05000454/FIN-2018003-01
From kanterella
Revision as of 01:29, 4 December 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Finding | |
---|---|
Title | Minor Violation |
Description | On June 14, 2018, the licensee performed IST surveillance 2BOSR 5.5.8.DO1, Test of the Diesel Oil Transfer System, on the 2A diesel oil transfer pump. On June 19, 2018, the inspectors noted that an issue concerning the calibration of the Flexim ultrasonic flow meter used during the test had not been documented in the licensees Corrective Action Program (CAP). Specifically, the calibration sticker on the flow meter used during the surveillance test indicated that the instrument was calibrated to a 5 percent accuracy when the ASME OM Code required an instrument accuracy of 2 percent. The inspectors discussed the issue with licensee management. The licensee subsequently confirmed that the instrument calibration did not meet ASME OM Code requirements and entered this issue into their CAP.Title 10 CFR Part 50, Appendix B, Criterion XII, Control of Measuring and Test Equipment, requires that measures be established to assure that tools, gages, instruments, and other measuring and testing devices used in activities affecting quality are properly controlled, calibrated, and adjusted at specific periods to maintain accuracy within necessary limits. Licensee procedure ERAA321, Administrative Requirements for Inservice Testing,Section 4.10.3, states, in part, that instrument accuracy and range requirements are specified in the applicable ASME Code Edition/Addenda. ASME OM Code Paragraph ISTB-3510, General, states, in part, that instrument accuracy shall be within the limits of Table ISTB-35101, Required Instrument Accuracy. Table ISTB35101 states that the required instrument accuracy for determining flow rate is 2 percent. Screening: The failure to implement programmatic controls that ensured measurement and test equipment was calibrated to the accuracy requirements of the ASME OM Code was a performance deficiency. The instruments used in IST surveillances were later re-certified to meet the required 2 percent accuracy in the ASME OM Code with no required adjustments. As a result, the performance deficiency was determined to be minor because the inspectors answered No to all of the more-than-minor screening criteria in IMC 0612, Appendix B. The licensee generated Issue Report (IR) 04149294 to document this issue in their CAP. This issue was also incorporated into a corrective action program evaluation (CAPE) report evaluating an adverse trend identified with ASME test performance at the site (AR 04154533). Violation: The failure to comply with 10 CFR Part 50, Appendix B, Criterion XII, Control of Measuring and Test Equipment, constituted a minor violation that was not subject to enforcement action in accordance with the NRCs Enforcement Policy. |
Site: | Byron |
---|---|
Report | IR 05000454/2018003 Section 4OA2 |
Date counted | Sep 30, 2018 (2018Q3) |
Type: | Violation: Severity level Minor |
cornerstone | No Cornerstone |
Identified by: | NRC identified |
Inspection Procedure: | IP 71152 |
Inspectors (proximate) | J Mcghee C Hunt D Kimble T Hartman S Bell J Cassidy J Bozga C Thompson E Duncan |
Violation of: | 10 CFR 50 Appendix B 10 CFR 50 Appendix B Criterion XII, Control of Measuring and Test Equipment |
INPO aspect | |
' | |
Finding - Byron - IR 05000454/2018003 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Byron) @ 2018Q3