Issue date | Title | |
---|---|---|
ML22111A192 | 31 March 2022 | 2 to Updated Safety Analysis Report, Chapter 1, Introduction and General Description of Plant |
ML22111A203 | 31 March 2022 | 2 to Updated Safety Analysis Report, Chapter 5, Reactor Coolant System and Connected Systems |
ML22111A217 | 31 March 2022 | 2 to Updated Safety Analysis Report, Appendix B, Construction Material Standards and Quality Control Procedures |
ML22021B660 | 1 February 2022 | Issuance of Amendments Related to Order Approving Transfer of Licenses (EPID L-2022-LLM-0000)-Enclosure 1 |
ML21277A193 | 16 November 2021 | Enclosure 2, Draft Conforming License Amendments |
RS-21-039, Supplemental Information Regarding Application for Order Approving Transfers and Proposed Conforming License Amendments | 25 March 2021 | Supplemental Information Regarding Application for Order Approving Transfers and Proposed Conforming License Amendments |
ML20105A245 | 31 March 2020 | 1 to Updated Safety Analysis Report, Chapter 1, Introduction and General Description of Plant |
ML20105A256 | 31 March 2020 | 1 to Updated Safety Analysis Report, Chapter 5, Reactor Coolant System and Connected Systems |
ML20105A270 | 31 March 2020 | 1 to Updated Safety Analysis Report, Appendix B, Construction Material Standards and Quality Control Procedures |
IR 05000461/2018004 | 12 February 2019 | NRC Integrated Inspection Report 05000461/2018004; 07201046/2018001 |
ML17223A470 | 11 August 2017 | NRC Integrated Inspection Report 05000461/2017002 and Notice of Violation |
RS-16-196, Clinton - Updated Safety Analysis Report (Usar), Revision 18, Appendix B - Construction Material Standards and Quality Control Procedures | 31 October 2016 | Clinton - Updated Safety Analysis Report (Usar), Revision 18, Appendix B - Construction Material Standards and Quality Control Procedures |
ML16306A142 | 31 October 2016 | Updated Safety Analysis Report (Usar), Revision 18, Appendix B - Construction Material Standards and Quality Control Procedures |
U-604237, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report | 14 August 2015 | Post-Outage 90-Day Inservice Inspection (ISI) Summary Report |
IR 05000461/2015009 | 11 August 2015 | EA-15-064; Final Significance Determination of a White Finding with Assessment Followup and Notice of Violation; NRC Inspection Report No. 05000461/2015009; Clinton Power Station |
IR 05000461/2013005 | 11 February 2014 | IR 05000451-13-005, 10/01/2013 - 12/31/2013, Clinton Power Station, Unit 1, Outage Activities, Identification & Resolution of Problems, Occupational As-Low-As-Reasonably-Achievable Planning & Controls, & Follow-up of Events & Notices of Enforcement Discr |
IR 05000451/2013005 | 11 February 2014 | IR 05000451-13-005, 10/01/2013 - 12/31/2013, Clinton Power Station, Unit 1, Outage Activities, Identification & Resolution of Problems, Occupational As-Low-As-Reasonably-Achievable Planning & Controls, & Follow-up of Events & Notices of Enf |
ML14031A222 | 28 January 2014 | Post-Outage 90-Day Inservice Inspection (ISI) Summary Report |
ML14015A285 | 9 January 2014 | Updated Safety Analysis Report, Revision 16, Appendix B - Construction Material Standards and Quality Control Procedures |
ML14015A104 | 9 January 2014 | Updated Safety Analysis Report, Revision 16, Chapter 1 - Introduction and General Description of Plant |
RS-14-006, Clinton, Unit 1, Updated Safety Analysis Report, Revision 16, Appendix B - Construction Material Standards and Quality Control Procedures | 9 January 2014 | Clinton, Unit 1, Updated Safety Analysis Report, Revision 16, Appendix B - Construction Material Standards and Quality Control Procedures |
RS-14-006, Clinton, Unit 1, Updated Safety Analysis Report, Revision 16, Chapter 1 - Introduction and General Description of Plant | 9 January 2014 | Clinton, Unit 1, Updated Safety Analysis Report, Revision 16, Chapter 1 - Introduction and General Description of Plant |
ML13016A349 | 10 January 2013 | Updated Safety Analysis Report, Revision 15, Appendix B - Contruction Material Standards and Quality Control Procedures |
U-604060, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report | 21 March 2012 | Post-Outage 90-Day Inservice Inspection (ISI) Summary Report |
RA-11-087, Response to Request for Additional Information - Proposed Alternative to Utilize Code Case N-789, Alternative Requirements for Pad Reinforcement of Class 2 and 3 Moderate Energy Carbon Steel Piping for Raw Water Service, Section XI, Divisi | 10 November 2011 | Response to Request for Additional Information - Proposed Alternative to Utilize Code Case N-789, Alternative Requirements for Pad Reinforcement of Class 2 and 3 Moderate Energy Carbon Steel Piping for Raw Water Service, Section XI, Divisio |
