IR 05000400/20230039 November 2023Integrated Inspection Report 05000400/2023003
IR 05000400/202344017 July 2023Special Inspection Report 05000400/2023440 and Preliminary Greater than Green Finding and Apparent Violation Cover Letter
IR 05000400/202300110 May 2023Integrated Inspection Report 05000400 2023001
IR 05000400/20220047 February 2023Integrated Inspection Report 05000400/2022004
IR 05000400/202200310 November 2022Integrated Inspection Report 05000400/2022003
IR 05000400/20220025 August 2022Integrated Inspection Report 05000400/2022002
IR 05000400/202201013 June 2022Design Basis Assurance Inspection (Programs) Inspection Report 05000400/2022010
IR 05000400/202100310 November 2021Integrated Inspection Report 05000400/2021003
IR 05000400/202100129 April 2021Integrated Inspection Report 05000400/2021001
IR 05000400/202000427 January 2021Integrated Inspection Report 05000400/2020004
IR 05000400/20200112 December 2020Biennial Problem Identification and Resolution Inspection Report 05000400/2020011
IR 05000400/20200036 November 2020Integrated Inspection Report 05000400/2020003
ML20237F4354 September 2020Issuance of Amendments Regarding the Technical Specification Requirements Pertaining to Mode Change Limitations
IR 05000400/202000211 August 2020Integrated Inspection Report 05000400/2020002
ML20223A27710 August 2020Integrated Inspection Report 05000400/2020002
ML20099F50529 June 2020Issuance of Amendment No. 177 Regarding Elimination of Certain Technical Specification Requirements in Alignment with Improved Standard Technical Specifications
ML20147A03015 May 2020Amendment 63 to Final Safety Analysis Report, Chapter 13, Conduct of Operations
IR 05000400/20200017 May 2020Integrated Inspection Report 05000400/2020001
IR 05000400/201900324 October 2019Integrated Inspection Report 05000400/2019003
IR 05000400/201900110 May 2019Nuclear Regulatory Commission Integrated Inspection Report 05000400/2019001
IR 05000400/20190102 May 2019NRC Design Bases Assurance Inspection (Programs) Report 05000400/2019010
IR 05000400/20180027 September 2018Errata - Shearon Harris Nuclear Power Plant - Nuclear Regulatory Commission Integrated Inspection Report 005000400/2018002
ML18222A16510 August 2018Nuclear Regulatory Commission Integrated Inspection Report 05000400/2018002
ML18214A42331 July 2018EP SDP Comment Form, Over-Classification Improvement
ML18214A42031 July 2018EP SDP Comment Form - Dce
ML18214A42131 July 2018EP SDP Comment Form Declaration Improvement
ML18214A42231 July 2018EP SDP Comment Form ANS Improvement
IR 05000400/20170037 November 2017Regulatory Commission Integrated Inspection Report 05000400/2017003
ML20311A5566 November 20172017 Q1-Q4 ROP Inspection Findings
IR 05000400/201700722 May 2017NRC Design Bases Inspection Assurance Inspection (Team) Report Number 05000400/2017007
IR 05000400/201700121 April 2017NRC Integrated Inspection Report 05000400/2017001
IR 05000400/201600427 January 2017NRC Integrated Inspection Report 05000400/2016004
IR 05000400/20160031 November 2016NRC Integrated Inspection Report 050000400/2016003
IR 05000400/201600227 July 2016NRC Integrated Inspection Report 05000400/2016002, April 1, 2016 Through June 30, 2016
IR 05000400/201600119 April 2016NRC Integrated Inspection Report 05000400/2016001, January 1, 2016 Through March 31, 2016
IR 05000400/201500427 January 2016NRC Integrated Inspection Report 05000400/2015004, October 1, 2015 Through December 31, 2015
IR 05000400/201500722 December 2015IR 05000400/2015007, November 16, 2015, Through December 10, 2015, Shearon Harris Nuclear Power Plant - NRC Evaluation of Changes, Tests, and Experiments and Permanent Plant Modifications
IR 05000400/201500813 November 2015IR 05000400/2015008 on September 14, 2015 - October 01, 2015; Shearon Harris Nuclear Power Plant, Unit 1; Biennial Inspection of Problem Identification and Resolution Program
IR 05000400/201500330 October 2015IR 05000400/2015003; on July 1, 2015, Through September 30, 2015; Duke Energy Progress, Inc., Shearon Harris Nuclear Power Plant, Unit 1, Flood Protection Measures, Maintenance Effectiveness, Plant Modifications, Problem Identification and
IR 05000400/201500229 July 2015IR 05000400/2015002; April 1, 2015, - June 30, 2015; Shearon Harris Nuclear Power Plant, Unit 1, Operability Determinations and Functionality Assessments, Plant Modifications
IR 05000400/201500130 April 2015IR 05000400/2015001; 01/01/2015 - 03/31/2015; Duke Energy Progress, Inc., Shearon Harris Nuclear Power Plant, Unit 1, Integrated Inspection Report
IR 05000400/201400527 January 2015IR 05000400/2014005; on October 1, 2014, Through December 31, 2014; Duke Energy Progress, Inc., Shearon Harris Nuclear Power Plant, Unit 1, Operability Determinations and Functionality Assessments
IR 05000400/201440311 December 2014IR 05000400/2014403, on 11/20/2014, Shearon Harris Nuclear Plant, U.S. Nuclear Regulatory Commission Security Inspection Report
IR 05000400/201400430 October 2014IR 05000400/2014004; Duke Energy Progress, Inc.; on July 1, 2014 - September 30, 2014; Shearon Harris Nuclear Power Plant, Unit 1; Identification and Resolution of Problems
IR 05000400/20140073 September 2014IR 05000400/2014007, June 23, 2014 - July 25, 2014, Shearon Harris Nuclear Plant, Unit 1, Component Design Bases Inspection
IR 05000400/201400325 July 2014IR 05000400-14-003: Duke Energy Progress, Inc.; on April 1, 2014 - June 30, 2014; Shearon Harris Nuclear Power Plant, Unit 1; Plant Modifications
IR 05000400/201400823 June 2014IR 05000400-14-008, 04/21-25/2014 - 05/5-9/2014, Shearon Harris, NRC Triennial Fire Protection
IR 05000400/201400228 April 2014IR 05000400-14-002, Duke Energy Progress, Inc.; on January 1, 2014 - March 31, 2014; Shearon Harris Nuclear Power Plant, Unit 1; Operability Evaluations, Surveillance Testing, and Identification and Resolution of Problems
IR 05000400/20130054 February 2014IR 05000400-13-005 and 05000400-13-502, on October 1, 2013 - December 31, 2013; Shearon Harris Nuclear Power Plant, Unit 1; Plant Modifications and Identification and Resolution of Problems
IR 05000400/20130044 November 2013IR 05000400-13-004: on 07/01/2013 & 09/30/2013; Shearon Harris Nuclear Power Plant, Unit 1; Fire Protection