ML23319A387 | 20 December 2023 | Issuance of Amendment Nos. 185 and 185 Regarding Implementation of Full Spectrum Loss-of-Coolant Accident (Fsloca) Methodology | Loop seal Anticipated operational occurrence Hydrostatic Coatings Pressure and Temperature Limits Report |
ML23313A073 | 6 December 2023 | Issuance of Amendment Nos. 184 and 184 Regarding Revision to Technical Specifications to Implement WCAP-17661-P-A, Rev. 1, Improved Roac and CAOC Fq Surveillance Technical Specifications | Anticipated operational occurrence Hydrostatic Pressure and Temperature Limits Report Surveillance Frequency Control Program |
ML23237B428 | 28 September 2023 | Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 2, Draft Conforming License Amendments | Safe Shutdown Probabilistic Risk Assessment Cyber Security Large early release frequency Safeguards Contingency Plan License Renewal Fire Protection Program |
ML23237B430 | 28 September 2023 | Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 4, Safety Evaluation for Transfer of Licenses and Draft Conforming License Amendments (EPID L-2023-LLM-0000) (Public) | Decommissioning Funding Plan |
ML23198A321 | 27 July 2023 | Authorization and Safety Evaluation for Proposed Alternative RV-1 | Safe Shutdown Incorporated by reference |
ML22192A007 | 22 August 2022 | Issuance of Amendment Nos. 183 and 183 Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-505, Revision 2 | Safe Shutdown High winds Internal Flooding Probabilistic Risk Assessment FLEX Fukushima Dai-Ichi Surveillance Frequency Control Program Large early release frequency Flooding Focused Evaluation Maintenance Rule Program Offsite Circuit |
ML22194A059 | 14 July 2022 | Correction to Amendment Nos. 182 and 182 to Revise Technical Specifications to Adopt TSTF-577, Revision 1, Revised Frequencies for Steam Generator Tube Inspections | |
ML22129A072 | 16 May 2022 | Review of Quality Assurance Program Changes | Offsite Dose Calculation Manual Process Control Program Grace period |
ML22077A841 | 24 March 2022 | Proposed Alternative SNB-3 for the Snubber Inservice Program Third Interval Extension | Incorporated by reference |
ML21321A349 | 24 February 2022 | Issuance of Amendment Nos. 182 and 182 to Revise Technical Specifications to Adopt TSTF-577, Rev. 1, Revised Frequencies for Steam Generator Tube Inspections | Post Accident Monitoring Nondestructive Examination Pressure and Temperature Limits Report Surveillance Frequency Control Program |
ML21322A103 | 7 December 2021 | Proposed Alternative for the Continued Use of a Risk-Informed Process for the Selection of Class 1 and 2 Piping Welds for Inservice Inspection | Internal Flooding Probabilistic Risk Assessment Large early release frequency Exemption Request DM weld |
ML21132A089 | 9 June 2021 | Issuance of Amendment Nos. 181 and 181 Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-567, Rev. 1, Add Containment Sump TS to Address GSI - 191 Issues | Surveillance Frequency Control Program |
ML21061A217 | 19 May 2021 | Issuance of Amendment Nos. 180 and 180 to Authorize Revision of Certain Emergency Action Levels of the Emergency Plan | Safe Shutdown Ultimate heat sink Operating Basis Earthquake Earthquake |
ML21103A039 | 23 April 2021 | Issuance of Amendment Nos. 179 and 179 the Adoption of Technical Specifications Task Force Traveler, TSTF-569, Revision 2, Revise Response Time Testing Definition (EPID L-2020-0147) | Shutdown Margin Anticipated operational occurrence |
ML21015A212 | 12 February 2021 | Issuance of Amendment Nos. 178 and 178 Regarding One-Time Revision to Technical Specifications 3.7.8 Station Service Water System (Ssws) and 3.8.1 AC Sources - Operating | Safe Shutdown High winds Shutdown Margin Ultimate heat sink Safe Shutdown Earthquake Internal Flooding Probabilistic Risk Assessment Incorporated by reference FLEX Offsite Circuit Fire Protection Program Fire Watch |
ML21022A162 | 8 February 2021 | Proposed Alternative to the Requirements of the ASME OM Code to Extend the Inservice Testing Program Interval for Certain Check and Relief Valves (EPID L-2020-LLR-0096 (COVID-19)) | Incorporated by reference Pandemic COVID-19 |
