Semantic search

Jump to navigation Jump to search
 Issue dateTitleTopic
ML20217G97914 October 1999Forwards SE Accepting Relief Requests to Rev 5 of First 10-year Interval Inservice Insp Program for Plant,Units 1 & 2
ML20217A93129 September 1999Informs That NRC 6-month Review of Braidwood Identified That Performance in Maint Area Warranted Increased NRC Attention. Addl Insps Beyond Core Insp Program Will Be Conducted Over Next 6 Months to Better Understand Causes of Problem
ML20216H43023 September 1999Informs That Arrangements Made for Administration of Licensing re-take Exams at Braidwood Generating Station for Week of 991108
ML20216F74417 September 1999Forwards Insp Repts 50-456/99-13 & 50-457/99-13 on 990706-0824.Three Violations Noted & Being Treated as Ncvs. Insp Focused on C/As & Activities Addressing Technical Concerns Identified During Design Insp Completed on 980424
ML20212A69910 September 1999Forwards SE Accepting Licensee Second 10-year Interval ISI Program Request for Relief 12R-07 for Plant,Units 1 & 2
ML20211Q6616 September 1999Informs That NRC Tentatively Scheduled Initial Licensing Exam for Braidwood Operator License Applicants During Wk of 010115 & 22.Validation of Exam Will Occur at Station During Wk of 001218
ML20211P1903 September 1999Forwards Insp Repts 50-456/99-12 & 50-457/99-12 on 990707-0816.No Violations Noted.Insp Generally Characterized by safety-conscious Operations,Sound Engineering & Maint Practices & Careful Radiological Work Controls
ML20211K1082 September 1999Responds to Request for Addl Info to GL 92-01,Rev 1,Suppl 1, Reactor Vessel Structural Integrity, for Braidwood,Units 1 & 2 & Byron,Unit 2
ML20211P1762 September 1999Discusses Licensee Aug 1998 Rev 3K to Portions of Braidwood Nuclear Power Station Generating Stations Emergency Plan Site Annex Submitted Under Provisions of 10CFR50.54(q). NRC Approval Not Required
ML20211B86920 August 1999Forwards Insp Repts 50-254/99-10,50-265/99-10,50-454/99-09, 50-455/99-09,50-456/99-10 & 50-457/99-10 on 990628-0721. Action Plans Developed to Address Configuration Control Weaknesses Not Totally Effective as Listed
ML20210U8034 August 1999Forwards SER Granting Licensee Relief Requests VR-1,VR-3 & Portion of VR-2 Pursuant to 10CFR50.55a(a)(3)(ii).Relief Request VR-4 Does Not Require Explicit NRC Approval for Second 10-year Inservice Testing ProgramIncorporated by reference
ML20210K97630 July 1999Forwards SE Accepting Licensee 60-day Response to GL 96-05, Periodic Verification of Design Basis Capability of Safety-Related Movs, for Plant
ML20210G62929 July 1999Forwards Insp Repts 50-456/99-11 & 50-457/99-11 on 990525-0706.Two Violations Noted & Being Treated as NCV, Consistent with App C of Enforcement PolicyEnforcement Discretion
ML20210C39620 July 1999Forwards Insp Repts 50-456/99-09 & 50-457/99-09 on 990517-0623.No Violations Noted.Weakness Identified on 990523,when Station Supervisors Identified Individual Sleeping in Cable Tray in RCA
ML20210B70716 July 1999Responds to Requesting Review & Approval of Three Proposed Changes to Ceco QA TR,CE-1A Per 10CFR50.54(a)(3) & 10CFR50.4(b)(7)
IR 05000456/199930115 July 1999Forwards Operator Licensing Exam Repts 50-456/99-301OL & 50-457/99-301OL for Test Administered from 990607-11 to Applicants for Operating Licenses.Three Out of Four Applicants Passed Exams
ML20209H51414 July 1999Discusses 990701 Telcon Re Arrangements for NRC to Inspect Licensed Operator Requalification Program at Braidwood Nuclear Generating Station for Week of 990927,which Coincides with Licensee Regularly Scheduled Exam Cycle
ML20196H06328 June 1999Provides Individual Exam Results for Licensee Applicants Who Took June 1999 Initial License Exam.Without Encls
ML20212H82424 June 1999Informs That Effective 990531 NRC Project Mgt Responsibility for Byron & Braidwood Stations Was Transferred to Gf Dick
ML20196D45918 June 1999Forwards Insp Repts 50-456/99-07 & 50-457/99-07 on 990414- 0524.No Violations Noted.Conduct of Activities Generally Characterized by safety-conscious Operations,Sound Engineering & Maintenance Practices
ML20196A66717 June 1999Refers to 990609 Meeting with Util in Braidwood,Il Re Licensee Initiatives in Risk Area & to Establish Dialog Between SRAs & Licensee PRA StaffProbabilistic Risk Assessment
ML20195J37414 June 1999Forwards Insp Rept 50-457/99-08 on 990415-0518.No Violations Noted.Sg Insp Program Found to Be Thorough & Conservative
ML20195F3239 June 1999Informs That in ,Arrangements Finalized for Exam to Be Administered at Plant During Wk of 990607.All Parts of Plant Initial Licensed Operator Exam Approved for Administration
ML20207B63625 May 1999Forwards SE Accepting Revised SG Tube Rupture (SGTR) Analysis for Bryon & Braidwood Stations.Revised Analysis Was Submitted to Support SG Replacement at Unit 1 of Each Station
ML20207A58920 May 1999Forwards Insp Repts 50-456/99-05 & 50-457/99-05 on 990405-23.Two non-cited Violations IdentifiedTemporary Modification
