The query [[Category:ENS Notification]] [[Reactor type::W-AP1000]] was answered by the SMWSQLStore3 in 0.0088 seconds.


Results 1 – 42    (Previous 50 | Next 50)   (20 | 50 | 100 | 250 | 500)   (JSON | CSV | RSS | RDF)
 Entered dateSiteRegionReactor typeEvent description
ENS 533092 April 2018 18:33:00VogtleNRC Region 2W-AP1000A contractor employee supervisor had a confirmed positive for illegal drugs during a fitness for duty test. The employee's access to the site has been terminated. The NRC Resident Inspector has been notified.
ENS 5327722 March 2018 09:31:00VogtleNRC Region 2W-AP1000A non-licensed contract supervisor attempted to subvert a random Fitness For Duty test using a subversion kit on their person. The employee's access to the plant has been terminated. The NRC Resident Inspector has been notified.
ENS 5301816 October 2017 17:59:00VogtleNRC Region 2W-AP1000A non-licensed supervisory contractor subverted a random Fitness for Duty (FFD) test. At 0851 (EDT) on October 16, 2017, a contractor supervisor was notified to report for a random FFD test and (the individual) did not report to the testing facility and left the premises. The contractor's site access has been terminated. The NRC Resident Inspector was notified.
ENS 5296814 September 2017 09:10:00VogtleNRC Region 2W-AP1000On September 13, 2017, Southern Nuclear Operating Company (SNC) determined a Contractor Manager confirmed positive for alcohol during a for cause fitness-for-duty test. The employee's unescorted access to the plant has been terminated. The NRC Resident Inspector has been notified.
ENS 5276318 May 2017 15:14:00VogtleNRC Region 2W-AP1000On May 17, 2017, at 1852 (EDT), Southern Nuclear Operating Company (SNC) contractor informed SNC that a contractor Fitness-for-Duty (FFD) collector failed to follow the process defined in both NRC Regulation 10 CFR 26.105(b) and contractor FFD procedures. The collector was fully trained, qualified, and knowledgeable of the process requirements. This determination was made based on initial department investigations and corroborated via independent investigations performed by the contractor. SNC has determined that this is reportable under 10 CFR 26.719(b)(3). The licensee informed the NRC Resident Inspector and NRC Region II.
ENS 526686 April 2017 15:58:00SummerNRC Region 2W-AP1000A contractor manager had a confirmed positive for alcohol during a pre-access test. The employee's access to the construction site has been revoked. The licensee notified the NRC Unit 2 & 3 Resident Inspector.
ENS 5264127 March 2017 16:02:00VogtleNRC Region 2W-AP1000A non-licensed contractor employee had a confirmed positive for a controlled substance during a random fitness-for-duty test. The employee's access to the site has been terminated. The licensee notified the NRC Resident Inspector.
ENS 5248211 January 2017 13:52:00VogtleNRC Region 2W-AP1000A non-licensed supervisor tested positive for alcohol during a for-cause test. The individual's access to the site has been terminated pending the results of an investigation. The licensee notified RII (Patterson) and the NRC Resident Inspector.
ENS 524127 December 2016 13:12:00VogtleNRC Region 2W-AP1000In accordance with 10 CFR 52.99(c)(2), Vogtle Units 3 and 4 Construction is making this notification to NRC for determining that Inspection, Test, Analysis, and Acceptance Criteria (ITAAC) 2.6.01.02.ii (ECS System Seismic Category I Equipment Design Basis Loads) for both units requires additional actions to restore its completed status. The Closure Notification for this ITAAC (NRC Index No. 580) was originally submitted on May 17, 2016 (reference ML 16138A080 and ML 16166A030). On November 1, 2016, it was determined by the Vogtle 3&4 Contractor that modifications to the Reactor Coolant Pump (RCP) breaker (i.e., switchgear) cabinet design were required to ensure compliance with the applicable portions of IEEE 384, 'Standard Criteria for Independence of Class 1E Equipment and Circuits.' The modification involves an engineering change which adds different equipment to the RCP Breaker cabinet that function to trip the RCP. The new components were not previously qualified for use in the RCP breaker cabinet assembly. Additional seismic qualification type testing and analysis of components are being performed for the added components in the RCP breaker. Update of the Equipment Qualification Data Package and Equipment Qualification Summary Report for the RCP breaker to confirm the breaker withstands seismic design basis loads and Licensee's acceptance is in progress. The revised ITAAC Completion Notice will be submitted to the NRC once all related ITAAC activities have been completed. The licensee has notified the NRC Resident Inspector.
