IR 05000315/2023004 | 31 January 2024 | Integrated Inspection Report 05000315/2023004 and 05000316/2023004 | |
IR 05000315/2023404 | 6 November 2023 | Cyber Security Inspection Report 05000315/2023404 and 05000316/2023404 | Cyber Security Affidavit |
IR 05000315/2023403 | 19 September 2023 | Security Baseline Inspection Report 05000315/2023403 and 05000316/2023403 | |
IR 05000315/2023011 | 31 August 2023 | Functional Engineering Inspection - Commercial Grade Dedication Report 05000315/2023011 and 05000316/2023011 | Commercial Grade Dedication Coatings |
IR 05000315/2023402 | 11 August 2023 | Security Baseline Inspection Report 05000315/2023402 and 05000316/2023402 | Affidavit |
IR 05000315/2023002 | 24 July 2023 | Integrated Inspection Report 05000315/2023002 and 05000316/2023002 | Stroke time Internal Flooding Enforcement Discretion Temporary Modification Functionality Assessment FLEX Operability Determination Maintenance Rule Program Fire Protection Program |
IR 05000315/2023012 | 22 June 2023 | Biennial Problem Identification and Resolution Inspection Report 05000315/2023012 and 05000316/2023012 | Commercial Grade Dedication Met Tower Condition Adverse to Quality Significance Determination Process Operability Determination |
IR 05000315/2023501 | 21 June 2023 | Emergency Preparedness Biennial Exercise Inspection Report 05000315/2023501 and 05000316/2023501 | Siren |
IR 05000315/2023001 | 3 May 2023 | Integrated Inspection Report 05000315/2023001 and 05000316/2023001 | High winds Fire Barrier Past operability Enforcement Discretion Temporary Modification Functionality Assessment Significance Determination Process Operability Determination Fire Protection Program Fire Watch Scaffolding Power change |
IR 05000315/2023401 | 16 March 2023 | Security Baseline Inspection Report 05000315/2023401 and 05000316/2023401 | Fitness for Duty |
IR 05000315/2022006 | 1 March 2023 | Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2022006 and 05000316/2022006) | Commercial Grade Dedication Exemption Request Coronavirus |
IR 05000315/2022004 | 1 February 2023 | Integrated Inspection Report 05000315/2022004 and 05000316/2022004 and Exercise of Enforcement Discretion | Boric Acid Internal Flooding Enforcement Discretion Nondestructive Examination Temporary Modification Functionality Assessment FLEX Process Control Program Operability Determination Severe Accident Management Guideline Through-Wall Leak Fire Protection Program |
IR 05000315/2023010 | 31 January 2023 | Phase 4 Post-Approval License Renewal Inspection Report 05000315/2023010 and 05000316/2023010 | Aging Management License Renewal Fire Protection Program |
IR 05000315/2022011 | 4 November 2022 | Design Basis Assurance Inspection (Teams) Inspection Report 05000315/2022011 and 05000316/2022011 | Safe Shutdown Ultimate heat sink Stroke time Incorporated by reference Condition Adverse to Quality FLEX Significance Determination Process Large early release frequency Battery sizing Earthquake Power-Operated Valves Weak link |
IR 05000315/2022003 | 28 October 2022 | Integrated Inspection Report 05000315/2022003 and 05000316/2022003 | Offsite Dose Calculation Manual Internal Flooding Functionality Assessment Significance Determination Process Annual Radioactive Effluent Release Report Annual Radiological Environmental Operating Report Operability Determination Fire Protection Program Scaffolding |
IR 05000315/2022420 | 19 October 2022 | Cover Letter - Donald C. Cook Nuclear Plant Units 1 and 2 - Security Baseline Inspection Report 05000315/2022420 and 05000316/2022420 | Affidavit |
IR 05000315/2022401 | 21 September 2022 | Security Baseline Inspection Report 05000315 2022401 05000316 2022401 Independent Spent Fuel Storage Security Inspection Report 07200072 2022401 | |
