Semantic search

Jump to navigation Jump to search
 Issue dateTitleTopic
L-99-035, Forwards non-proprietary & Proprietary Versions of Farley Units 1 & 2 LBB Calculation Results Due to SG Replacement & SG Snubber Elimination Programs, Used to Support SG Replacement Project.Proprietary Encl Withheld18 October 1999Forwards non-proprietary & Proprietary Versions of Farley Units 1 & 2 LBB Calculation Results Due to SG Replacement & SG Snubber Elimination Programs, Used to Support SG Replacement Project.Proprietary Encl Withheld
ML20217P0666 October 1999Requests Withholding of Proprietary Rept NSD-SAE-ESI-99-389, Farley Units 1 & 2 LBB Calculation Results Due to SG Replacement & SG Snubber Elimination Programs
ML20217B1894 October 1999Submits Clarification Re Development of Basis for Determining Limiting Internal Pressure Loads Re Review of NRC SE for Cycle 16 Extension Request.Util Intends to Use Guidelines When Evaluating SG Tube Structural IntegritySafe Shutdown
L-99-034, Forwards Comments on Draft Current Tech Specs Discussion of Change Tables for Jm Farley Nuclear Plant.Units 1 & 223 September 1999Forwards Comments on Draft Current Tech Specs Discussion of Change Tables for Jm Farley Nuclear Plant.Units 1 & 2
L-99-032, Responds to NRC Re Adequacy of Kaowool Fire Retardant Fire Barriers in Use at Jfnp,Units 1 & 223 September 1999Responds to NRC Re Adequacy of Kaowool Fire Retardant Fire Barriers in Use at Jfnp,Units 1 & 2Fire Barrier
Exemption Request
Fire Protection Program
ML20212F88623 September 1999Forwards Revised Relief Request Number 32 for NRC Approval. Approval Requested by 991231 to Support Activities to Be Performed During Unit 1 Refueling Outage Scheduled for Spring of 2000
ML20212C23516 September 1999Submits Corrected Info Concerning Snoc Response to NRC GL 99-02, Lab Testing of Nuclear-Grade Activated Charcoal
ML20212D01015 September 1999Informs That Submittal of clean-typed Copy of ITS & ITS Bases Will Be Delayed.Delay Due to Need for Resolution of Two Issues Raised by NRC staff.Clean-typed Copy of ITS Will Be Submitted within 4 Wks Following Resolution of IssuesEnforcement Discretion
L-99-031, Informs NRC That Review of MOV Testing Frequency & Changes Made to Frequency of MOV Testing Has Been Completed13 September 1999Informs NRC That Review of MOV Testing Frequency & Changes Made to Frequency of MOV Testing Has Been Completed
ML20212C46413 September 1999Forwards Info Requested in Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing ExamsGeneric Fundamentals Examination
ML20211K21331 August 1999Informs That Snoc Has Conducted Review of Reactor Vessel Integrity Database,Version 2 (RVID2) & Conclude That Latest Data Submitted for Farley Units Has Not Been Incorporated Into RVID2
ML20211K41031 August 1999Resubmits Relief Requests Q1P16-RR-V-5 & Q2P16-RR-V-5 That Seek to Group V661 Valves from Each Unit Into Sample Disassembly & Insp Group,Per 990525 Telcon with NRC
L-99-030, Forwards SNC Review Comments on Draft SE & marked-up Copy of Draft SE Incorporating SNC Comments Re Proposed Conversion to ITS30 August 1999Forwards SNC Review Comments on Draft SE & marked-up Copy of Draft SE Incorporating SNC Comments Re Proposed Conversion to ITSShutdown Margin
High Radiation Area
Grab sample
Offsite Dose Calculation Manual
Turbine Missile
Offsite Circuit