ML20206U46418 May 1999Responds to Util 990517 Request That NRC Exercise Discretion Not to Enforce Compliance with Actions Required in TS 3.0.3. Documents 990516 Telcon with Licensee Re NOEDEnforcement Discretion
ML20206N47913 May 1999Forwards RAI Re 980529 Amend Request for Byron & Braidwood to Credit Automatic PORV Operation for Mitigation of Inadvertent SI at Power Accident.Response Requested 60 Days After Receipt Date
ML20206Q53211 May 1999Forwards Insp Repts 50-456/99-06 & 50-457/99-06 on 990302-0413.Configuration Control Error Resulted in Isolation of Unit 1 Emergency Boration Flow Path Through Designated Boric Acid Pump for Period of 3 H OccurredBoric Acid
ML20206H8165 May 1999Confirms Discussion Re Meeting to Be Conducted on 990527 at Braidwood Station Training Building.Meeting Will Discuss Braidwood Station Performance as Described in Most Recent Plant Performance Review
ML20206E7023 May 1999Advises That Info Contained in Document Entitled, Licensing Rept for Sf Rack Installation at Byron & Braidwood Stations, HI-982083,will Be Withheld from Public Disclosure Per 10CFR2.790
ML20205G96326 March 1999Advises of Planned Insp Effort Resulting from Braidwood Plant Performance Review for Period 870830-990131.Historical Listing of Plant Issues & Details of NRC Insp Plan for Next 6 Months EnclSystematic Assessment of Licensee Performance
Fire Protection Program
ML20204J42423 March 1999Forwards Insp Repts 50-456/99-04 & 50-457/99-04 on 990222-24 & 0303 Onsite & 0309 & 11 Region 3 Ofc.No Violations Noted. Implementation of Physical Security Plan Was Examined
ML20204J90023 March 1999Forwards Insp Repts 50-456/99-02 & 50-457/99-02 on 990120- 0301.No Violations Noted
ML20204G20322 March 1999Forwards Year 2000 Readiness Audit Rept Which Documents Results of NRR Audit Conducted at Facility from 990124-28
ML20204C72016 March 1999Ack Receipt of Expressing Concern Over Sale of Certain Properties by Commonwealth Edison CoUltimate heat sink
ML20204E33416 March 1999Expresses Appreciation for Re Concerns Over Sale of Certain Properties by Licensee.No Regulatory Basis for NRC to Require Util to Rely on strip-mine Ponds as Suppl Source of Cooling WaterUltimate heat sink
ML20204E28016 March 1999Ack Receipt of Rev 3M to Portions of Braidwood Nuclear Power Generating Station Emergency Plan Site Annex.Informs That NRC Approval Not Required Based on Ceco Determinations That Changes in Rev 3M Do Not Decrease Effectiveness of Plan
ML20207J97411 March 1999Discusses Rev 3,to Portions of Braidwood Power Station EP Site Annex.Based on Licensee Determinations That Changes Do Not Decrease Effectiveness of EP & Plan Continues to Meet Standards of 10CFR50.47(b),NRC Approval Not Required
ML20203E95211 February 1999Forwards Insp Rept 50-456/98-16 on 980916-990121.No Violations Were Identified.Insp Was Exam of Activities Re Engineering & Maint Activities for Replacement of Steam Generators for Compliance with Commission Regulations
ML20203F25410 February 1999Informs That Beginning 990216,DE Hills Will Be Chief of Operations Branch Which Includes Operator Licensing Function
ML20203C9768 February 1999Ack Receipt of ,Which Transmitted Changes Identified as Rev 44 to Security Plan.No NRC Approval Required
ML20203A4605 February 1999Ack Receipt of 981109 Evaluation of Indication in Base Metal of Braidwood Station,Unit 1,main Steam Piping Sys Elbow
ML20203A3643 February 1999Forwards Copy of FEMA Evaluation Rept for 980520 Emergency Preparedness Exercise at Braidwood.One Deficiency & Three Areas Requiring Corrective Action Identified.Deficiency Corrected During Remedial Exercise Held on 980806
ML20199E65615 January 1999Discusses Unresolved Security Item Re Adequacy of Compensatory Measures Implemented for Section of Vehicle Barrier Sys.Issue Briefly Described as Listed
ML20199E1358 January 1999Forwards Revised Dates for Engineering & Technical Support Insp,Emergency Planning Insp,Security Insp & Operational Assessment Insp for Braidwood
IR 05000456/19980145 January 1999Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts on 50-456/98-14 & 50-457/98-14 Issued on 981117
ML20198R07430 December 1998Forwards Insp Repts 50-456/98-20 & 50-457/98-20 on 981020-1207.No Violations Noted.Insp Generally Characterized by safety-conscious Operations,Sound Engineering & Maint Practices & Careful Radiological Work Controls
ML20197J68310 December 1998Forwards Insp Repts 50-456/98-21 & 50-457/98-21 on 981110- 24.No Violations Noted.Insp Reviewed Corrective Actions for Previously Identified Issues
ML20197H4264 December 1998Forwards Insp Rept 50-456/98-18 on 981015-23 & 1109-10.No Violations Noted.Some Weaknesses Identified in Operator Performance & Training
ML20197K1312 December 1998Forwards Planned Insp Effort for Next 6 Months at Plant.Info Provided to Minimize Resource Impact on Staff & Allow for Scheduling Conflicts & Personnel Availability to Be Resolved in Advance of Inspector Arrival OnsiteShutdown Margin
Fire Barrier
Probabilistic Risk Assessment
Nondestructive Examination
Foreign Material Exclusion
Operability Determination
Continuous fire watch
Fire Watch
Inattentive