ML11189A129 | 8 July 2011 | IR 05000461-11-008, on 05/16/2011 - 06/03/2011, Clinton Power Station; Identification and Resolution of Problems |
U-603958, Post-Outage 90-Day Inservice Inspection Summary Report | 6 May 2010 | Post-Outage 90-Day Inservice Inspection Summary Report |
U-603907, Submittal of Program for the Second 10-Year Interval Containment Inservice Inspection Plan | 31 July 2009 | Submittal of Program for the Second 10-Year Interval Containment Inservice Inspection Plan |
ML22216A210 | 1 January 2009 | 2 to Updated Safety Analysis Report Chapter 6, Engineered Safety Features_Redacted |
U-603857, 90-Day Post-Outage Inservice Inspection (ISI) Summary Report | 5 May 2008 | 90-Day Post-Outage Inservice Inspection (ISI) Summary Report |
RS-07-134, Co. and Amergen Energy Co., LLC, Response to Request for Additional Information Request for Relief - Use of the Boiling Water Reactor Vessel and Internals Project (BWRVIP) Guidelines in Lieu of Specific ASME Code Requirements | 5 October 2007 | Co. and Amergen Energy Co., LLC, Response to Request for Additional Information Request for Relief - Use of the Boiling Water Reactor Vessel and Internals Project (BWRVIP) Guidelines in Lieu of Specific ASME Code Requirements |
U-603774, 90-Day Post-Outage Inservice Inspection (SI) Summary Report | 26 May 2006 | 90-Day Post-Outage Inservice Inspection (SI) Summary Report |
ML070930357 | 31 January 2005 | Cps/Usar, Appendix B, Construction Material Standards and Quality Control Procedures, Revision 11 |
ML070930225 | 31 January 2005 | Cps/Usar, Chapter 6, Engineered Safety Features, Revision 11 |
ML070920206 | 31 January 2005 | Cps/Usar, Chapter 5, Reactor Coolant System and Connected System, Revision 11 |
ML070920167 | 31 January 2005 | Cps/Usar, Chapter 1, Introduction and General Description of Plant, Revision 11 |
ML042390181 | 16 July 2004 | Holtec International Report No. HI-2033124 Spent Fuel Storage Expansion at Clinton Power Station. |
U-603676, Day Post-Outage Inservice Inspection (ISI) Summary Report | 27 May 2004 | Day Post-Outage Inservice Inspection (ISI) Summary Report |
RS-04-065, Request for Relief from ASME Section XI for Performance of Class 2 & 3 Raw Water Piping Repairs | 26 April 2004 | Request for Relief from ASME Section XI for Performance of Class 2 & 3 Raw Water Piping Repairs |
U-603571, Day Post-Outage Inservice Inspection (ISI) Summary Report | 2 August 2002 | Day Post-Outage Inservice Inspection (ISI) Summary Report |
IR 05000461/2002006 | 30 July 2002 | IR 05000461-02-006, on 04/01-06/30/2002, Amergen Energy Company LLC, Clinton Power Station. Personnel Performance During Non-Routine Plant Evolutions; Refueling & Other Outage Activities & Event Followup |
RS-02-071, Request for Approval of Quality Assurance Program Changes for Exelon Generation Company, LLC, and Amergen Energy Company, LLC, Nuclear Power Plants | 9 April 2002 | Request for Approval of Quality Assurance Program Changes for Exelon Generation Company, LLC, and Amergen Energy Company, LLC, Nuclear Power Plants |
ML20211C962 | 26 July 1999 | ISI Summary Rept |
U-602683, Provides Response to NRCs RAI Re Adequacy & Availabilty of Design Bases Info at Util,Per 10CFR50.54(f) | 12 February 1997 | Provides Response to NRCs RAI Re Adequacy & Availabilty of Design Bases Info at Util,Per 10CFR50.54(f) |
ML20137A102 | 10 July 1996 | Rev 5 to App IV Second 10-Yr Interval Inservice Exam Plan |
ML20086G215 | 21 June 1995 | ISI Summary Rept, for Clinton Power Station, |
IR 05000461/1993020 | 23 December 1993 | Insp Rept 50-461/93-20 on 931006-1202.No Violations Noted. Major Areas Inspected:Review of Program,Procedures, Observation of Work Activities,Data Review & Evaluation & Review of Erosion/Corrosion Program |
ML20063B641 | 21 December 1993 | ISI Summary Rept Refueling Outage RF-4 |
ML20102B207 | 24 June 1992 | Part 21 Rept Re Cracking of Stellite 21 Hardfacing on Guide Nose of Poppets Supplied as Part of MSIV Leakage Improvement Mod.Initially Reported by Clei on 920522. Recommends That Liquid Penetrant Exam Be Performed |
Information Notice 1991-32, Possible Flaws in Certain Piping Systems Fabricated by Associated Piping and Engineering | 15 May 1991 | Possible Flaws in Certain Piping Systems Fabricated by Associated Piping and Engineering |