 Issue dateTitle
ML23261B18514 September 2023Notification of Inspection and Request for Information
IR 05000382/20220021 November 2022Revised Integrated Inspection Report 05000382/2022002
ML22217A1119 August 2022Integrated Inspection Report 05000382/2022002
ML21327A45422 November 2021ISI PWR RFI
IR 05000382/202100311 November 2021Electrical Station, Unit 3 - Integrated Inspection Report 05000382/2021003
IR 05000382/20210025 August 2021Integrated Inspection Report 05000382/2021002
IR 05000382/202100110 May 2021Integrated Inspection Report 05000382/2021001
IR 05000382/202000329 October 2020Integrated Inspection Report 05000382/2020003
ML20258A08811 September 201911 to Final Safety Analysis Report, Chapter 06 - Engineered Safety Features (EPID L-2020-LLA-0164) - Redacted
IR 05000382/201900130 April 2019NRC Integrated Inspection Report 05000382/2019001
IR 05000382/201800330 October 2018NRC Integrated Inspection Report 05000382/2018003
ML20255A24225 July 201810 to Final Safety Analysis Report, Chapter 6, Engineered Safety Features (EPID L-2020-LLA-0164) - Redacted
W3F1-2018-0030, Supplemental Information Supporting the Request for NRC Alternative to ASME IWA-5211 Regarding Charging Pipe Visual Inspection, Relief Request W3-ISI-03031 May 2018Supplemental Information Supporting the Request for NRC Alternative to ASME IWA-5211 Regarding Charging Pipe Visual Inspection, Relief Request W3-ISI-030
ML18078A3336 March 2018FEMA - After Action Report/Improvement Plan Exercise Date December 5-6, 2017, Radiological Emergency Preparedness (REP) Program for Waterford, Unit 3
W3F1-2017-0075, Submittal of the Inservice Testing Plan for the Fourth 10-Year Interval4 December 2017Submittal of the Inservice Testing Plan for the Fourth 10-Year Interval
W3F1-2017-0082, Submittal of the Inservice Inspection Plan and Containment Inservice Inspection Plan for the Fourth 10-Year Interval4 December 2017Submittal of the Inservice Inspection Plan and Containment Inservice Inspection Plan for the Fourth 10-Year Interval
ML16256A18625 August 2016Revision 309 to Final Safety Analysis Report, Chapter 3, Design of Structures, Components Equipment and Systems, Section 3.8 - Design of Category I Structures
ML16256A45225 August 2016Revision 309 to Final Safety Analysis Report, Chapter 9, Auxiliary Systems, Section 9.5
ML15278A23114 September 20152015-09 Final Operating Test
ML15225A56414 September 20152015-09 Draft Operating Test and Revised Outlines
IR 05000382/201500230 July 2015IR 05000382/2015002; on 04/01/2015 - 06/30/2015; Waterford Steam Electric Station, Unit 3; Adverse Weather Protection, Problem Identification and Resolution
IR 05000382/201400512 February 2015IR 05000382/2014005; on 10/01/2014 - 12/31/2014; Waterford, Unit 3, Adverse Weather Protection, Operability Determinations and Functionality Assessments, Post-Maintenance Testing, Occupational ALARA Planning and Controls, and Other Activiti
ML14129A35029 April 2014Report of Facility Changes, Tests and Experiments and Commitment Changes for Two Year Period Ending April 25, 2014
IR 05000382/201300313 August 2013IR 05000382-13-003; 04/01/2013 - 06/30/2013; Waterford Steam Electric Station, Unit 3, Integrated Resident & Regional Report; Adv. Weather Prot.; Eval of Changes, Test, or Exper & Perm Plant Mods; Refuel. & Other Outage Act.; Pi&R; Other Ac
W3F1-2013-0024, Engineering Report WF3-CS-12-00003, Attachment D, Rev. 0, Area Walk-by Checklists (Awcs), Enclosure to W3F1-2013-0024, Pages 592 - 817 of 101425 March 2013Engineering Report WF3-CS-12-00003, Attachment D, Rev. 0, Area Walk-by Checklists (Awcs), Enclosure to W3F1-2013-0024, Pages 592 - 817 of 1014
ML13120A46225 March 2013Engineering Report WF3-CS-12-00003, Attachment G, Rev. 0, Peer Review Checklist for SWEL, Enclosure to W3F1-2013-0024, Pages 820 - 1014 of 1014
IR 05000382/201200514 February 2013IR 05000382-12-005; 10/01/2012 - 12/31/2012; Waterford Steam Electric Station, Unit 3, Integrated Resident and Regional Report; Radiological Hazard Assessment and Exposure Controls, Problem Identification and Resolution
ML12333A27416 November 2012WF3-CS-12-00003, Rev. 0, Waterford Steam Electric Station Unit 3 Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic. Part 4
IR 05000382/20120085 November 2012IR 05000382-12-008, July 16, 2012 - September 24, 2012, Waterford 3 Biennial Baseline Inspection of the Identification and Resolution of Problems.
