- 2.
NRC RAI Some of the ultrasonic testing (UT) techniques qualified by POI from the 10 have difficulty in detecting axial cracks, and use supplemental eddy current testing for this purpose. Will any supplemental examinations, such as eddy current testing, be performed on the 10 to detect possible surface-breaking flaws and to confirm if possible indications detected by UT are surface breaking?
SNC Response to NRC RAI2 Supplemental eddy current examinations are used by our vendor to detect possible surface-breaking flaws and to confirm if possible indications detected by UT are surface-breaking.
3a.
NRC RAI The cited difficulties in depth-sizing come from issues with the specific POI mock ups used for Appendix VIII, Supplement 10 10 depth-sizing qualifications.
Specifically, these samples do not have smooth <<1/32 inch waviness) 10 surfaces. It is not clear if the limitations in the PDI specimens apply to the inspection conditions in Farley Unit 1.
Has profilometry been previously performed on any of these welds? If yes, provide a description of the surface waviness and estimate the percentage of areas with suspected probe lift-off.
SNC Response to NRC RAI 3a The UT technique utilized by our vendor includes the methodology for measuring the profile of the 10 surface of these welds and adjacent base metal using an immersion ultrasonic technique. This profile can be used to apply beam plotting E-1
Enclosure to NL-11-1543 Response to NRC RAI Regarding Proposed Relief Request FNP-ISI-RR-01 for Farley Nuclear Plant, Unit 1 of indications for establishing a through-wall depth and ligament of a flaw indication, to assist in defining examination limitations, to help discriminate geometric reflectors, and to aid the UT examiner in understanding the effects of surface geometry on the inspection data.
Profilometry using UT methods was performed on the 10 surface during the fall 2007 1 R21 outage at Unit-1. The surface condition of the nozzle to safe-end welds were relatively smooth with no lack of coverage noted. A more recent examination on Farley-2 was completed during the fall 2008 2R19 outage with similar results. Figures 3, 4, and 5 provide representative profilometry profiles for Farley-1 hot-leg nozzles.
3b.
NRC RAt If the POI mockups have significantly different 10 surface conditions than the welds in this relief request, provide a discussion on the time and effort necessary to produce mockups that match the 10 conditions in the welds covered in this relief request.
SNC Response to NRC RAI3b SNC has no plans to fund the fabrication of additional mock-ups with less conservative surface conditions. No ultrasonic indications were observed in the previous Unit-1 or -2 examinations, and we expect similar results in future examinations. If UT indications are found, the depth of the observed flaw will be increased by the RMSE value. This process would be conservative when evaluating actual flaw depth vs. the acceptance standards. Therefore, the fabrication of additional mock-ups and the associated costs are not warranted.
- 4.
NRC RAI All of the examinations described in this relief request are to be preformed from the inner diameter of the welds. If the vendor has qualified for depth-sizing from the 00, please provide a discussion on the difficulties that would inhibit depth sizing from the 00.
SNC Response to NRC RAI 4 The Farley-1 vendor for the 10 Supplement 10 examinations is Appendix VIII qualified for depth-sizing using an automated system from the 00. However, the "sand-box" configuration at Farley does not permit access to the 00 while the cavity is flooded for 10 examinations. Access from the 00 for Plant Farley requires the cavity to be drained and the "sand box" covers in the cavity to be removed. These welds should be able to be examined from the 00; however, E-2
Enclosure to NL-11-1543 Response to NRC RAI Regarding Proposed Relief Request FNP-ISI-RR-01 for Farley Nuclear Plant, Unit 1 walkdowns will need to be performed to determine the feasibility and limitations associated with 00 ultrasonic examinations.
Sa.
NRC RAI Some licensees have located representative mockups (with smooth 10 surfaces) containing cracks. UT vendors have used these mockups to demonstrate 10 depth sizing RMSE capabilities. Also, vendors have independently participated in blind and non-blind round robin demonstrations on mockups containing representative cracks.
Provide a discussion of SNC's efforts to provide representative mockups containing cracks (or simulated cracks with crack-like responses) with 10 surfaces similar to the surfaces used for successful 00 depth-sizing qualifications.
SNC Response to NRC RAI Sa As indicated in the response to Question 3b, SNC has no plans to fund the fabrication of additional mock-ups. The Farley vendor has successfully performed multiple examinations including sizing at a few plants. These examinations were performed to ASME Section XI, Appendix VIII requirements as amended by NRC rulemaking.
5b.