ENS 523548 November 2016 11:44:00SummerNRC Region 2W-AP1000In accordance with 10CFR52.99(c)(2), V.C. Summer Units 2 and 3 Construction is making this notification to NRC for determining that Inspection, Test, Analysis, and Acceptance Criteria (ITAAC) 2.6.01.02.ii (Seismic Qualification of Reactor Coolant Pump Switchgear) for both units requires additional actions to restore its completed status. The Closure Notification for this ITAAC (NRC Index No. 580) was originally submitted on February 29, 2016 (reference ML16060A344 and ML16060A345). On November 2, 2016, it was determined that modifications to the RCP switchgear cabinet design were required to ensure compliance with the applicable portions of IEEE 384, Standard Criteria for Independence of Class 1E Equipment and Circuits. The modification involved an engineering change which adds different equipment to the RCP Switchgear cabinet which function to trip the RCP. The new components were not previously seismically qualified for use in the RCP switchgear cabinet assembly. The additional components have now undergone seismic qualification testing for use in the RCP switchgear. The Equipment Qualification Data Package and Equipment Qualification Summary Report for the RCP switchgear will be revised based on the results of the testing to confirm the switchgear withstands seismic design basis loads. The revised testing report has been completed on November 8 2016. The licensee notified the NRC Resident Inspector.
ENS 5220830 August 2016 16:05:00VogtleNRC Region 2W-AP1000A non-licensed employee supervisor had a confirmed positive for alcohol during a random fitness-for-duty test. The employee's access to the plant has been terminated.
ENS 521472 August 2016 16:22:00VogtleNRC Region 2W-AP1000A member of the Fitness-For-Duty (FFD) staff violated the FFD policy in December, 2014 by responding to a call-in for unscheduled work after having consumed alcohol within the prohibited 5 hour period. The licensee informed the NRC Resident Inspector.
ENS 5208614 July 2016 15:15:00SummerNRC Region 2W-AP1000On 7/14/16, at 0741 (EDT), it was determined that (a contract employee supervisor) violated its FFD policy. The individual's construction site access has been revoked. This event is reportable pursuant to 10 CFR 26.719(b)(2)(ii). The Units 2 and 3 (NRC) Resident Inspector has been notified.
ENS 519867 June 2016 14:10:00VogtleNRC Region 2W-AP1000A non-licensed contract supervisor had a confirmed positive for a controlled substance during a random fitness-for-duty test. The employee's access to the plant has been terminated. The licensee notified the NRC Resident Inspector.
ENS 5194118 May 2016 08:13:00SummerNRC Region 2W-AP1000A contract supervisor had a confirmed positive for illegal drugs during a for-cause fitness-for-duty test. The employee's access to the plant has been terminated. The licensee notified the NRC Construction Resident Inspector.
ENS 5187521 April 2016 18:18:00VogtleNRC Region 2W-AP1000A non-licensed supervisory contractor admitted to attempting to subvert a Fitness for Duty test. The contractor's site access has been terminated. The NRC Resident Inspector was notified.
ENS 5115816 June 2015 10:39:00SummerNRC Region 2W-AP100010 CFR 50.55(e) initial notification for a failure to comply with requirements of 10 CFR 50 Appendix B associated with AP1000 nuclear power plant construction by Chicago Bridge & Iron Company (CB&I) at the V.C. Summer Units 2 & 3 construction site. This 50.55(e) initial notification addresses a failure to comply by CB&I, an agent of South Carolina Electric & Gas Company (SCE&G) for V.C. Summer Units 2 & 3, to meet the requirements of Appendix B, Criteria V and XV. It is concluded that Quality Assurance programmatic issues, as identified by CB&I Root Cause Analysis 2015-0539, could have produced a defect and this condition is reportable in accordance with 10 CFR 50.55(e)(3)(iii)(C). Root Cause Analysis 2015-0539 investigated the causes that lead to impingement of safety related reinforcing steel and the steel containment vessel during concrete core drilling operations within the Unit 2 containment structure. No defect has been identified. This condition is associated with NRC special inspection report number 05200027/2015-009. This notification closes the Interim Part 21 report submitted on April 16th, 2015, by CB&I. This 50.55(e) Initial Notification is being submitted pursuant to the requirements of 10 CFR 50.55(e)(3)(iii)(C). The licensee notified the NRC Resident Inspector.
ENS 5101024 April 2015 14:14:00SummerNRC Region 2W-AP1000A contract employee supervisor tested positive for a follow-up fitness-for-duty test. The employees access to the site has been denied. The licensee has notified the NRC Resident Inspector.
ENS 5100523 April 2015 13:18:00SummerNRC Region 2W-AP1000A contract employee supervisor willfully acted to avoid a random fitness-for-duty test. The individual left the construction site after the notification to report to the fitness-for-duty office. The employees access to the plant has been terminated. The licensee has notified the NRC Resident Inspector.