ML20346A019 | 1 February 2021 | Issuance of Amendment Nos. 177 and 177 Regarding Revision to Technical Specifications 3.8.1, AC Sources - Operating | Stroke time Condition Adverse to Quality Surveillance Frequency Control Program Offsite Circuit |
ML21021A100 | 1 February 2021 | Proposed Alternative to the Requirements of the ASME OM Code to Extend the Inservice Testing Program Interval for Certain Snubbers (EPID L-2020-LLR-0095 (Covid 19)) | Incorporated by reference Locked High Radiation Area Pandemic Coronavirus COVID-19 |
ML21013A128 | 28 January 2021 | Approval of Proposed Alternative to the Requirements of the ASME Code to Extend the Third Inservice Inspection Interval (EPID L-2020-LLR-0092 (COVID-19)) | Boric Acid Incorporated by reference Pandemic Coronavirus COVID-19 |
ML21021A002 | 28 January 2021 | Approval of Proposed Alternatives 1A4-1 and 1A4-2 from Certain Requirements of 10 CFR 50.55a for Inservice Inspection of Nuclear Power Plants | Boric Acid Nondestructive Examination Pandemic Coronavirus COVID-19 |
ML20282A709 | 17 November 2020 | Proposed Alternative to the Requirements of the ASME Omcode to Extend the Inservice Testing Program Interval for Certain Snubbers (EPID L-2020-LLR-0060 (COVID-19)) | Incorporated by reference Pandemic Coronavirus COVID-19 |
ML20281A472 | 4 November 2020 | Use of Later Code Edition to the Requirements of the ASME OM Code | Incorporated by reference |
ML20255A100 | 7 October 2020 | Proposed Alternative to the Requirements of the ASME OM Code to Extend the Inservice Test Program Interval for Certain Check and Relief Valves (EPID L-2020-LLR-0061 and EPID L-2020-LLR-0062 (COVID-19)) | Incorporated by reference Pandemic Coronavirus COVID-19 Grace period |
ML20223A349 | 31 August 2020 | Issuance of Amendment Nos. 175 and 175 Regarding One-Time Revision to Technical Specification 3.7.19, Safety Chilled Water | Safe Shutdown High winds Ultimate heat sink Probabilistic Risk Assessment FLEX COVID-19 Fire Protection Program Fire Watch |
ML20226A013 | 17 August 2020 | Use of Later Code Edition to the Requirements of the ASME Code | Incorporated by reference |
ML20167A318 | 6 July 2020 | Issuance of Amendment Nos. 174 and 174 Regarding Revision to Technical Specifications to Adopt TSTF-563, Revision 0 | Probabilistic Risk Assessment Surveillance Frequency Control Program Large early release frequency |
ML20108E878 | 17 April 2020 | Issuance of Amendment Nos. 173 and 173 Revision to TS 5.5.9, Unit 1 Model D76 and Unit 2 Model D5 Steam Generator (SG) Program (Exigent Circumstances) | Grab sample Anticipated operational occurrence Nondestructive Examination Surveillance Frequency Control Program Foreign Material Exclusion Pandemic COVID-19 |
ML20054A276 | 27 February 2020 | Approval of Change to the Quality Assurance Program as Described in the Comanche Peak Nuclear Power Plant Final Safety Analysis Report | |
ML19267A018 | 4 November 2019 | Issuance of Amendment Nos. 172 and 172 to Revise Augmentation Times and Emergency Response Organization Staffing for the Emergency Plan | Minimum staff Fire Protection Program |
ML18304A487 | 30 November 2018 | Issuance of Amendments 171 and 171 Regarding Revision to Technical Specifications for Engineered Safety Feature Actuation System Instrumentation | Anticipated operational occurrence |
ML18267A384 | 25 October 2018 | Issuance of Amendment Nos. 170 and 170 Revision to Technical Specification 3.8.4, DC Sources - Operating, Condition B (Exigent Circumstances) | Safe Shutdown Anticipated operational occurrence Enforcement Discretion Probabilistic Risk Assessment Condition Adverse to Quality FLEX Surveillance Frequency Control Program Spent Fuel Pool Instrumentation Battery sizing Fire Watch |
ML18221A632 | 15 August 2018 | Eicb Safety Evaluation - Comanche Peak Nuclear Power Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.3.2 Engineered Safety Feature Actuation System Instrumentation Docket/Epid 000976/05000446/L-2018-LLA-0 | Anticipated operational occurrence |
ML17129A024 | 29 June 2017 | Comanche Peak Nuclear Power Plant, Units 1 and 2 - Issuance of Amendment Nos. 169 and 169 Re: Administrative Change to Licensee Name (CAC Nos. MF8933 and MF8934) | |
