 Issue dateTitleTopic
ML17300B38130 September 1999Monthly Operating Repts for Sept 1999 for Pvngs,Units 1,2 & 3.With 991007 Ltr
ML17300B32731 August 1999Monthly Operating Rept for Aug 1999 for Pvngs,Units 1,2 & 3
ML17313B07527 August 1999LER 99-002-00:on 990730,test Mode Trip Bypass for EDG Output Breakers Not Surveilled.Cause Under Investigation.Operations Personnel Conservatively Invoked SR 3.0.3 for SR 3.8.1.13. with 990827 LtrMissed surveillance
ML17313B06131 July 1999Monthly Operating Repts for July 1999 for Pvngs,Units 1,2 & 3.With 990810 Ltr
ML17313B01916 July 1999LER 99-005-00:on 990618,RT on Low DNBR Was Noted.Caused by Hardware Induced Calculation Error.Cr Operator Was Taken to Place Reactor in Stable Condition IAW Appropriate Operating ProcedureAnticipated operational occurrence
ML17300B31530 June 1999Monthly Operating Repts for June 1999 for Pvngs,Units 1,2 & 3.With 990714 Ltr
ML17313A99221 June 1999Special Rept:On 990525,RMS mini-computer Was Removed from Service to Implement Yr 2000 Mod & Was OOS Longer than 72 H Allowed.Caused by Planned Y2K Mods.Preplanned Alternate Sampling Program Was InitiatedOffsite Dose Calculation Manual
ML17313A99118 June 1999Special Rept:On 990510,loose-part Detection Sys Channel 2 Was Declared Inoperable.Caused by Malfunction of Mineral Cable Connector to Accelerometer.Licensee Will Implement Modifications Which Will Enhance loose-part Detection Sys
ML17313A97331 May 1999Monthly Operating Repts for May 1999 for Pvngs,Units 1,2 & 3.With 990608 Ltr
ML17313A9287 May 1999LER 99-004-00:on 990408,PSV Lift Pressures Were Outside of TS Limits.Caused by Lift Pressure Setpoint Drift.Psvs Have Been Tested,Disassembled,Inspected,Reassembled & Certified at Wyle Labs
ML17313A92030 April 1999Monthly Operating Repts for Apr 1999 for Pvngs,Units 1,2 & 3.With 990512 Ltr
ML17313A89514 April 1999LER 99-003-00:on 990317,required Surveillance Requirement Not Completed Due to Deficient Procedure,Was Determined. Caused by Cognitive Personnel Error.St Procedures Revised to Require Chiller to Be Operating & Oil Temperature CheckedUltimate heat sink
Missed surveillance
ML17313A89213 April 1999LER 98-003-01:on 980902,discovered That MSSV as-found Lift Pressures Were Outside TS Limits.Caused by Bonding of Valve Disc to Nozzle Seat.Affected Valves Were Adjusted,Retested & Returned to Svc
ML17313A8899 April 1999LER 99-001-00:on 990310,RT on High Pressurizer Pressure Was Noted.Caused by Loss of Heat Removal.Cr Supervisor Was Removed from Shift Duties for Diagnostics Skills Training. with 990409 LtrShutdown Margin
ML17300B30731 March 1999Seismic Portion of Submittal-Only Screening Review of Palo Verde Nuclear Generating Station Units Ipeee.Safe Shutdown
Safe Shutdown Earthquake
Design basis earthquake
Earthquake
ML17313A88031 March 1999Monthly Operating Repts for Mar 1999 for Pvngs,Units 1,2 & 3.With 990412 Ltr
ML20207M92312 March 1999Amended Part 21 Rept Re Cooper-Bessemer Ksv EDG Power Piston Failure.Total of 198 or More Pistons Have Been Measured at Seven Different Sites.All Potentially Defective Pistons Have Been Removed from Svc Based on Encl Results
ML20207H74710 March 19991999 Emergency Preparedness Exercise 99-E-AEV-03003High Radiation Area
Ultimate heat sink
Grab sample
Safe Shutdown Earthquake
Operating Basis Earthquake
Earthquake
Deep Dose Equivalent
Chernobyl
Downpower
Siren
ML17313A8361 March 1999LER 99-001-00:on 990103,TS Violation for Power Dependent Insertion Limit Alarm Being Inoperable.Caused by Personnel Error.Revised Procedure to Clarify How Computer Point Is to Be Returned to Scan Mode.With 990302 LtrShutdown Margin
ML17313A85028 February 1999Monthly Operating Repts for Feb 1999 for Palo Verde Nuclear Generating Station.With 990311 Ltr
ML17313A7795 February 1999Safety Evaluation Accepting Licensee Rev to Emergency Plan That Would Result in Two Less Radiation Protection Positions Immediatelu Available During Emergencies
ML17313A80631 January 1999Monthly Operating Repts for Jan 1999 for Pvngs,Units 1,2 & 3.With 990218 Ltr
ML17313A77015 January 1999LER 96-008-00:on 960507,inadequate Procedure Results in Nuclear Power Channels Not Calibrated During Power Ascension Tests Occurred.Caused by Deficient Procedure.Procedure Revised