ML12310A4975 November 2012IR 05000382-12-008, July 16, 2012 - September 24, 2012, Waterford 3 Biennial Baseline Inspection of the Identification and Resolution of Problems.
IR 05000382/201100613 May 2011NRC Temporary Instruction 2515/183, Inspection Report 050003822011006, 03/23/2011 04/29/2011 - Follow-up to the Fukushima Daiichi Nuclear Station Fuel Damage Event
ML11097045421 March 2011WT-2011-03 Final Operating Test
W3F1-2010-0079, Response to NRC Request for Additional Information Regarding Exemption Request3 November 2010Response to NRC Request for Additional Information Regarding Exemption Request
IR 05000382/201000210 May 2010IR 05000382-10-002 on 01/01/2010 - 03/31/2010 for Waterford Steam Electric Station, Unit 3, Integrated Inspection Report
ML09323067518 November 2009IR 05000382-09-004; on July 8, 2009 Through October 7, 2009; Waterford Steam Electric Station, Unit 3; Operability Evaluations
ML1012704955 October 2009WT-2009-10-FINAL OP Test
CNRO-2009-00001, Relief Requests for Third 120 Month Inservice Inspection Interval23 January 2009Relief Requests for Third 120 Month Inservice Inspection Interval
IR 05000382/200800314 August 2008IR 05000382-08-003; on 04/08/08-06/30/08; Waterford Steam Electric Station, Unit 3; Integrated Resident and Regional Report, ALARA Planning and Controls, Access Control to Radiologically Significant Areas, Inservice Inspection Activities
ML08156072621 May 2008CEP-ISI-104, Rev. 0, ASME Section XI, Division 1, Inservice Inspection Program.
CNRO-2008-00016, Relief Requests for Third 120 Month Inservice Testing Interval20 May 2008Relief Requests for Third 120 Month Inservice Testing Interval
W3F1-2008-0013, Revision to Request for Alternative W3-ISI-005, Request to Use ASME Code Case N-71614 February 2008Revision to Request for Alternative W3-ISI-005, Request to Use ASME Code Case N-716
ML08014031828 January 2008Staff Audit Report on Results of Corrective Actions to Address GSI-191 GL 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design-Basis Accidents at PWRs
W3F1-2007-0059, Response to Request for Additional Information on Request for Alternative W3-ISI-004 - Proposed Alternative to Second Interval ISI Examinations, Waterford Steam Electric Station, Unit 311 December 2007Response to Request for Additional Information on Request for Alternative W3-ISI-004 - Proposed Alternative to Second Interval ISI Examinations, Waterford Steam Electric Station, Unit 3
CNRO-2007-00044, Unit 1 and Arkansas Nuclear One, Units 1 & 2 - Inservice Testing Plan30 November 2007Unit 1 and Arkansas Nuclear One, Units 1 & 2 - Inservice Testing Plan
W3F1-2007-0061, Supplement to Request for Alternative W3-ISI-005 Request to Use ASME Code Case N-71630 November 2007Supplement to Request for Alternative W3-ISI-005 Request to Use ASME Code Case N-716
W3F1-2007-0046, Request for Alternative W3-ISI-005, Request to Use ASME Code Case N-71618 October 2007Request for Alternative W3-ISI-005, Request to Use ASME Code Case N-716
ML07292043318 October 2007Request for Alternative W3-ISI-005, Request to Use ASME Code Case N-716
ML0603903869 February 2006Request for Additional Information Response to Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design-Basis Accident at Pressurized-Water Reactors.
ML05103006815 April 2005License Amendment 199 Regarding Extended Power Uprate
W3F1-2004-0110, Report of Facility Changes, Tests and Experiments and Commitment Changes29 November 2004Report of Facility Changes, Tests and Experiments and Commitment Changes