Issue date | Title | Topic | |
---|---|---|---|
05000364/LER-2017-005 | 11 January 2018 | Power Range Nuclear Instrument Inoperable Due to Poor Connection of High Voltage Cable Connector LER 17-005-00 for Joseph M. Farley Nuclear Plant, Unit 2, Regarding Power Range Nuclear Instrument Inoperable Due to Poor Connection of High Voltage Cable Connector | |
05000364/LER-2017-004 | 22 December 2017 | I OF 3 LER 17-004-00 for Joseph M. Farley Nuclear Plant, Unit 2 Regarding Turbine-Driven Auxiliary Feedwater Pump Steam Admission Valve Air Leak Resulted in a Condition Prohibited by Technical Specifications | |
05000364/LER-2017-003 | 20 December 2017 | Pressurizer Safety Valve Lift Pressure Outside of Technical Specifications Limits LER 17-003-00 for Joseph M. Farley, Unit 2, Regarding Pressurizer Safety Valve Lift Pressure Outside of Technical Specifications Limits | Time of Discovery |
05000364/LER-2017-002 | 19 December 2017 | Main Steam Safety Valve Lift Pressure Outside of Technical Specifications Limits LER 17-002-00 for Joseph M. Farley, Unit 2, Regarding Main Steam Safety Valve Lift Pressure Outside of Technical Specifications Limits | |
05000364/LER-2017-001 | 21 August 2017 | 2B Emergency Diesel Generator Rendered Inoperable Due to a Jacket Water Leak without Makeup Capability LER 17-001-00 for Farley, Unit 2, Regarding 28 Emergency Diesel Generator Rendered Inoperable Due to a Jacket Water Leak without Makeup Capability | Mission time Past operability |
05000348/LER-2016-007 | 7 June 2017 | Plant Shutdown Required by Technical Specifications due to Inoperable Steam Flow Transmitters LER 16-007-01 for Joseph M. Farley, Unit 1, Regarding Plant Shutdown Required by Technical Specifications due to Inoperable Steam Flow Transmitters | |
05000348/LER-2016-009 | 2 February 2017 | Tornado Missile Vulnerabilities Result in Condition Prohibited by Technical Specifications LER 16-009-00 for Joseph M. Farley Nuclear Plant, Units 1 and 2 Regarding Tornado Missile Vulnerabilities Result in Condition Prohibited by Technical Specifications | Safe Shutdown Unanalyzed Condition Time of Discovery Tornado Missile Enforcement Discretion Tornado-Generated Missile Tornado Generated Missile Tornado Missile Protection TORMIS |
05000348/LER-2016-008 | 23 January 2017 | Manual Reactor Trip Due to Generator Voltage Swings LER 16-008-00 for Farley, Unit 1, Regarding Manual Reactor Trip Due to Generator Voltage Swings | |
05000348/LER-2016-005 | 28 December 2016 | Toxic Gas Event LER 16-005-00 for Joseph M. Farley Nuclear Plant, Unit 1, Regarding Toxic Gas Event | Safe Shutdown Fire Watch |
05000348/LER-2016-006 | 19 December 2016 | Manual Reactor Trip due to Loss of Speed Control on 1A Steam Generator Feed Pump LER 16-006-00 for Joseph M. Farley Nuclear Plant, Unit 1 Regarding Manual Reactor Trip due to Loss of Speed Control on 1A Steam Generator Feed Pump | |
05000348/LER-2016-004 | 19 December 2016 | Unapproved Environmental Qualification Material Caused Inoperability of One Containment Cooling Train LER 16-004-00 for Joseph M. Farley Nuclear Plant, Unit 1, Regarding Unapproved Environmental Qualification Material Caused lnoperability of One Containment Cooling Train | |
05000348/LER-2016-003 | 12 December 2016 | Pressurizer Safety Valve Setpoint Pressure Outside of Technical Specification Tolerance Band LER 16-003-00 for Farley, Unit 1, Regarding Pressurizer Safety Valve Setpoint Pressure Outside of Technical Specification Tolerance Band | Boric Acid Time of Discovery |
05000348/LER-2016-002 | 30 November 2016 | Automatic Reactor Trip and Safety Injection Due to Closure of Main Steam Isolation Valve LER 16-002-00 for Joseph M. Farley Nuclear Plant, Unit 1 Regarding Automatic Reactor Trip and Safety Injection Due to Closure of Main Steam Isolation Valve | |
05000348/LER-2016-001 | 9 June 2016 | Condition Prohibited by Technical Specifications Due to 600V Load Center Inoperable Longer than Allowed by Technical Specifications LER 16-001-00 for Farley, Unit 1, Regarding Condition Prohibited by Technical Specifications Due to 600V Load Center Inoperable Longer than Allowed by Technical Specifications | |
05000364/LER-2015-001 | 13 January 2016 | Turbine Driven Auxiliary Feedwater Pump in a Condition Prohibited by Technical Specifications due ,to a Design Issue LER 15-001-01 for Farley, Unit 2, Regarding Turbine Driven Auxiliary Feedwater Pump in a Condition Prohibited by Technical Specifications Due to a Design Issue | Past operability Temporary Modification |
NL-13-1525, Special Report 13-001-00 for Joseph M. Farley, Unit 2, Regarding Nonfunctional Radiation Monitor R-60B | 26 July 2013 | Special Report 13-001-00 for Joseph M. Farley, Unit 2, Regarding Nonfunctional Radiation Monitor R-60B | |
NL-11-2445, LER 11-S01-00 for Joseph M. Farley, Unit 1 Regarding Loss of Power to Security Systems | 9 January 2012 | LER 11-S01-00 for Joseph M. Farley, Unit 1 Regarding Loss of Power to Security Systems | |
NL-08-0756, Special Report 2008-002-00, Inoperable Radiation Monitor R-60B | 9 May 2008 | Special Report 2008-002-00, Inoperable Radiation Monitor R-60B | |
NL-08-0659, Special Report 2008-001-00, Inoperable Radiation Monitor R-29B | 25 April 2008 | Special Report 2008-001-00, Inoperable Radiation Monitor R-29B | |
NL-05-2234, Special Report No. 2005-001-00 for Joseph M. Farley Nuclear Plant - Unit 1 Re Inoperable Radiation Monitor R-60B | 6 December 2005 | Special Report No. 2005-001-00 for Joseph M. Farley Nuclear Plant - Unit 1 Re Inoperable Radiation Monitor R-60B |