ML23241A045 | 29 August 2023 | COL Docs - FW Draft LAR and Exemption Request Regarding Tier 1 and Tier 2 Requirements |
ML23039A167 | 8 February 2023 | Draft LAR to Remove Tier 1 and Tier 2 Star Requirements |
NL-22-0208, License Amendment Request for Alternative Source Term, TSTF-51, TSTF-471, and TSTF-490 | 30 June 2022 | License Amendment Request for Alternative Source Term, TSTF-51, TSTF-471, and TSTF-490 |
ML20069A003 | 9 March 2020 | COL Docs - FW: Request for 2nd Psm on Thurs. March 19, 2020 - Request for Exemption to 10CFR52, Appendix D (Compliance with Tier 1 plant-specific DCD) |
ND-19-1095, (VEGP) Units 3 and 4 - Emergency Action Levels and Basis | 18 April 2019 | (VEGP) Units 3 and 4 - Emergency Action Levels and Basis |
ML19024A509 | 5 December 2018 | Licensing Amendment Request Non Concurrence Process Redacted E-mails (Redacted Version) |
ML18249A112 | 20 September 2018 | Documentation of the Completion of Required Actions Taken in Response to Fukushima Lessons Learned |
ML17293A427 | 7 March 2018 | Staff Review of Seismic Probabilistic Risk Assessment Associated with Reevaluated Seismic Hazard Implementation of the Near-Term Task Force Recommendation 2.1 |
ML18008A305 | 20 December 2017 | NCP-2017-16 Non-Concurrence Associated with VEGP, Units 1 and 2 - Staff Review of Seismic PRA Associated with NTTF Recommendation 2.1 |
ML15127A669 | 8 August 2017 | Issuance of Amendment Nos. 188 and 171, Implementation of NEI 06-09, Risk Informed Technical Specifications Initiative 4B, Risk Managed Technical Specification Guidelines |
NL-16-1830, Southern Nuclear Operating Company Response to RAI for License Amendment Regarding Emergency Action Level Schemes to Adopt NEI 99-01 Rev 6 and to Modify Radiation Monitors at Farley Nuclear Plant, Part 1C of 1C | 3 November 2016 | Southern Nuclear Operating Company Response to RAI for License Amendment Regarding Emergency Action Level Schemes to Adopt NEI 99-01 Rev 6 and to Modify Radiation Monitors at Farley Nuclear Plant, Part 1C of 1C |
ML16071A195 | 3 March 2016 | Enclosure 6: Clean-Typed EAL Schemes - License Amendment Request for Changes to EAL Schemes to Adopt NEI 99-01 Rev. 6 and to Modify Radiation Monitors at Farley Nuclear Plant |
ML16071A185 | 3 March 2016 | Enclosure 5: Marked-Up EAL Schemes - License Amendment Request for Changes to EAL Schemes to Adopt NEI 99-01 Rev. 6 and to Modify Radiation Monitors at Farley Nuclear Plant. Part 5 of 8 |
ML16071A160 | 3 March 2016 | Enclosure 5: Vogtle Marked-Up EAL Schemes - License Amendment Request for Changes to EAL Schemes to Adopt NEI 99-01 Rev. 6 and to Modify Radiation Monitors at Farley Nuclear Plant. Part 1 of 4 |
ML16071A176 | 3 March 2016 | Enclosure 5: Marked-Up EAL Schemes - License Amendment Request for Changes to EAL Schemes to Adopt NEI 99-01 Rev. 6 and to Modify Radiation Monitors at Farley Nuclear Plant. Part 1 of 8 |
NL-15-1898, Enclosure 5: Vogtle Marked-Up EAL Schemes - License Amendment Request for Changes to EAL Schemes to Adopt NEI 99-01 Rev. 6 and to Modify Radiation Monitors at Farley Nuclear Plant. Part 1 of 4 | 3 March 2016 | Enclosure 5: Vogtle Marked-Up EAL Schemes - License Amendment Request for Changes to EAL Schemes to Adopt NEI 99-01 Rev. 6 and to Modify Radiation Monitors at Farley Nuclear Plant. Part 1 of 4 |
NL-15-1898, Enclosure 5: Marked-Up EAL Schemes - License Amendment Request for Changes to EAL Schemes to Adopt NEI 99-01 Rev. 6 and to Modify Radiation Monitors at Farley Nuclear Plant. Part 1 of 8 | 3 March 2016 | Enclosure 5: Marked-Up EAL Schemes - License Amendment Request for Changes to EAL Schemes to Adopt NEI 99-01 Rev. 6 and to Modify Radiation Monitors at Farley Nuclear Plant. Part 1 of 8 |
