Semantic search

Jump to navigation Jump to search
 Issue dateTitle
ML23243B04919 December 2023VEGP Units 3 and 4, Safety Evaluation, LAR-22-002, TS 3.8.3 Inverters Operating, Completion Time Extension - Enclosure 3
ML23335A12319 December 2023Safety Evaluation Final Integrated Plan
ML23312A35014 November 2023Integrated Inspection Report 05200026/2023003
ML23318A45814 November 2023Integrated Inspection Report 05200025/2023003
ML23304A2687 November 2023License Amendment Request to Revise the Ultimate Heat Sink Mission Time Pre Submittal Meeting on November 7, 2023
ML23311A2457 November 2023Pre-Submittal Meeting on November 7, 2023 - License Amendment Request to Revise the Ultimate Heat Sink Mission Time (Slides)
ND-23-0025, Compliance with Order EA-12-04921 August 2023Compliance with Order EA-12-049
ML23223A00214 August 2023(Vegp), Unit 3, Integrated Inspection Report 05200025/2023002
NL-23-0670, Response to Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-1448311 August 2023Response to Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-14483
ML23093A0281 August 2023Issuance of Amendments Nos. 220 and 203, Regarding Use of Accident Tolerant Fuel Lead Test Assemblies
ML23214A22130 July 2023Historical Vogtle Unit 3 Combined License Appendix C as of July 30 2023
ML23158A20919 July 2023LAR-23-005 U/4 Amd 189 Timing of TS Effectiveness Prior to Initial Criticality Amendment Attachment
ML23158A20619 July 2023LAR-23-005 U/4 Amd 189 Timing of TS Effectiveness Prior to Initial Criticality Safety Evaluation
ML23165A21613 June 2023Enclosure 3: Vogtle Electric Generating Plant, Units 3 and 4, Updated Final Safety Analysis Report, Tier 1, Revision 11
ML23165A21913 June 2023Enclosure 9: Vogtle Electric Generating Plant, Units 3 and 4, Technical Specifications Bases, Revision 73
ML23165A21513 June 2023Enclosure 1: Vogtle Electric Generating Plant, Units 3 and 4, Updated Final Safety Analysis Report, Revision 12
NL-23-0467, Response to Request for Additional Information Regarding License Amendment Request: Timing of Unit 4 Technical Specifications Effectiveness Prior to Initial Criticality (LAR-23-005S1)9 June 2023Response to Request for Additional Information Regarding License Amendment Request: Timing of Unit 4 Technical Specifications Effectiveness Prior to Initial Criticality (LAR-23-005S1)
ML23121A3204 May 2023NRC Initial Test Program and Operational Programs Integrated Inspection Report 05200025/2023010
NL-23-0135, License Amendment Request: Timing of Technical Specifications Effectiveness Prior to Initial Criticality (LAR-23-005)17 April 2023License Amendment Request: Timing of Technical Specifications Effectiveness Prior to Initial Criticality (LAR-23-005)
ML23097A0067 April 2023COL Docs - FW Pre-Submittal Meetings
ML23044A39014 February 2023Integrated Inspection Report05200025 2022007
ML23033A3977 February 2023NRC Integrated Inspection Report 05200026/2022007
ML23013A22013 January 2023Safety Evaluation for License Amendment No. 189 Tech Spec Limiting Conditions for Operability Reqs for Auto Depressurization System Stage 4 Flow Paths Prior to Initial Criticality
ND-22-0881, License Amendment Request for Technical Specification 3.8.3, Inverters Operating, Completion Time Extension (LAR-22-002)3 January 2023License Amendment Request for Technical Specification 3.8.3, Inverters Operating, Completion Time Extension (LAR-22-002)
NL-22-0764, License Amendment Request to Revise Technical Specification 1.1 and Add 5.5.23 to Use Online Monitoring Methodology21 December 2022License Amendment Request to Revise Technical Specification 1.1 and Add 5.5.23 to Use Online Monitoring Methodology
IR 05000424/20220102 December 2022Design Basis Assurance Inspection (Teams) Inspection Report 05000424/2022010 and 05000425/2022010
ML22307A0072 November 2022Draft LAR for TS 3.8.3 Inverters Operating Completion Time Extension
ML22326A06731 October 20224 to the Updated Final Safety Analysis Report, Chapter 3, Design of Structures, Components, Equipment, and Systems (Part 5 of 7)