L-99-029, Forwards Revised Response to Chapter 3.1 RAI Requested in 990726 Conference Call,Rai Response Related to Beyond Scope Issue for Chapter 3.5 Requested by Conference Call on 990805 & RAI Response to Chapter 3.8 Requested on 990615 & 072719 August 1999Forwards Revised Response to Chapter 3.1 RAI Requested in 990726 Conference Call,Rai Response Related to Beyond Scope Issue for Chapter 3.5 Requested by Conference Call on 990805 & RAI Response to Chapter 3.8 Requested on 990615 & 0727Shutdown Margin
Qualified Offsite Circuit
Offsite Circuit
ML20211B94317 August 1999Forwards Fitness for Duty Performance Data for six-month Reporting Period 990101-990630,IAW 10CFR26.71(d).Rept Covers Employees at Jm Farley Nuclear Plant & Southern Nuclear Corporate HeadquartersFitness for Duty
ML20211B92117 August 1999Responds to NRC Re Violations Noted in Insp Rept 50-348/99-09 & 50-364/99-09.Corrective Actions:Security Response Plan Was Revised to Address Vulnerabilities Identified During NRC Insp
ML20210R51012 August 1999Forwards Revised Page 6 to 990430 LAR to Operate Farley Nuclear Plant,Unit 1,for Cycle 16 Only,Based on risk- Informed Approach for Evaluation of SG Tube Structural Integrity,As Result of Staff Comments
ML20212C8149 August 1999Forwards Correspondence Received from Jm Sherman.Requests Review of Info Re Established Policies & Procedures
ML20210G49030 July 1999Responds to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal, Issued 990603.Ltr Contains NRC License Commitment to Utilize ASTM D3803-1989 with Efficiency Acceptance Criteria Utilizing Safety Factor of 2Enforcement Discretion
L-99-028, Responds to NRC 990730 RAI Re 990423 OL Change Request to Allow for Risk Informed Approach for Evaluation of SG Tube Structural Integrity as Described by NEI 97-06, SG Program Guidelines30 July 1999Responds to NRC 990730 RAI Re 990423 OL Change Request to Allow for Risk Informed Approach for Evaluation of SG Tube Structural Integrity as Described by NEI 97-06, SG Program GuidelinesNondestructive Examination
L-99-027, Addresses Clarifications to Selected Responses to Chapter 3.8 RAI Requested in NRC Conference Call on 990624, Resolution of Open Issue Related to Containment Purge in Chapter 3.6 & Response Related to Chapter 3.527 July 1999Addresses Clarifications to Selected Responses to Chapter 3.8 RAI Requested in NRC Conference Call on 990624, Resolution of Open Issue Related to Containment Purge in Chapter 3.6 & Response Related to Chapter 3.5Qualified Offsite Circuit
Offsite Circuit
ML20210E40722 July 1999Responds to NRC 990702 RAI Re Change Request to Allow for Risk Informed Approach for Evaluation of SG Tube Structural Integrity as Described in NEI 97-06, SG Program Guidelines
L-99-026, Forwards Response to NRC 990702 RAI Re SG Replacement Related TS Change Request Submitted 981201.Ltr Contains No New Commitments19 July 1999Forwards Response to NRC 990702 RAI Re SG Replacement Related TS Change Request Submitted 981201.Ltr Contains No New CommitmentsEarthquake
L-99-264, Responds to NRC 990603 Administrative Ltr 99-02, Operating Licensing Action Estimates, for Fy 2000 & 200113 July 1999Responds to NRC 990603 Administrative Ltr 99-02, Operating Licensing Action Estimates, for Fy 2000 & 2001
ML20209H47213 July 1999Responds to NRC 990603 Administrative Ltr 99-02, Operating Licensing Action Estimates, for Fy 2000 & 2001
05000364/LER-1999-001, Forwards LER 99-001-00 Re Reactor Trip Due to Loss of Condenser Vacuum Steam Dump Drain Line Failure.Commitments Made by Licensee,Listed2 July 1999Forwards LER 99-001-00 Re Reactor Trip Due to Loss of Condenser Vacuum Steam Dump Drain Line Failure.Commitments Made by Licensee,Listed
