ML20062E007 | 14 November 1990 | Forwards List of Unimplemented GSIs at Facility,Per Generic Ltr 90-04 | |
ML20062D665 | 8 November 1990 | Ack Receipt of Forwarding Util Evaluation of NRC Inspector General Rept 90N-02 Re Offsite Emergency Planning | |
ML20058G976 | 7 November 1990 | Forwards Safety Insp Rept 50-293/90-20 on 900816-1008 & Notice of Violation | |
ML20058C550 | 26 October 1990 | Requests Written Policies & Procedures Needed for NRC Preparation for Planned fitness-for-duty Insp | |
ML20062B431 | 17 October 1990 | Advises That 901012 Response to Generic Ltr 90-03 Re Vendor Interface for safety-related Components,Acceptable | |
ML20062B716 | 12 October 1990 | Extends Invitation to Attend 910220-21 Util Symposium/ Workshop in King of Prussia,Pa Re Engineering Role in Plant Support.Interest to Participate,Intent to Attend & Approx Number of Representatives to Attend Requested by 901115 | |
ML20062B628 | 12 October 1990 | Forwards Insp Rept 50-293/90-21 on 900905-07.Insp Conducted to Review Event of 900902-03 Which Involved Number of Component Malfunctions & Operational Complications Following Shutdown | |
ML20059N725 | 1 October 1990 | Requests That Matls Listed in Encl Be Furnished to Assist Maint Program Team Insp Scheduled for 901105-16 | Systematic Assessment of Licensee Performance |
ML20059K690 | 11 September 1990 | Forwards Transcript of 900906 Public Meeting in Plymouth,Ma W/State & Local Officials Re Emergency Planning.W/O Encl | |
ML20059H587 | 1 September 1990 | Advises That Reactor Operator & Senior Reactor Operator Exams Scheduled for 901203.Encl Listed Ref Matl Requested | Job Performance Measure |
ML20059J652 | 29 August 1990 | Forwards Safety Insp Rept 50-293/90-09 on 900806-10.No Violations Noted.Concludes That Engineering & Technical Support Organizations Continue to Provide Strong Station Support | |
ML20059A148 | 17 August 1990 | Forwards 900816 Summary of 900807 Meeting Re Inservice Testing Program | |
ML20058P047 | 9 August 1990 | Forwards Safety Insp Rept 50-293/90-18 on 900709-13.No Violations Noted | |
ML20058N040 | 6 August 1990 | Discusses Licensee Engineering Initiatives.Power Reactor Licenses in Region 1 Should Initiate Similar Program to Provide Sharing of Info & Experiences Involving Engineering Initiatives & Solution to Problems Common to All | |
ML20056A480 | 30 July 1990 | Forwards Safeguards Insp Rept 50-293/90-16 on 900625-29.No Violations Noted.One Unresolved Item Identified | |
ML20058L705 | 27 July 1990 | Forwards Safety Insp Rept 50-293/90-17 on 900625-29.No Violations Noted | |
ML20055F246 | 29 June 1990 | Forwards Safety Insp Rept 50-293/90-13 on 900501-0611.No Violations Noted.Repetitive Failures of Diesel Driven Fire Pump Noted,Requiring Increased Mgt Attention | |
ML20059M842 | 13 June 1990 | Forwards NRC Performance Indicators for First Quarter 1990. W/O Encl | |
ML20247R807 | 21 September 1989 | Forwards SALP Rept 50-293/88-99 for 880516-890630.Instances of Deviation from Approved Practices & Lack of Attention to Detail Which Led to Challenges to Plant Equipment & Personnel Noted | Systematic Assessment of Licensee Performance |
ML20247K666 | 7 September 1989 | Forwards Insp Rept 50-293/89-07 on 890525-0710 & Notice of Violation | |
ML20246K509 | 24 August 1989 | Accepts Summary of QA Program Description Changes for 1989, Forwarded by | |
ML20246L782 | 23 August 1989 | Forwards Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $25,000.Failures to Properly Plan, Supervise & Inspect Tagout of Circuit Breakers Directly Contributed to Event | |
ML20246D726 | 18 August 1989 | Submits Response to Re Plant Power Ascension Program.Util Proposal to Defer Phase 2 of Shutdown from Outside Control Room Test to Planned Fall 1989 mid-cycle Outage Accepted | |
IR 05000293/1989007 | 18 August 1989 | Approves Reactor Operation Up to 75% of Full Power Per Licensee Power Ascension Test Program.Nrc Findings Docketed in Insp Repts 50-293/89-07 & 50-293/89-08 & Status of Emergency Preparedness for Communities Encl | |
ML20246J481 | 18 August 1989 | Clarifies NRC Position Re Definition of Extremity for Purposes of Setting Occupational Exposure Limits.Due to Misunderstanding,No Enforcement Action Planned If Licensee Procedures Incorporated Misunderstanding | |
ML20246G186 | 18 August 1989 | Approves Reactor Operation Up to 75% of Full Power Per Licensee Power Ascension Test Program.Nrc Findings Docketed in Insp Repts 50-293/89-07 & 50-293/89-08 & Status of Emergency Preparedness for Communities Encl | |
ML20245F178 | 31 July 1989 | Forwards Insp Rept 50-293/89-06 on 890411-0524.No Violations Noted.Licensee Actions W/Respect to 890503 Turbine Trip/Reactor Scram Demonstrated Excellent Approach to Problem Investigation & Resolution | |