ENS 508572 March 2015 18:31:00VogtleNRC Region 2W-AP1000On March 2, 2015, Southern Nuclear Operating Company (SNC) had a non-licensed supervisory contractor employee confirmed positive result for alcohol during a fitness-for-duty test. The contractor employee's unescorted access to the plant has been terminated. The NRC Senior Resident Inspector has been informed.
ENS 5081512 February 2015 17:19:00SummerNRC Region 2W-AP1000This is a 10 CFR 50.55 initial notification for a significant breakdown in the Quality Assurance (QA) Program of Chicago Bridge & Iron (CB&I), an agent for the Licensee of the V. C. Summer 2 & 3 Construction Project. In August 2014, deviations were found in sub-modules CA03-06, -08, and -09 for the Vogtle 3 Construction Project, which initiated the discovery and evaluation processes for both Part 21 and 10 CFR 50.55. The conditions were determined to be not reportable by CB&I under 10 CFR 21, but an evaluation of the root cause analysis results concluded that a significant QA program breakdown had occurred that could have produced a defect. No defect has been identified. This initial notification is being made in accordance with 10 CFR 50.55(e)(4)(iii) and 10 CFR 50.55(e)(5)(i). The NRC Resident Inspector has been notified.".
ENS 507989 February 2015 11:36:00VogtleNRC Region 2W-AP1000This is a 10 CFR 50.55 initial notification for a significant breakdown in the Quality Assurance (QA) Program of Chicago Bridge & Iron (CB&I), an agent for the Licensee of the Vogtle 3&4 Construction Project. In August 2014, deviations were found in sub-modules CA03-06, -08, and -09, which initiated the discovery and evaluation processes for both Part 21 and 10 CFR 50.55 . The conditions were determined to be not reportable by CB&I under 10 CFR 21, but an evaluation of the root cause analysis results concluded that a significant QA program breakdown had occurred that could have produced a defect. No defect has been identified. This initial notification is being made in accordance with 10 CFR 50.55 (4)(iii) and 10 CFR 50.55 (5)(i). The NRC Resident Inspector will be notified.
ENS 5057429 October 2014 14:08:00VogtleNRC Region 2W-AP1000A contractor employee had a confirmed positive for alcohol during a for-cause fitness-for-duty test. The contractor employee's unescorted access to the plant has been terminated. The licensee notified the NRC Resident Inspector.
ENS 5044210 September 2014 11:51:00SummerNRC Region 2W-AP1000This is a 10CFR50.55(e) initial notification for a significant breakdown in the Quality Assurance (QA) program of Chicago Bridge & Iron (CB&I) Lake Charles facility, a sub-supplier of CB&I. CB&I Lake Charles supplies safety-related structural sub modules for the Virgil C. Summer Units 2 and 3 construction project. In March, 2014, CB&I Lake Charles issued a root cause analysis report for welding program deviations associated with the fabrication of sub-modules being supplied to domestic AP1000 construction projects. An evaluation of the root cause analysis results concluded that a significant QA program breakdown had occurred that could have produced a defect. No defect has been identified. This initial notification is being made in accordance with 10CFR50.55(e)(4)(iii) and 10CFR50.55(e)(5)(i). The licensee notified the NRC Resident Inspector.
ENS 5044110 September 2014 11:24:00VogtleNRC Region 2W-AP1000This is a 10CFR50.55(e) initial notification for a significant breakdown in the Quality Assurance (QA) Program of Chicago Bridge & Iron (CB&I) Lake Charles facility, a sub-supplier of CB&I. CB&I Lake Charles supplies safety-related structural sub-modules for the Vogtle 3 and 4 construction project. In March, 2014, CB&I Lake Charles issued a root cause analysis report for welding program deviations associated with the fabrication of sub-modules being supplied to domestic AP1000 construction projects. An evaluation of the root cause analysis results concluded that a significant QA program breakdown had occurred that could have produced a defect. No defect has been identified. This initial notification is being made in accordance with 10CFR50.55(e)(4)(iii) and 10CFR50.55(e)(5)(i). The licensee notified the NRC Resident Inspector.
ENS 5022625 June 2014 11:48:00VogtleNRC Region 2W-AP1000A non-licensed contract employee had a confirmed positive for a controlled substance during a random fitness-for-duty test. The employee's plant access has been terminated. The NRC Resident Inspector has been notified.
ENS 501632 June 2014 16:47:00VogtleNRC Region 2W-AP1000A non-licensed contract employee supervisor had a confirmed positive result for a controlled substance. The employee's access to the plant has been terminated. The licensee has notified the NRC Senior Resident Inspector.
ENS 498827 March 2014 15:26:00SummerNRC Region 2W-AP1000A construction supervisor failed a random fitness-for-duty test. The employee's access to the plant has been revoked. The NRC Resident Inspector has been notified. Notified R2DO (Rose).
