IR 05000271/201500112 February 2015IR 05000271-15-001; on 01/01/2015 - 01/24/2015; Vermont Yankee Nuclear Power Station (Vermont Yankee); Surveillance Testing
IR 05000271/201400510 February 2015IR 05000271-14-005; 10/01/2014 - 12/31/2014; Vermont Yankee Nuclear Power Station (Vy); Fire Protection, Drill Evaluation, and Follow-up of Events and Notices of Enforcement Discretion
ML20311A35026 November 20142017 Q1-Q4 ROP Inspection Findings
IR 05000271/201400427 October 2014IR 05000271-14-004; 07/01/2014 - 09/30/2014; Vermont Yankee Nuclear Power Station; Equipment Alignment, Plant Modifications, and Problem Identification and Resolution
IR 05000271/201400712 May 2014IR 05000271-14-007; 3/17/2014 - 4/03/2014; Vermont Yankee Nuclear Power Station; Component Design Bases Inspection
IR 05000271/20140028 May 2014IR 05000271-14-002; 01/01/2014 - 03/31/2014; Vermont Yankee Nuclear Power Station; Maintenance Effectiveness
ML13338A61226 March 2014G20130229 - 2.206 Petition Closure Letter Re Revoke Operating License for General Electric Mark I and Mark II Boiling Water Reactors
BVY 14-017, Reply to Notice of Violation 05000271/2013-005-01, Inadequate Corrective Actions to Restore Switchgear Room Flood Boundary5 March 2014Reply to Notice of Violation 05000271/2013-005-01, Inadequate Corrective Actions to Restore Switchgear Room Flood Boundary
IR 05000271/20130056 February 2014IR 05000271-13-005; 10/01/2013 - 12/31/2013; Vermont Yankee Nuclear Power Station; Flood Protection Measures, Maintenance Risk Assessments and Emergent Work Control
IR 05000271/20130045 November 2013IR 05000271-13-004; 07/01/2013 - 09/30/2013; Vermont Yankee Nuclear Power Station; Maintenance Effectiveness, Occupational as Low as Is Reasonably Achievable Planning and Controls, Problem Identification and Resolution
IR 05000271/20130039 August 2013IR 05000271-13-003, 07200059-13-001; on 04/01/2013 - 06/30/2013; Vermont Yankee Nuclear Power Station; Adverse Weather Protection, Equipment Alignment, and Refueling and Other Outage Activities
IR 05000271/201300831 July 2013IR 05000271-13-008; Entergy Nuclear Operations, Inc; 06/10/2013 - 06/27/2013; Vermont Yankee Nuclear Power Station, Biennial Baseline Inspection of Problem Identification and Resolution
IR 05000271/201300219 April 2013IR 05000271-13-002; 01/01/2013 - 03/31/2013; Vermont Yankee Nuclear Power Station; Equipment Alignment, Plant Modifications, Problem Identification and Resolution and Other Activities
IR 05000271/201200530 January 2013IR 05000271-12-005, on 10/01/2012 - 12/31/2012, Vermont Yankee Nuclear Power Station - NRC Integrated Inspection Report
ML12362A05020 November 2012Engineering Report VY-RPT-12-00019, Vermont Yankee Seismic Walkdown Submitted Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Cover Through Page 204 of 505
IR 05000271/201200431 October 2012IR 05000271-12-004; 07/01/2012 - 09/30/2012; Vermont Yankee Nuclear Power Station; Maintenance Effectiveness, Surveillance Testing
IR 05000271/201200326 July 2012IR 05000271-12-003, 04/01/2012-06/30/2012, Vermont Yankee Nuclear Power Station, Maintenance Risk Assessments and Emergent Work Control
IR 05000271/201200216 April 2012IR 05000271-12-002, 01/01/2012 - 03/31/2012, Vermont Yankee Nuclear Power Station, Maintenance Effectiveness, Post Maintenance Testing
IR 05000271/201100527 January 2012IR 05000271-11-005, on 10/01/2011 - 12/31/2011, Vermont Yankee Nuclear Power Station, Maintenance Risk Assessments and Emergent Work Control, Refueling and Other Outage Activities, and Problem Identification and Resolution
CY-92-223, G20110523/LTR-11-0411/EDATS: SECY-2011-0411 - Ltr. from Rep. E.J. Markey to Chairman Jaczko NRC Safety Requirements for Reactors Granted Construction Permits Prior to 197114 July 2011G20110523/LTR-11-0411/EDATS: SECY-2011-0411 - Ltr. from Rep. E.J. Markey to Chairman Jaczko NRC Safety Requirements for Reactors Granted Construction Permits Prior to 1971
ML11175021922 June 2011NRC Inspection Findings Related to Closed Cooling Water Systems (1/1/2004 to 6/22/2011)
IR 05000271/20110082 June 2011IR 05000271/2011008; 04/04/2011-04/21/2011; Vermont Yankee Nuclear Power Station Biennial Baseline Inspection of Problem Identification and Resolution (Pi&R)