ML20247D018 | 18 July 1989 | Ack Receipt of Re Response to NRC Bulletin 89-003, Inadequate Latch Engagement in Hfa Type Relays Mfg by Ge. Necessary Actions Performed to Address Issues in Bulletin | |
ML20246N392 | 14 July 1989 | Forwards Safety Insp Rept 50-293/89-09 on 890619-22.No Violations Noted | |
ML20246D496 | 6 July 1989 | Advises That 880713 Response to NRC Bulletin 88-004, Potential Safety-Related Pump Loss Acceptable | |
ML20246A756 | 26 June 1989 | Approves Reactor Operation Up to 50% Full Power,Per Util Power Ascension Test Program & Confirmatory Action Ltr 86-10.Assessment of Licensee Readiness for Release from NRC Approval Point 3 & Related Info Encl | Reactor Vessel Water Level |
ML20246B596 | 22 June 1989 | Forwards,For Info,Nrr Ack Receipt of Petition Filed by Ecology Ctr of Southern CA & Stating That Petition Being Treated Under 10CFR2.206 of Commission Regulations | |
ML20245A537 | 9 June 1989 | Forwards Insp Rept 50-293/89-05 on 890311-0410.Weaknesses Noted Re Evaluation of Failure Rate & Root Causes for Failures of Airlock Doors & Interlocks | |
ML20244C212 | 7 June 1989 | Responds to Util 881011 Response to Generic Ltr 87-02, Verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors. Implementation Schedule Contingent Upon Resolution of Procedure | |
ML20244C275 | 6 June 1989 | Forwards Draft Safety Evaluation Re Plant Compliance W/ 10CFR50.62, ATWS Rule. Requests Response to NRC Concerns Re Diversity & Testability of Alternate Rod Injection & Reactor Pump Trip Sys | |
NUREG-1275, Informs That Util Fulfilled Requirements of Generic Ltr 88-14, Instrument Air Supply Sys Problems Affecting Safety Related Sys | 2 June 1989 | Informs That Util Fulfilled Requirements of Generic Ltr 88-14, Instrument Air Supply Sys Problems Affecting Safety Related Sys | |
ML20247P550 | 1 June 1989 | Forwards Request for Addl Info on Proposed Tech Specs Change Re Visual Insp of High Energy Piping.Listed Concerns Based on Review of Bechtel Calculation 17322-S5,Rev 1 | |
ML20247M266 | 26 May 1989 | Forwards Director'S Decision,Ltr of Transmittal & Fr Notice in Response to Ocre 2.206 Petition Expressing Concerns Re 880309 Power Oscillation Event at LaSalle Unit 2 & Request to Reopen Rulemaking on ATWS Issue.W/O Encls | |
ML20246P605 | 15 May 1989 | Forwards Notice of Withdrawal of Application for Amend to License DPR-35.Amend Would Modify Tech Specs Re ECCS Surveillance Requirements | |
ML20247D548 | 8 May 1989 | Forwards Augmented Insp Team Rept 50-293/89-80 on 890413-19 & 17-26.Team Concluded That Safety Significance of 890412 Pressurization Transient Was Minor,Though Event Raised Concerns Re Proximate Human Factors & Equipment | |
ML20246N795 | 4 May 1989 | Forwards Mgt Meeting Rept 50-293/89-04 on 890328-30 W/Commonwealth of Ma & Local Officials | |
ML20247A691 | 3 May 1989 | Extends Invitation to Attend Power Reactor Operator Licensing Seminar on 890531 in King of Prussia,Pa.Agenda & Info Re Lodging Arrangements Encl | |
ML20245H837 | 26 April 1989 | Forwards SAIC-89/1121, In-Progress Audit Rept of Dcrdr at Boston Edison Co Pilgrim Nuclear Power Station & SAIC-89-1119, In-Progress Audit Rept for Boston Edison Co Pilgrim Nuclear Poser Station Spds | |
ML20245H955 | 26 April 1989 | Forwards Insp Rept 50-293/89-01 on 890206-0310 & Notice of Violation | |
ML20245J144 | 25 April 1989 | Advises That 880921 & 890302 Responses to NRC Bulletin 88-007 & Suppl 1, Power Oscillations in BWRs Meet Requirements of Both Bulletins | |
ML20244E461 | 14 April 1989 | Requests Prompt Review & Reporting of Status of Implementation of TMI Action Plan Items at Facility.Printout of All TMI Items Annotated Where Tracking Sys Indicates That Implementation Not Complete Encl | |
ML20244C277 | 10 April 1989 | Informs of Completion of Followup on Plant Regulatory Effectiveness Review Effort & Activities Re TAC 56995. Previous Compensatory Measures Removed as Result of Implementing Corrective Action | |
ML20244A693 | 7 April 1989 | Forwards Mgt Meeting Rept 50-293/89-43 on 890309 to Discuss Util Followup Actions to 890304 Reactor Scram | |
ML20244A628 | 3 April 1989 | Forwards Insp Rept 50-293/88-37 on 881227-890205.Violation Noted Re Failure to Control Locked High Radiation Area Access | Locked High Radiation Area |
ML20236A845 | 3 March 1989 | Approves Reactor Operation Up to 25% of Full Power Per Util Power Ascension Test Program & Confirmatory Action Ltr 86-10.Urges Util to Cooperate W/Commonwealth of Ma & Local Govts to Further Improve State of Emergency Preparedness |