NL-15-1898, Enclosure 5: Marked-Up EAL Schemes - License Amendment Request for Changes to EAL Schemes to Adopt NEI 99-01 Rev. 6 and to Modify Radiation Monitors at Farley Nuclear Plant. Part 5 of 8 | 3 March 2016 | Enclosure 5: Marked-Up EAL Schemes - License Amendment Request for Changes to EAL Schemes to Adopt NEI 99-01 Rev. 6 and to Modify Radiation Monitors at Farley Nuclear Plant. Part 5 of 8 |
NL-15-1898, Enclosure 6: Clean-Typed EAL Schemes - License Amendment Request for Changes to EAL Schemes to Adopt NEI 99-01 Rev. 6 and to Modify Radiation Monitors at Farley Nuclear Plant | 3 March 2016 | Enclosure 6: Clean-Typed EAL Schemes - License Amendment Request for Changes to EAL Schemes to Adopt NEI 99-01 Rev. 6 and to Modify Radiation Monitors at Farley Nuclear Plant |
ML15174A257 | 1 September 2015 | Letter to Licensees Coordination of Request for Information for Flooding Hazard Reevaluations and Mitigating Strategies for Beyond-Design-Basis External Events |
ML15049A153 | 17 February 2015 | Speech-S-15-001: Prepared Remarks of NRC Chairman Stephen G. Burns Platts 11th Annual Nuclear Energy Conference February 17, 2015- Washington, D.C |
ML14111A147 | 9 May 2014 | Seismic Screening and Prioritization Results Regarding Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Seismic Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Review of Insights |
ML14030A046 | 20 February 2014 | Letter from Eric J. Leeds Supplemental Information Related to Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Seismic Hazard Reevaluations for Recommendation 2.1 |
ML13044A561 | 1 March 2013 | Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Re Flooding Hazard Reevaluation for Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident |
ML121250387 | 3 May 2012 | Licensees, Response Opposing Petitioners' Motion to Stay |
ML12054A735 | 12 March 2012 | Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events |
ML12054A679 | 12 March 2012 | Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation |
ML12056A045 | 12 March 2012 | Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events |
ML12056A044 | 12 March 2012 | Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status |
NRC-2012-0067, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status | 12 March 2012 | Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status |
NRC-2012-0068, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events | 12 March 2012 | Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events |
ML11206B172 | 20 July 2011 | Update of Nuclear Regulatory Commission (NRC) Distribution List for Documents Containing Safeguards (Sgi), Official Use Only (Ouo), and Routine Information - (Vogtle Nuclear Plant) |
NL-11-0298, Comment (4) of M. J. Ajuni on Behalf of Southern Nuclear Operating Co. Draft NRC Regulatory Issue Summary (RIS) 2011-XX, Adequacy of Station Electric Distribution System Voltages | 17 February 2011 | Comment (4) of M. J. Ajuni on Behalf of Southern Nuclear Operating Co. Draft NRC Regulatory Issue Summary (RIS) 2011-XX, Adequacy of Station Electric Distribution System Voltages |
ML110480403 | 17 February 2011 | Edwin I. Hatch, Units 1 and 2, and Vogtle, Units 1 and 2, Comments on Draft NRC Regulatory Issue Summary 2011-xx, Adequacy of Station Electric Distribution System Voltages. |
NL-11-0298, Joseph M. Farley, Units 1 and 2, Edwin I. Hatch, Units 1 and 2, and Vogtle, Units 1 and 2, Comments on Draft NRC Regulatory Issue Summary 2011-xx, Adequacy of Station Electric Distribution System Voltages. | 17 February 2011 | Joseph M. Farley, Units 1 and 2, Edwin I. Hatch, Units 1 and 2, and Vogtle, Units 1 and 2, Comments on Draft NRC Regulatory Issue Summary 2011-xx, Adequacy of Station Electric Distribution System Voltages. |