L-99-024, Responds to NRC RAI Re Conversion to ITS for Chapters 3.4, 3.5,3.6,3.7,3.9 & 5.0,per 990419-20 Meetings with NRC30 June 1999Responds to NRC RAI Re Conversion to ITS for Chapters 3.4, 3.5,3.6,3.7,3.9 & 5.0,per 990419-20 Meetings with NRC
L-99-025, Forwards Rev 2 to Jfnp Security plan,FNP-0-M-99,IAW 10CFR50.4(b)(4).Attachment 1 Contains Summary of Changes & Amended Security Plan Pages.Encl Withheld from Public Disclosure Per 10CFR73.2130 June 1999Forwards Rev 2 to Jfnp Security plan,FNP-0-M-99,IAW 10CFR50.4(b)(4).Attachment 1 Contains Summary of Changes & Amended Security Plan Pages.Encl Withheld from Public Disclosure Per 10CFR73.21
ML20196J86330 June 1999Submits Correction to Errors Contained in to NRC Re TS Changes Re Control Room,Penetration Room & Containment Purge Filtration Systems & Radiation Monitoring Instrumentation.Errors Do Not Require Rev of SA
L-99-249, Submits Correction to Errors Contained in to NRC Re TS Changes Re Control Room,Penetration Room & Containment Purge Filtration Systems & Radiation Monitoring Instrumentation.Errors Do Not Require Rev of SA30 June 1999Submits Correction to Errors Contained in to NRC Re TS Changes Re Control Room,Penetration Room & Containment Purge Filtration Systems & Radiation Monitoring Instrumentation.Errors Do Not Require Rev of SA
L-99-224, Submits Rev to Unit 2 SG Tube voltage-based Repair Criteria Data Rept.Ltr Contains No Commitments7 June 1999Submits Rev to Unit 2 SG Tube voltage-based Repair Criteria Data Rept.Ltr Contains No Commitments
ML20195F1737 June 1999Forwards Proprietary & non-proprietary Responses to NRC RAIs Re W TR WCAP-14750, RCS Flow Verification Using Elbow Taps at W 3-Loop Pwrs. W Proprietary Notice,Affidavit & Copyright Notice,Encl.Proprietary Info Withheld
L-99-217, Forwards Proprietary & non-proprietary Responses to NRC RAIs Re W TR WCAP-14750, RCS Flow Verification Using Elbow Taps at W 3-Loop Pwrs. W Proprietary Notice,Affidavit & Copyright Notice,Encl.Proprietary Info Withheld7 June 1999Forwards Proprietary & non-proprietary Responses to NRC RAIs Re W TR WCAP-14750, RCS Flow Verification Using Elbow Taps at W 3-Loop Pwrs. W Proprietary Notice,Affidavit & Copyright Notice,Encl.Proprietary Info Withheld
L-99-225, Responds to GL 98-01, Yr 2000 Readiness of Computer Sys at Nuclear Power Plants7 June 1999Responds to GL 98-01, Yr 2000 Readiness of Computer Sys at Nuclear Power Plants
ML20195F0627 June 1999Submits Rev to Unit 2 SG Tube voltage-based Repair Criteria Data Rept.Ltr Contains No Commitments
ML20195E9587 June 1999Responds to GL 98-01, Yr 2000 Readiness of Computer Sys at Nuclear Power Plants
ML20195C69428 May 1999Forwards Response to NRC RAI Re GL 96-05 for Farley Nuclear Plant.Farley Is Committing to Implement Phase 3 of JOG ProgramProbabilistic Risk Assessment
Weak link
L-99-021, Forwards Response to RAI Re Conversion to ITSs for Chapter 3.3.Attachment II Includes Proposed Revs to Previously Submitted LAR Re Rais,Grouped by RAI number.Clean-typed Copies of Affected ITS Pages Not Included28 May 1999Forwards Response to RAI Re Conversion to ITSs for Chapter 3.3.Attachment II Includes Proposed Revs to Previously Submitted LAR Re Rais,Grouped by RAI number.Clean-typed Copies of Affected ITS Pages Not IncludedShutdown Margin
