NLS2011057, Revised Submittal Date for 10 CFR 50.48(c) License Amendment Request and Request for Extension of Enforcement Discretion
| ML11182A912 | |
| Person / Time | |
|---|---|
| Site: | Cooper |
| Issue date: | 06/27/2011 |
| From: | O'Grady B Nebraska Public Power District (NPPD) |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| NLS2011057 | |
| Download: ML11182A912 (3) | |
Text
Nebraska Public Power District Always there when you need us NLS2011057 June 27, 2011 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001
Subject:
Revised Submittal Date for 10 CFR 50.48(c) License Amendment Request and Request for Extension of Enforcement Discretion Cooper Nuclear Station, Docket No. 50-298, DPR-46
Reference:
- 1.
Letter from Stewart B. Minahan (Nebraska Public Power District) to U.S.
Nuclear Regulatory Commission, dated September 19, 2008, "Request for Extension of Enforcement Discretion and Revised Submittal Date for 10 CFR 50.48(c) License Amendment Request" (NLS2008079).
- 2.
Staff Requirements Memorandum - SECY-11-0033, "Proposed NRC Staff Approach to Address Resource Challenges Associated With Review of a Large Number of NFPA 805 License Amendment Requests," dated April 20, 2011.
- 3.
Staff Requirements Memorandum - SECY-11-0061, "A Request to Revise the Interim Enforcement Policy for Fire Protection Issues on 10 CFR 50.48(c) to Allow Licensees to Submit License Amendment Requests in a Staggered Approach (RIN 3150-AG48)," dated June 10, 2011.
Dear Sir or Madam:
The purpose of this letter is to inform the Nuclear Regulatory Commission (NRC) that the Nebraska Public Power District (NPPD) intends to revise its planned submittal date for a License Amendment Request (LAR) for transition to the NFPA 805 Fire Protection Standard, and to request the extension of enforcement discretion consistent with this revised submittal date.
In Reference 1, NPPD communicated to the NRC that the 10 CFR 50.48(c) LAR for Cooper Nuclear Station (CNS) would be submitted within six months after the date of the NRC safety evaluation approving the second pilot plant LAR. In Reference 2, the NRC approved a staggered submittal approach for 10 CFR 5 0.48(c) LARs to allow for better coordination of staff resources.
In Reference 3, the NRC approved a revision to the Enforcement Policy for fire protection issues to accommodate this staggered approach.
COOPER NUCLEAR STATION 4OO_7 P.O. Box 98 / Brownville, NE 68321-0098 Telephone: (402) 825-3811 / Fax: (402) 825-5211 www.nppd.comn
NLS2011057 Page 2 of 2 In light of References 2 and 3, NPPD commits to submit the CNS 10 CFR 50.48(c) LAR by April 27, 2012. Consistent with Reference 3, NPPD requests that enforcement discretion for fire protection issues be extended to correspond with the LAR submittal date. Per the revised Enforcement Policy, once the LAR is submitted, the NPPD understands that the enforcement discretion would then continue while the LAR is under review.
Should you have any questions regarding this submittal, please contact Todd Stevens, NFPA 805 Transition Project Manager, at (402) 825-5159.
Sincerely, Brian J. O'Grady Vice President - Nuclear and Chief Nuclear Officer
/WV cc:
Regional Administrator USNRC - Region IV Senior Project Manager, Plant Licensing Branch USNRC - DORL Cooper Project Manager USNRC - NRR Project Directorate IV-1 Director, Office of Enforcement USNRC Senior Resident Inspector USNRC - CNS NPG Distribution CNS Records
ATTACHMENT 3 LIST OF REGULATORY COMMITMENTS© 4 ATTACHMENT3 LIST OF REGULATORY COMMITMENTS@4 Correspondence Number: NLS2011057 The following table identifies those actions committed to by Nebraska Public Power District (NPPD) in this document. Any other actions discussed in the submittal represent intended or planned actions by NPPD. They are described for information only and are not regulatory commitments. Please notify the Licensing Manager at Cooper Nuclear Station of any questions regarding this document or any associated regulatory commitments.
COMMITMENT COMMITTED DATE COMMITMENT NUMBER OR OUTAGE NPPD commits to submit the CNS 10 CFR 50.48(c) LAR by April 27, 2012.
4 4-4 4-PROCEDURE 0.42 REVISION 27 PAGE 18 OF 25