IR 05000315/2022301 | 31 August 2022 | NRC Initial License Examination Report 05000315/2022301; 05000316/2022301 | Job Performance Measure |
IR 05000315/2022005 | 24 August 2022 | Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2022005 and 05000316/2022005) | Commercial Grade Dedication License Renewal Exemption Request COVID-19 |
IR 05000315/2022002 | 8 August 2022 | Integrated Inspection Report 05000315/2022002 and 05000316/2022002 | Unanalyzed Condition Boric Acid High Radiation Area Nondestructive Examination Temporary Modification Functionality Assessment Locked High Radiation Area Significance Determination Process Operability Determination Liquid penetrant Minimum staff Fire Protection Program Downpower Siren |
IR 05000315/2022402 | 5 July 2022 | Material Control and Accounting Program Inspection Report 05000315/2022402 and 05000316/2022402 | Affidavit |
ML22165A201 | 14 June 2022 | Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000315/2022001 and 05000316/2022001 | Boric Acid Non-Destructive Examination Aging Management Foreign Material Exclusion Dissimilar Metal Weld Scaffolding |
IR 05000315/2022001 | 10 May 2022 | Integrated Inspection Report 05000315/2022001 and 05000316/2022001 | Safe Shutdown Shutdown Margin Fire Barrier Temporary Modification Functionality Assessment Operability Determination Fire Protection Program Scaffolding Power change |
ML22129A205 | 10 May 2022 | Integrated Inspection Report 05000315/2022001 and 05000316/2022001 | Safe Shutdown Shutdown Margin Fire Barrier Temporary Modification Functionality Assessment Fire Protection Program Scaffolding Power change |
IR 05000315/2022010 | 5 April 2022 | Triennial Fire Protection Inspection Report 05000315/2022010 and 05000316/2022010 | Safe Shutdown Fire Protection Program |
ML22084A581 | 25 March 2022 | Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team): Inspection Report 05000315/2022011 05000316/2022011 | Stroke time Probabilistic Risk Assessment Temporary Modification Aging Management Job Performance Measure Large early release frequency Coronavirus |
IR 05000315/2021006 | 2 March 2022 | Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2021006 and 05000316/2021006) | License Renewal Exemption Request COVID-19 |
IR 05000315/2021004 | 7 February 2022 | Integrated Inspection Report 05000315/2021004 and 05000316/2021004 and Exercise of Enforcement Discretion | Packing leak Internal Flooding Enforcement Discretion Temporary Modification Functionality Assessment Aging Management Significance Determination Process Operability Determination Through Wall Leak Fire Protection Program Flow Induced Vibration |
IR 05000315/2021013 | 6 December 2021 | Inspection Report 05000315/2021013 and 05000316/2021013 | Probabilistic Risk Assessment Open Phase Condition Coronavirus COVID-19 |
IR 05000315/2021403 | 17 November 2021 | Security Baseline Inspection Report 05000315/2021403 and 05000316/2021403 | Coronavirus COVID-19 |
IR 05000315/2021011 | 15 November 2021 | Design Basis Assurance Inspection (Programs) Inspection Report 05000315/2021011 and 05000316/2021011 | Boric Acid Packing leak Probabilistic Risk Assessment Anchor Darling Significance Determination Process Power-Operated Valves Power Operated Valves Coronavirus COVID-19 Weak link |
IR 05000315/2021003 | 26 October 2021 | Integrated Inspection Report 05000315/2021003; 05000316/2021003; and 07200072/2021001 | Ultimate heat sink Internal Flooding Enforcement Discretion Temporary Modification Functionality Assessment Aging Management Operability Determination Coronavirus COVID-19 Liquid penetrant Fire Protection Program |
IR 05000315/2021401 | 21 October 2021 | Cyber Security Inspection Report 05000315/2021401 and 05000316/2021401 | Cyber Security Affidavit |