ML17074A494 | 13 April 2017 | Issuance of Amendment Nos. 168 and 168 Adoption of TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing | Incorporated by reference Missed surveillance Surveillance Frequency Control Program |
ML17095A251 | 7 April 2017 | Request for Alternative 2B3-1 Re Examination of Reactor Vessel Closure Head Penetration Nozzles | |
ML16334A173 | 14 December 2016 | Comanche Peak Nuclear Power Plant, Units 1 And 2; Safety Evaluation Regarding Implementation Of Mitigating Strategies And Reliable Spent Fuel Pool Instrumentation Related To Orders EA-12-049 And EA-12-051 | Spent Fuel Pool Instrumentation |
ML16179A405 | 11 July 2016 | Relief Request Nos. B-9, B-3, B-10, and B-11 for Piping Welds, Second 10-year Inservice Inspection Interval | Boric Acid VT-2 Incorporated by reference Pressure Boundary Leakage Through-Wall Leak Dissimilar Metal Weld Scaffolding |
ML16137A056 | 14 June 2016 | Issuance of Amendment Nos. 166 and 166, Request to Revise Emergency Action Levels Based on Nuclear Energy Institute (NEI) 99-01, Revision 6 | High winds Ultimate heat sink Safe Shutdown Earthquake Operating Basis Earthquake Spent Fuel Pool Instrumentation Earthquake Fuel cladding |
ML16096A266 | 6 May 2016 | Redacted Letter, Order, Safety Evaluation, and Draft Conforming Amendments, Application for Order Approving Direct and Indirect Transfer of Licenses and Conforming License Amendments | Safe Shutdown Cyber Security Decommissioning Funding Plan Fire Protection Program |
ML16096A264 | 6 May 2016 | Draft Conforming Amendments, Application for Order Approving Direct and Indirect Transfer of Licenses and Conforming License Amendments | Safe Shutdown Cyber Security Fire Protection Program |
ML16074A001 | 14 March 2016 | Relief Request 1B3-3, Alternative for Reactor Pressure Vessel Cold Leg Weld Inspection Frequency from Not to Exceed 7 Years to 9 Years for the Third 10-Year Inservice Inspection Interval | Through-Wall Leak DM weld |
ML16063A001 | 11 March 2016 | Relief Request No. B-15, C-2, and C-4 for Welds in the RPV and Containment Spray and Residual Heat Removal Heat Exchanger Shells, Second 10-year Inservice Inspection Interval | VT-2 Incorporated by reference Liquid penetrant |
ML16011A073 | 19 January 2016 | Relief Request T-1; Alternative to the ASME OM Code Frequency Specifications for Inservice Testing for the Third 10-Year IST Interval | Power-Operated Valves Grace period |
ML15309A073 | 30 December 2015 | Issuance of Amendment Nos. 165 and 165, Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, to Increase ILRT Test Interval from 10 to 15 Years and Type C Tests from 60 to 75 Mos | High winds Safe Shutdown Earthquake Internal Flooding Probabilistic Risk Assessment Coatings Moisture barrier Grace period |
ML15259A004 | 30 October 2015 | Relief Request 1B3-4, Alternative for Reactor Pressure Vessel Head Penetration Weld Inspection Frequency (from 10 to 15 Years), Third 10-Year Inservice Inspection Interval | Boric Acid VT-2 |
ML15257A242 | 18 September 2015 | Relief Request 2A3-1, from ASME Code Section XI Requirements, Risk-Informed Process for Selection of Class 1 and Class 2 Piping Weld Examinations, Third 10-Year Inservice Inspection Interval | Internal Flooding Probabilistic Risk Assessment Large early release frequency Exemption Request DM weld |
ML15257A240 | 15 September 2015 | Relief Request 2C3-1, from ASME Code, Section XI Requirements Reactor Pressure Vessel Leak-Off Flange for the Third 10-Year Inservice Inspection Interval | Boric Acid VT-2 Foreign Material Exclusion |
ML15090A104 | 3 April 2015 | Relief Requests B-7, B-12, and B-13 - Steam Generator Head-to-Tube Sheet Welds for the Second 10-Year Inservice Inspection Interval | VT-2 Incorporated by reference |
ML15008A133 | 24 February 2015 | Issuance of Amendment Nos. 164 and 164, Revise Technical Specification 3.8.1 for a 14-Day Completion Time for Offsite Circuits | Safe Shutdown Enforcement Discretion Offsite Circuit Hourly Fire Watch |
ML14183A342 | 8 September 2014 | Issuance of Amendment Nos. 163 and 163 to Revise License Condition Related to Approval of Revised Cyber Security Plan Implementation Schedule | Safe Shutdown Cyber Security Fire Protection Program |