L-99-203, Forwards Response to NRC RAI Re GL 96-05 for Farley Nuclear Plant.Farley Is Committing to Implement Phase 3 of JOG Program28 May 1999Forwards Response to NRC RAI Re GL 96-05 for Farley Nuclear Plant.Farley Is Committing to Implement Phase 3 of JOG ProgramProbabilistic Risk Assessment
Weak link
ML20195F21024 May 1999Requests That Farley Nuclear Plant Proprietary Responses to NRC RAI Re W WCAP-14750, RCS Flow Verification Using Elbow Taps at W 3-Loop Pwrs, Be Withheld from Public Disclosure Per 10CFR2.790
L-99-180, Forwards Responses to NRC RAI Questions for Chapter 3.8 of Ts.Proposed Revs to TS Previously Submitted with LAR Related to RAI30 April 1999Forwards Responses to NRC RAI Questions for Chapter 3.8 of Ts.Proposed Revs to TS Previously Submitted with LAR Related to RAISafe Shutdown
Offsite Circuit
ML20206F43230 April 1999Forwards Responses to NRC RAI Questions for Chapter 3.8 of Ts.Proposed Revs to TS Previously Submitted with LAR Related to RAISafe Shutdown
Offsite Circuit
L-99-017, Forwards Responses to NRC RAI Questions for Chapters 3.1, 3.2,3.5,3.7 & 3.9 of Ts.Attached Pages Include Proposed Revs Previously Submitted LAR to Rais,Grouped by Chapters & RAI Numbers30 April 1999Forwards Responses to NRC RAI Questions for Chapters 3.1, 3.2,3.5,3.7 & 3.9 of Ts.Attached Pages Include Proposed Revs Previously Submitted LAR to Rais,Grouped by Chapters & RAI NumbersShutdown Margin
ML20206C80226 April 1999Forwards 1998 Annual Rept, for Alabama Power Co.Encls Contain Financial Statements for 1998,unaudited Financial Statements for Quarter Ending 990331 & Cash Flow Projections for 990101-991231
05000348/LER-1998-007, Forwards SG-99-04-001, Farley-1:Final Cycle 16 Freespan ODSCC Operational Assessment, as Committed to in Licensee & LER 98-007-00.Util Is Revising Plant Administrative SG Operating Leakage Requirements as Listed23 April 1999Forwards SG-99-04-001, Farley-1:Final Cycle 16 Freespan ODSCC Operational Assessment, as Committed to in Licensee & LER 98-007-00.Util Is Revising Plant Administrative SG Operating Leakage Requirements as ListedProbabilistic Risk Assessment
Large early release frequency
L-99-015, Forwards Rev 1 to Jfnp Security plan,FNP-O-M-99,resulting from Implementation of Biometrics Sys.Changes Incorporate Changes Previously Submitted to NRC as Rev 28 by Licensee .Encl Withheld,Per 10CFR73.2121 April 1999Forwards Rev 1 to Jfnp Security plan,FNP-O-M-99,resulting from Implementation of Biometrics Sys.Changes Incorporate Changes Previously Submitted to NRC as Rev 28 by Licensee .Encl Withheld,Per 10CFR73.21
ML20206B43921 April 1999Forwards Corrected ITS Markup Pages to Replace Pages in 981201 License Amend Requests for SG Replacement
L-99-172, Forwards FNP Annual Radioactive Effluent Release Rept for 1998, IAW TSs Sections 6.9.1.8 & 6.9.1.9.Changes to ODCM Revs 16,17 & 18 Are Encl,Iaw TS Section 6.14.221 April 1999Forwards FNP Annual Radioactive Effluent Release Rept for 1998, IAW TSs Sections 6.9.1.8 & 6.9.1.9.Changes to ODCM Revs 16,17 & 18 Are Encl,Iaw TS Section 6.14.2Offsite Dose Calculation Manual
Annual Radioactive Effluent Release Report
ML20205S95021 April 1999Forwards FNP Annual Radioactive Effluent Release Rept for 1998, IAW TSs Sections 6.9.1.8 & 6.9.1.9.Changes to ODCM Revs 16,17 & 18 Are Encl,Iaw TS Section 6.14.2Offsite Dose Calculation Manual
Annual Radioactive Effluent Release Report
ML20205R04313 April 1999Forwards Correction to 960212 GL 95-07 180 Day Response. Level 3 Evaluation for Pressure Locking Utilized Analytical Models.Encl Page Has Been Amended to Correct Error