IR 05000315/2021501 | 6 October 2021 | Emergency Preparedness Biennial Exercise Inspection Report 05000315/2021501 and 05000316/2021501 | Coronavirus COVID-19 |
IR 05000315/2021010 | 7 September 2021 | Biennial Problem Identification and Resolution Inspection Report 05000315/2021010 and 05000316/2021010 | Packing leak Stroke time FLEX Operability Determination Power-Operated Valves Coronavirus COVID-19 |
IR 05000315/2021005 | 1 September 2021 | Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2021005 and 05000316/2021005) | Cyber Security Open Phase Condition License Renewal Exemption Request COVID-19 |
IR 05000315/2021012 | 2 August 2021 | Donald Cook Nuclear Plant - NRC Inspection Report 05000315/2021012 and 05000316/2021012 | Spent Fuel Pool Instrumentation Coronavirus COVID-19 |
IR 05000315/2021002 | 22 July 2021 | Integrated Inspection Report 05000315/2021002 and 05000316/2021002 | Boric Acid High Radiation Area Internal Flooding Hydrostatic Nondestructive Examination Temporary Modification Incorporated by reference Significance Determination Process Operability Determination Control of Heavy Loads Coronavirus COVID-19 Liquid penetrant Fire Protection Program Downpower |
ML21158A173 | 9 June 2021 | Review of the Fall 2017 Steam Generator Tube Inspections Report | |
IR 05000315/2021402 | 9 June 2021 | Donald D. C. Cook Nuclear Plant - Security Baseline Inspection Report 05000315/2021402 and 05000316/2021402 | |
IR 05000315/2021001 | 28 April 2021 | Integrated Inspection Report 05000315/2021001 and 05000316/2021001 | Stroke time Enforcement Discretion Functionality Assessment Significance Determination Process Process Control Program Operability Determination Coronavirus COVID-19 Fire Protection Program Power change |
IR 05000315/2020006 | 4 March 2021 | Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2020006 and 05000316/2020006) | Open Phase Condition License Renewal Exemption Request COVID-19 |
IR 05000315/2020004 | 8 February 2021 | Integrated Inspection Report 05000315/2020004 and 05000316/2020004 | Boric Acid High Radiation Area Internal Flooding Enforcement Discretion Nondestructive Examination VT-2 Functionality Assessment Locked High Radiation Area FLEX Significance Determination Process Large early release frequency Operability Determination Coronavirus COVID-19 Fire Protection Program Unidentified leakage |
IR 05000315/2020403 | 16 December 2020 | Security Baseline Inspection Report 05000315/2020403 and 05000316/2020403 | Coronavirus COVID-19 |
IR 05000315/2020402 | 4 November 2020 | Security Baseline Inspection Report 05000315/2020402 and 05000316/2020402 | Coronavirus COVID-19 |
IR 05000315/2020003 | 28 October 2020 | Integrated Inspection Report 05000315/2020003 and 05000316/2020003 | Non-Destructive Examination Temporary Modification Functionality Assessment Operability Determination Coronavirus COVID-19 Power change |
IR 05000315/2020301 | 19 October 2020 | NRC Initial License Examination Report 05000315/2020301; 05000316/2020301 | Job Performance Measure |
IR 05000315/2020011 | 17 September 2020 | Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000315/2020011; 05000316/2020011 | Open Phase Condition |
IR 05000315/2020005 | 1 September 2020 | Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2020005 and 05000316/2020005) | Operator Manual Action Cyber Security Open Phase Condition License Renewal Exemption Request Power-Operated Valves COVID-19 |
IR 05000315/2020002 | 10 August 2020 | Integrated Inspection Report 05000315/2020002 and 05000316/2020002 | Offsite Dose Calculation Manual Enforcement Discretion Temporary Modification Functionality Assessment Annual Radioactive Effluent Release Report Operability Determination Coronavirus COVID-19 Fire Protection Program Siren |