IR 05000271/201140423 May 2011IR 05000271-11-404, on 04/04/2011 - 04/22/2011, Vermont Yankee Nuclear Power Station, Problem Identification and Resolution. (Letter Only)
IR 05000271/201100229 April 2011Lr 05000271-11-002;01/01/2011 - 03/31/2011; Vermont Yankee Nuclear Power Station; Post-Maintenance Testing; Event Follow-up
IR 05000271/201140314 April 2011IR 05000271-11-403, on 03/14/2011 - 03/18/2011; Vermont Yankee Nuclear Power Station; Identification and Resolution of Problems. (Letter Only)
IR 05000271/201040329 March 2011IR 05000271/2010403; 12/05/2010 - 02/23/2011; Vermont Yankee Nuclear Power Station; Problem Identification and Resolution
IR 05000271/20100058 February 2011IR 05000271-10-005, on 10/01/2010-12/31/2010, Vermont Yankee Nuclear Power Station, Identification and Resolution of Problems
IR 05000271/20100088 November 2010IR 05000271-10-008; 09/13/2010 - 10101/2010; Vermont Yankee Nuclear Power Station; Triennial Fire Protection Team Inspection
IR 05000271/201000427 October 2010IR 05000271-10-04 on 07/01/2010 - 09/30/2010 for Vermont Yankee Nuclear Power Station, Identification and Resolution of Problems
ML10258000914 September 2010NRC Staff'S Opposition to New England Coalition'S Motion to Reopen the Hearing and Answer to Proposed New Contention and Affidavit of Roy K. Mathew
IR 05000271/201000329 July 2010IR 05000271-10-003, on 04/01/2010 - 06/30/2010; Vermont Yankee Nuclear Power Station; Refueling and Other Outage Activities
IR 05000271/201000210 May 2010IR 05000271-10-002; 01/01/2010 - 03/31/2010; Vermont Yankee Nuclear Power Station; Maintenance Effectiveness, Maintenance Risk Assessments and Emergent Work Control, and Identification and Resolution of Problems
ML1109702017 April 2010E-mail from K. Kingsley, Entergy, Regarding NRC DFI to Enterg, Dated March 1, 2010
ML1006404252 March 2010G20100128/EDATS: OEDO-2010-0176 - Mike Mulligan E-Mail 2.206 Petition on Vermont Yankee Surrounding Maintenance & Testing of High Pressure Coolant Injection of December 4, 2009
IR 05000271/200900525 January 2010IR 05000271-09-005, on 09/30/2009-12/31/2009; Vermont Yankee Integrated Inspection Report
IR 05000271/20094056 January 2010IR 05000271-09-405; on 12/1/09 - 12/2/09; Vermont Yankee Nuclear Power Station; Inspection of the Identification and Resolution of Problems
IR 05000271/20090049 November 2009IR 05000271-09-004, on 07/01/09 to 09/30/09, for Vermont Yankee Nuclear Power Station - NRC Integrated Inspection Report
IR 05000271/20094026 July 2009IR 05000271-09-402, on 06/01/2009 - 06/05/2009, for Vermont Yankee
IR 05000271/20090063 June 2009IR 05000271-09-006 on 04/06/09 - 04/23/09 for Vermont Yankee, Problem Identification and Resolution Inspection Report
IR 05000271/200800910 October 2008IR 05000271-08-009, Vermont Yankee Nuclear Power Station, NRC Special Inspection
IR 05000271/200800626 September 2008IR 05000271-08-006 & 07200059-08-001, on 04/21/2008 - 08/13/2008, Vermont Yankee Nuclear Power Station, Maintenance Effectiveness
IR 05000271/200800826 September 2008IR 05000271-08-008 on 07/21/2008 - 08/14/2008 for Vermont Yankee
IR 05000271/200840215 May 2008EA-08-134, Vermont Yankee - Final Significance Determination for a Greater than Green Finding and Notice of Violation (NRC Physical Security Baseline Inspection Report 05000271/2008402) (Redacted)
IR 05000271/200800229 April 2008IR 05000271-08-002; on 01/01/2008 - 03/31/2008; Vermont Yankee Nuclear Power Station; Maintenance Effectiveness - NRC Integrated Inspection Report
ML08240175028 April 2008New England Coalition, Inc. - Contentions 4, Prefiled Exhibits NEC-JH_53, NEC-RH_03, NEC-UW_03 - NEW-UW_11, Volume 2
ML12157A26528 April 2008New England Coalition, Inc Contention 3 Prefiled Exhibits NEC-JH_54-NEC-JH_61
ML08157060828 April 2008New England Coalition, Inc. Contention 4, Prefiled Exhibits, NEC-JH_36 - NEC-JH_53, NEC_RH_03, NEC-UW_03 - NEC-UW_13, Volume 1
ML08115024023 April 2008IR 05000271-08-402, on 03/10/2008 - 03/14/2008, Vermont Yankee Nuclear Power Station, Physical Protection (Letter Only)
ML0729006248 November 2007Distribution of Revision 2 of the Nrc'S Significance Determination Process Risk-Informed Inspection Notebooks, and Accompanying Phase 2 Pre-Solved Tables
IR 05000271/20070047 November 2007IR 05000271-07-004, on 07/01/07 - 09/30/07, Vermont Yankee Nuclear Power Station; Maintenance Effectiveness