 QuarterSiteTitleTopic
05000277/FIN-2018003-022018Q3Peach BottomInadequate Corrective Actions Result in the Failure of the E-3 EDGPreliminary White Finding
05000334/FIN-2018003-012018Q3Beaver ValleyInadequate Verification of Full Low Head Safety Injection Suction PipingNondestructive Examination
05000219/FIN-2018410-012018Q2Oyster CreekSecurity
05000352/FIN-2018002-012018Q2LimerickFailure to Conduct Adequate Radiation Surveys and Evaluate Potential Radiological Hazards
05000277/FIN-2017403-012017Q3Peach BottomSecurity
05000336/FIN-2017403-032017Q1MillstoneSecurity
05000293/FIN-2016403-032016Q4PilgrimSecurity
05000333/FIN-2016004-012016Q4FitzPatrickFailure to Ensure Proper Configuration Control of a PCIV During Planned MaintenanceSignificance Determination Process
Reasonable doubt of operability
05000353/FIN-2016003-012016Q3LimerickInadequate Design Control of Plant Processing Computer ModificationSignificance Determination Process
05000334/FIN-2016002-032016Q2Beaver ValleyFailure to Appropriately Utilize Multiple and Diverse Indications Results in Plant Transient
05000443/FIN-2016002-012016Q2SeabrookAutomatic Initiation of Emergency Feedwater Resulting from Performance of Procedural Steps in a Manner Prohibited by Documented InstructionsSignificance Determination Process
05000333/FIN-2016001-022016Q1FitzPatrickUncontrolled RPV Level Increase after Initiation of RHR Shutdown CoolingSignificance Determination Process
05000247/FIN-2016001-052016Q1Indian PointFailure to Provide Adequate Procedural Guidance in Order to Prevent an Overcurrent ConditionSignificance Determination Process
05000388/FIN-2015004-012015Q4SusquehannaFailure to Correct a Condition Adverse to Quality Associated with an Inoperable Primary Containment Isolation ValveCondition Adverse to Quality
05000387/FIN-2015004-042015Q4SusquehannaInadvertent Closure of the B Inboard MSIVSignificance Determination Process
05000317/FIN-2015004-022015Q4Calvert CliffsAFAS Channel Inoperable due to Valve MispositionSignificance Determination Process
05000410/FIN-2015003-012015Q3Nine Mile PointUse of Incorrect Grounding Cart Results in Loss of Electrical BusSignificance Determination Process
05000286/FIN-2015010-012015Q2Indian PointFailure to Correct a Degraded Condition of Fire Protection System Solenoid Valve SOV-230-1Fire Protection Program
05000220/FIN-2015002-012015Q2Nine Mile PointFailure to Notify of Changes to Work ScopeSignificance Determination Process
Unplanned internal exposure
Scaffolding
Substantial potential for overexposure
05000286/FIN-2015002-022015Q2Indian PointFailure to Maintain the Effectiveness of Emergency Plan Due to an Inadequate Basis for Emergency Action Level Thresholds
05000387/FIN-2015002-022015Q2SusquehannaEntry into a High Radiation Area without Radiological BriefingHigh Radiation Area
Substantial potential for overexposure
05000219/FIN-2015002-042015Q2Oyster CreekReset of the Automatic Voltage Regulator Controller Led to an Automatic Reactor Scram
05000219/FIN-2015002-032015Q2Oyster CreekReactor Water Cleanup Procedure Not Followed Resulting in a Level Transient
05000220/FIN-2015001-012015Q1Nine Mile PointFailure to Declare Notice of Unusual Event Following Sodium Bisulfite Spill in Unit 1 Screenhouse
05000412/FIN-2014004-012014Q3Beaver ValleyInadequate Plant Startup Procedure Led to Manual Reactor Trip
05000311/FIN-2014003-012014Q2SalemInadequate Solid Pressurizer Control Resulted in Low Temperature Overpressure Relief Lifting
05000410/FIN-2014003-032014Q2Nine Mile PointLoss of Spent Fuel Cooling Pump due to Inadequate ProceduresSignificance Determination Process
05000271/FIN-2014002-012014Q1Vermont YankeeFailure to Monitor the Unavailability of the Fire Water to Service Water CrosstieSignificance Determination Process
05000219/FIN-2014002-012014Q1Oyster CreekUntimely Performance of a 50.65 a(4) Risk Evaluation during a Maximum Emergency Generation Action
05000334/FIN-2013005-012013Q4Beaver ValleyMoisture Separator Reheater Valve Misposition Results in Plant TransientSignificance Determination Process
05000272/FIN-2012004-012012Q3SalemInadvertent Injection of Auxiliary Feedwater Into the 23 Steam GeneratorSignificance Determination Process
05000277/FIN-2011002-012011Q1Peach BottomFH Procedures Were Inadequate to Prevent Fuel from Contacting an ObstructionFuel cladding
05000271/FIN-2010004-012010Q3Vermont YankeeInadvertent isolation of Reactor Core Isolation Cooling (RCIC) During Surveillance Testing
05000352/FIN-2009005-012009Q4LimerickFailure to Ensure Adequate Cooling Water Flow to Residual Heat Removal Room Unit Cooler
05000277/FIN-2009005-032009Q4Peach BottomInadequate Verification Practices while Handling Fuel and Fuel Components
05000293/FIN-2009004-042009Q3PilgrimHuman Error Resulting in Unplanned High Pressure Coolant Injection (HPCI) Isolation
05000277/FIN-2009004-022009Q3Peach BottomInadequate Procedure Adherence Results in the Loss of Safety Function of Systems Supplied by the Sgig System
05000333/FIN-2009003-012009Q2FitzPatrickHigh Energy Line Break Door Missing Lower Support
05000219/FIN-2009003-062009Q2Oyster CreekLoss of Secondary Containment Integrity During Maintenance on Reactor Building Roof
05000317/FIN-2009002-012009Q1Calvert CliffsDid Not Follow MSIV Actuator System Procedure
05000247/FIN-2009002-012009Q1Indian PointFailure to Identify Open Louvers in 11 Fire Pump HouseCondition Adverse to Quality
Significance Determination Process
05000220/FIN-2009002-032009Q1Nine Mile PointFailure to Properly Standby Liquid Control System Surveillance
05000244/FIN-2008005-012008Q4GinnaFailure to Meet Minimum Shift Manning Requirements Due to InattentivenessFitness for Duty
Significance Determination Process
05000247/FIN-2008004-012008Q3Indian PointAuxiliary Feedwater System Configuration Control Deficiencies
05000244/FIN-2008004-012008Q3GinnaInadequate Procedure Adherence Resulting in a Loss of Normal Control Room CommunicationsSignificance Determination Process
05000247/FIN-2008003-052008Q2Indian PointFailure to Follow Plant START-UP Procedure Regarding MBFP Turbine Runback Arm/Defeat Switch
05000220/FIN-2008003-012008Q2Nine Mile PointFailure to Meet TS Oversight RequirementSignificance Determination Process
05000272/FIN-2008002-022008Q1SalemSalem Unit 2 Loss of All Three Chillers (Section 1R15)
05000220/FIN-2008002-012008Q1Nine Mile PointFailure to Correctly Perform Procedure Caused Inadvertent Isolation of RCIC Steam Supply
05000286/FIN-2008002-052008Q1Indian PointFailure to Follow Procedures Results in Loss of Safety Bus 5A