NRC RAI Provide a discussion of your vendor's participation in 10 depth-sizing demonstrations that may have been independent of the POI program. If available, include a description of the specimens (10 surface waviness, configurations, and materials) and cracks, types of tests (blind or not-blind),
differences between the procedures and personnel used for the demonstrations and those being proposed for examining the subject welds, a summary of results and RMSE values, and the organization sponsoring and/or proctoring the demonstrations.
SNC Response to NRC RAI5b Farley is using the same vendor as Braidwood-1 and -2. Exelon responded to the NRC in their RAI question 3(b) to this issue as documented in letter RS-11 087, dated June 6, 2011 (ML111580106). SNC confirmed with that vendor that their information is still valid.
E-3
Enclosure to NL-11-1543 Response to NRC RAI Regarding Proposed Relief Request FNP-ISI-RR-01 for Farley Nuclear Plant, Unit 1 SS Weld Alloy 600 Weld OJ r
("')
co eo en
("')
~
Buttering eo c:i OJ N
LO N
C")
N co N
~
N 3.77 i
t
(*)
Cast SS Pipe FLOW 3.15 CS Clad Nozzle 1 25-
- "/,L ; '-.-."
- .:2,//z:d'
_"k" 'l"'**' J>."
- J 1 1.09 t"')
r co o
~
~
N co
\\,'J N
c m
ci..
m
- 2 o
Q) ro ro o
0..
a..
0..
q N
"<;f" co ill x
x m
0::5 2
- 2 N
.. SS Safe-End FARLEY 1 OUTLET SAFE END DETECTION SCANS 25 0 ALA1-41 00-1 OM 145 0 ALA 1-4300-1 OM 265 0 ALA 1-4200-1 OM FIGURE 1 E-4
Enclosure to NL-11-1543 Response to NRC RAI Regarding Proposed Relief Request FNP-ISr-RR-01 for Farley Nuclear Plant, Unit 1 Alloy 600 Weld SS Weld N
a) o i 1..')
ill ill o
I,{)
l-.::t l"
11..0 01 N
(')
o N
N N
'F"
'F" N
IN
...- ----.50
. Buttering
,I i I I 3.27 1: I CS Clad Nozzle Cast SS Elbow 1 (")
t FLOW 1.09
"'0, l,{)
t
l" 0
r-I.{)
1..#.'
0 N
a L()
n N
co a.
l-n (I)
Q ro co I-CL a..
ID lro r-
!l.
0..
c
~s
- 2 x:
"'=
)(
~
- 2 ro ro C\\l
- 2
- SS Safe-End FARLEY 1 INLET SAFE END DETECTION SCANS 95° ALA1-4300-14DM 215 0 ALA1-4200-14DM 335 0 ALA1-4100-14DM FIGURE 2 E-5
Enclosure to NL-11-1543 Response to NRC RAI Regarding Proposed Relief Request FNP-ISI-RR-01 for Farley Nuclear Plant, Unit 1 Prcfile WR2S-SRPRPDITOR.utr_03.pfd Sweep 1, Xb = 0.0'
-0.5 I
--J 0.0 It' 0.5 l
II '\\
1.0 1.S
\\
I II \\
I I
,I' I
.\\1,0 I I
\\
l I
\\
I 1:12.0 113.Q 114.0 115.0 116.0 117.0 118.0 119.0 1.20.0 121.0 122.
FARLEY 1 25° Hot Leg Loop 1 FIGURE 3 E-6
Enclosure to NL-11-1543 Response to NRC RAI Regarding Proposed Relief Request FNP-ISI-RR-01 for Farley Nuclear Plant, Unit 1 Prafile 1lI265SEPRPDZTOU,utr_03.pfd Sweep 6, Xb. 4,go
-0.5, C.O I~
~'-
O.S II \\
I 1.0.
I I
.\\
f I /
\\
L 1..5 1
f'1
\\
I 2.D I I
\\
I I
\\
I j
112.0 113.0 l14,O 115.Q lUii.O 117.0 418.0 119.0 llO.a 12l..0 122.
FARLEY 1 265 0 Hot Leg Loop 2 FIGURE 4 E-7
Enclosure to NL-11-1543 Response to NRC RAI Regarding Proposed Relief Request FNP-ISI-RR-01 for Farley Nuclear Plant, Unit 1 Profile Dl45SlfRPDilTOIl.ut,_D3.pfd SWeep 31, Xb. 29,7'
-0.5 l'
0.0 11'
-.~
0.5 II II \\
1.0 I
L 1
\\
I I /
\\
1.5 f
,)
\\
2.0 Ii/
\\
I
\\
f 113.0 113. Q 114.0 l15.0 ll6.0 111.0 1l8.0 119.0 120.0 121.0 1~2.
FARLEY 1 145 0 Hot Leg Loop 3 FIGURE 5 E-8