ML22326A11331 October 20224 to the Updated Final Safety Analysis Report, Chapter 7, Instrumentation and Controls (Part 2 of 2), and Chapter 8, Electric Power (Part 1 of 3)
ML22326A05931 October 20224 to the Updated Final Safety Analysis Report, Chapter 3, Design of Structures, Components, Equipment, and Systems (Part 2 of 7)
NL-22-0810, 4 to the Updated Final Safety Analysis Report, Technical Specification Bases Changes, Technical Requirements Manual Changes, 10 CFR 50.59 Summary Report and Revised NRC Commitments Report31 October 20224 to the Updated Final Safety Analysis Report, Technical Specification Bases Changes, Technical Requirements Manual Changes, 10 CFR 50.59 Summary Report and Revised NRC Commitments Report
ML22326A12131 October 20224 to the Updated Final Safety Analysis Report, Chapter 15 (Part 2 of 2), Chapter 16, Chapter 17, Chapter 18, Chapter 19, Table of Contents, Rev 24 Epl
ML22326A11431 October 20224 to the Updated Final Safety Analysis Report, Chapter 10, Steam and Power Conversion System (Part 2 of 2); Chapter 11, Chapter 12, Chapter 13, Chapter 14, and Chapter 15 (Part 1 of 2)
ML22326A06231 October 20224 to the Updated Final Safety Analysis Report, Chapter 1, Introduction and General Description of Plant and Chapter 2, Site Characteristics (Part 1 of 2)
ML22326A11631 October 20224 to the Updated Final Safety Analysis Report, Chapter 6, Engineered Safety Features (Part 3 of 3) and Chapter 7, Instrumentation and Controls (Part 1 of 2)
ML22326A12031 October 20224 to the Updated Final Safety Analysis Report, Chapter 8, Electric Power (Part 3 of 3); Chapter 9, Auxiliary Systems; and Chapter 10, Steam and Power Conversion System (Part 1 of 2)
ML22326A06531 October 20224 to the Updated Final Safety Analysis Report, Chapter 3, Design of Structures, Components, Equipment, and Systems (Part 7 of 7) and Chapter 4, Reactor (Part 1 of 2)
ML22326A06431 October 20224 to the Updated Final Safety Analysis Report, Chapter 2, Site Characteristics (Part 2 of 2) and Chapter 3, Design of Structures, Components, Equipment, and Systems (Part 1 of 7)
IR 05000424/202200327 October 2022Integrated Inspection Report 05000424/2022003 and 05000425/2022003
ML22220A19910 August 2022Attachment 1 - NUREG-2194, Vol. 1, Rev. 1, Standard Technical Specifications, Westinghouse Advanced Passive 1000 Plants, Volume 1, Specifications
ML22220A20010 August 2022Attachment 2 - NUREG-2194, Vol. 2, Rev. 1, Standard Technical Specifications, Westinghouse Advanced Passive 1000 Plants. Volume 2, Bases
ML22193A29113 July 2022NRC Integrated Inspection Reports 05200025/2022003, 05200026/2022003 and Second Quarter Assessment Follow-Up Letter
ML22116A0845 July 2022Issuance of Amendment Nos. 215 and 198, Regarding Revision to Technical Specification 3.7.2, Main Steam Isolation Valves (Msivs)
NL-22-0288, License Amendment Request and Exemptions to Allow Use of Lead Test Assemblies for Accident-Tolerant Fuel30 June 2022License Amendment Request and Exemptions to Allow Use of Lead Test Assemblies for Accident-Tolerant Fuel
ND-22-0328, Enclosuvogtle Electric Generating Plant, Units 3 & 4 - Fukushima Response NEI 12-01 On-Shift Staffing Analysis Phase 2 Report, Revision 3.0, Standard Emergency Plan Annex, Revision 6.029 June 2022Enclosuvogtle Electric Generating Plant, Units 3 & 4 - Fukushima Response NEI 12-01 On-Shift Staffing Analysis Phase 2 Report, Revision 3.0, Standard Emergency Plan Annex, Revision 6.0
ML22179A14815 June 2022Technical Specifications Bases, Revision 70
ML22179A14615 June 2022Tier 1, Revision 10, Updated Through 04/22/2022
ML22091A3161 April 2022NRC Initial Test Program and Operational Programs Inspection Reports 05200025/2022002, 05200026/2022002
ND-22-0104, ITAAC Closure Notification on Completion of ITAAC 2.6.09.06 (Index Number 647)18 February 2022ITAAC Closure Notification on Completion of ITAAC 2.6.09.06 (Index Number 647)
NL-21-0994, Adoption of TSTF-283-A, Revision 3, Modify Section 3.8 Mode Restriction Notes22 December 2021Adoption of TSTF-283-A, Revision 3, Modify Section 3.8 Mode Restriction Notes