ML17313A73831 December 1998Monthly Operating Repts for Dec 1998 for Palo Verde Nuclear Generating Station,Units 1,2 & 3.With 990113 Ltr
ML20206H21031 December 1998SCE 1998 Annual Rept
ML17313A70330 November 1998Monthly Operating Repts for Nov 1998 for Pvngs,Unit 1,2 & 3. with 981209 Ltr
ML17313A6704 November 1998Rev 2 to PVNGS Unit 2 Colr.Shutdown Margin
ML17313A67431 October 1998Monthly Operating Repts for Oct 1998 for Pvngs,Units 1,2 & 3.With 981109 Ltr
ML17313A66124 October 1998LER 98-008-00:on 980729,EQ of Electrical Connectors Were Not Adequately Demonstrated.Caused Because Test Was Conducted with Only Single Lv Connector & Without Fully Ranged Inputs. Revised EQ Requirements
ML17313A65630 September 1998Monthly Operating Rept for Sept 1998 for PVNGS Units 1,2 & 3.With 981007 Ltr
ML17313A59614 September 1998LER 98-002-00:on 980814,B Train H Recombiner Was Noted Inoperable Due to cross-wired Power Receptacle.Cause of Event Is Under investigation.Cross-wired Power Supply Receptacle for B Train H Recombiner Was re-wired
ML17313A5768 September 1998LER 98-003-01:on 980113,discovered That One Channel of RWT Level Sys Had Failed High.Caused by Water Intrusion Into Electrical Termination Pull Box.Weep Holes Were Drilled Into Bottoms of Pull Boxes Nearest Level TransmittersTime of Discovery
ML17313A55928 August 1998LER 98-001-00:on 980730,entered TS 3.0.3 Due to Safety Injection Flow Instruments Being Removed from Svc.Caused by Personnel Error.Transmitters Were Unisolated & Returned to svc.W/980828 Ltr
ML20151S09421 August 1998Rev 6 to COLR for PVNGS Unit 3Shutdown Margin
ML20151S08621 August 1998Rev 4 to COLR for PVNGS Unit 1Shutdown Margin
ML20151S09021 August 1998Rev 1 to COLR for PVNGS Unit 2Shutdown Margin
ML18066A27713 August 1998Part 21 Rept Re Deficiency in CE Current Screening Methodology for Determining Limiting Fuel Assembly for Detailed PWR thermal-hydraulic Sa.Evaluations Were Performed for Affected Plants to Determine Effect of Deficiency
ML17313A54013 August 1998Special Rept:On 980715,declared PASS Inoperable.Caused by Failure of Offgas Flush/Purge Control Handswitch HS0101. Handswitch Replaced & Post Maintenance Retesting Was Initiated
ML17313A53031 July 1998Monthly Operating Repts for July 1998 for Pvgns,Units 1,2 & 3.W/980812 Ltr
ML17313A52030 July 1998LER 98-004-00:on 980630,personnel Discovered That Pressure Safety Valve Had Not Received Periodic Set Pressure Test for ASME Class 1 Pressure Safety Valve.Caused by Personnel Error.Pressure Safety Valve reviewed.W/980730 LtrTime of Discovery
Missed surveillance
ML17313A5797 July 1998to PVNGS SG Tube ISI Results for Seventh Refueling Outage Mar & Apr 1998.
ML17313A50030 June 1998Monthly Operating Repts for June 1998 for Palo Verde Nuclear Generating Station,Units 1,2 & 3.W/980710 Ltr
ML17313A46719 June 1998LER 98-007-00:on 980520,CR Personnel Observed Flow & Pressure Perturbations on Chemical & Vol Control Sys Letdown Sys.Caused by Cyclic Fatigue Due to Dynamic Pressure Transients.Unit Letdown Piping Replaced
ML17313A45219 June 1998Rev 5 to COLR for Pvngs,Unit 3.Shutdown Margin
ML17313A45019 June 1998Rev 4 to COLR for Pvngs,Unit 3.Shutdown Margin
ML17313A4135 June 1998LER 98-006-00:on 980507,determined That Plant Was Outside Design Basis Due to SI Discharge Check Valve Reverse Flow. Check Valve Was Disassembled,Examined & Reassembled, Whereupon Valve Met Acceptance CriteriaUnanalyzed Condition
ML17313A42131 May 1998Monthly Operating Repts for May 1998 for Pvngs,Units 1,2 & 3.W/980609 Ltr
ML17313A39526 May 1998LER 98-005-00:on 980428,noted That Required Response Time Testing Had Not Been Performed.Caused by Personnel Error. Coached I&C Personnel Responsible for Reviewing Work Authorization Documentation
ML17313A36930 April 1998Monthly Operating Repts for Apr 1998 for PVNGS.W/980412 Ltr
ML17313A3251 April 1998LER 98-004-00:on 980304,safety Valves as-found Pressures Out of Tolerance.Cause of Event Is Under Investigation.Three Mssv'S & Psv Will Be Replaced W/Refurbished & Recertified Valves During Refueling Outage U1R7Safe Shutdown
Time of Discovery