ML102520083 | 19 January 2011 | Issuance of Amendments Regarding Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program |
ML102140387 | 30 July 2010 | Nuclear Regulatory Commission Biweekly Notice - Applications and Amendments to Facility Operating Licenses Involving No Significant Hazards Considerations - Publication Date of August 10, 2010 |
ML091030655 | 13 April 2009 | Transcript of 561st ACRS Meeting on April 2, 2009 and Related Documents, Pages 1-479 |
RIS 2003-08, Enclosure 1 - NRC Regulatory Issue Summary 2003-08: Protection of Safeguards Information from Unauthorized Disclosure | 30 April 2003 7 November 2005 3 April 2008 | Enclosure 1 - NRC Regulatory Issue Summary 2003-08: Protection of Safeguards Information from Unauthorized Disclosure Summary of Safeguards Information Requirements, Attachment 1 to NRC Regulatory Issue Summary 2003-08: Protection of Safeguards Information from Unauthorized Disclosure |
RIS 2003-08, Protection of Safeguards Information from Unauthorized Disclosure | 30 April 2003 7 November 2005 3 April 2008 | Protection of Safeguards Information from Unauthorized Disclosure 2005/04/30-NRC Regulatory Issue Summary 2003-08 Protection of Safeguards Information from Unauthorized Disclosure Enclosure 1 - NRC Regulatory Issue Summary 2003-08: Protection of Safeguards Information from Unauthorized Disclosure Summary of Safeguards Information Requirements, Attachment 1 to NRC Regulatory Issue Summary 2003-08: Protection of Safeguards Information from Unauthorized Disclosure |
ML072610107 | 17 September 2007 | Rev. 0 to Audit and Review Plan for Plant Aging Management Programs, Reviews and Time-Limited Aging Analyses, Vogtle Electric Generating Plant, Units 1 and 2. |
NL-07-1232, Comment (21) of L. M. Stinson on Behalf of Southern Nuclear Operating Company, Inc., on Proposed Rule Pr 50 Regarding Industry Codes and Standards; Amended Requirements | 22 June 2007 | Comment (21) of L. M. Stinson on Behalf of Southern Nuclear Operating Company, Inc., on Proposed Rule Pr 50 Regarding Industry Codes and Standards; Amended Requirements |
ML071630054 | 11 June 2007 | Comment (5) Submitted by George L. Fechter on Proposed Rules PR-50 Regarding Industry Codes and Standards; Amended Requirements |
ML031110449 | 13 October 1999 | Relaxation of Technical Specification Requirements for PORC Review of Fire Protection Program Changes |
RIS 1999-02, Relaxation of Technical Specification Requirements for PORC Review of Fire Protection Program Changes | 13 October 1999 | Relaxation of Technical Specification Requirements for PORC Review of Fire Protection Program Changes |
NRC Generic Letter 1983-11 | 24 June 1999 | NRC Generic Letter 1983-011, Supplement 1: Licensee Qualification for Performing Safety Analysis |
ML20202H985 | 29 January 1999 | Safety Evaluation Accepting Rev 8 to First 10-year Interval Inservice Insp Program & Associated Requests for Relief for Vogtle Electric Generating Plant,Unit 1 |
NRC Generic Letter 1998-01 | 14 January 1999 | NRC Generic Letter 1998-001, Supplement 1: Year 2000 Readiness of Computer Systems at Nuclear Power Plants |
ML20196E522 | 1 December 1998 | Rev 8 to ISI-P-014, ISI Program for VEGP-2 |
ML20155J417 | 6 November 1998 | Submits Response to NRC GL 98-04, Potential for Degradation of ECCS & Containment Spray Sys After LOCA Because of Const & Protective Coating Deficiencies & Foreign Matl in Containment |