ENS 495952 December 2013 13:52:00VogtleNRC Region 2W-AP1000This is a 10 CFR 50.55(e) initial notification for a significant breakdown in the Quality Assurance (QA) Program of Chicago Bridge & Iron (CB&I) Lake Charles facility, a sub-supplier of CB&I. CB&I Lake Charles supplies safety-related structural sub-modules for the Vogtle 3 & 4 construction project. In September 2013, CB&I Lake Charles issued a root cause analysis report for deviations associated with sub-modules being supplied to domestic AP1000 construction projects. An evaluation of the root cause analysis results concluded that a significant QA program breakdown had occurred that could have produced a defect. No defect has been identified. This initial notification is being made in accordance with 10 CFR 50.55(e)(4)(iii) and 10 CFR 50.55(e)(5)(i). The licensee will notify the NRC Resident Inspector. Reference similar Summer Event (EN#49582).
ENS 4958226 November 2013 13:44:00SummerNRC Region 2W-AP1000This is a 10 CFR 50.55(e) initial notification for a significant breakdown in the Quality Assurance (QA) program of Chicago Bridge & Iron (CB&I) Lake Charles facility, a sub-supplier of CB&I. CB&I Lake Charles supplies safety-related structural sub modules for the Virgil C. Summer Units 2 & 3 construction project. In September 2013, CB&I Lake Charles issued a root cause analysis report for deviations associated with sub-modules being supplied to domestic AP1000 construction projects. An evaluation of the root cause analysis results concluded that a significant QA program breakdown had occurred that could have produced a defect. No defect has been identified. This initial notification is being made in accordance with 10 CFR 50.55(e)(4)(iii) and 10 CFR 50.55(e)(5)(i). The licensee will notify the NRC Resident Inspector.
ENS 495157 November 2013 16:05:00SummerNRC Region 2W-AP1000On November 7, 2013, at 0826 EST, an investigation determined that a Fitness for Duty (FFD) policy violation as defined in 10 CFR 26.417(b)(1) had occurred in the Chicago Bridge & Iron (CB&I) FFD Program at the South Carolina Electric & Gas (SCE&G) V.C. Summer Units 2 and 3 construction site. On November 5, 2013, a CB&I contractor vending machine service employee, in the presence of a CB&I contract security officer, used another contractor vending machine service employee's badge to gain access to the construction site after his badge did not allow access due to being inactivated in an effort to facilitate a random FFD test. The contractor vending machine service employee was escorted out of the construction site. Subsequent investigation uncovered that it was a practice within the contractor vending machine service company to maintain an employee's badge in the vehicle and periodically use it to ensure the badge was not deactivated. The contractor vending machine service company employee badges have been deactivated pending further investigation. The individuals involved in this event are under 10 CFR 26, Subpart K, and do not perform safety or security related work. This event has been entered in the CB&I and SCE&G Corrective Action Programs for resolution and development of appropriate corrective actions. SCE&G is providing this notification in accordance with 10 CFR 26.417(b)(1). The NRC Resident Inspector has been notified.
ENS 492539 August 2013 08:21:00SummerNRC Region 2W-AP1000A contractor supervisor tested positive for alcohol on a follow-up fitness for duty screening. The individual's construction site access was revoked. The Unit 2/3 Resident Inspector has been notified.
ENS 489912 May 2013 11:27:00SummerNRC Region 2W-AP1000On May 2, 2013, a non-licensed employee supervisor tested positive for alcohol on a random fitness for duty test. The individuals site access has been terminated. The licensee notified the NRC Resident Inspectors.
ENS 4891010 April 2013 16:44:00SummerNRC Region 2W-AP100050.55(e) initial notification for failure to comply with requirements of 10 CFR 50 Appendix B, Criterion VII for procurement of safety-related components associated with AP1000 Nuclear Power Plant construction by CB&I (formerly Shaw Nuclear). This 50.55(e) initial notification addresses a failure to comply by CB&I, an agent of South Carolina Electric & Gas (SCE&G) for Virgil C. Summer 2 & 3, to meet the requirements of Appendix B, Criterion VII. It is concluded that the QA programmatic issues, as identified by the root cause analysis associated with NRC violation 05200025/2012-004-02, could have produced a defect and this condition is reportable in accordance with 10 CFR 50.55(e)(3)(iii)(C). The root cause of the programmatic procurement problems was that the existing Shaw Nuclear procurement and quality oversight and inspection program did not include a sufficiently strategic, integrated, and graded approach to assure the required quality of material, equipment, and services. This notification closes the interim report submitted on February 4, 2013 by SCE&G. This 50.55(e) initial notification is being submitted pursuant to the requirements of 10 CFR 50.55(e)(3)(iii)(C). The licensee has notified the NRC Resident Inspector.
ENS 4890610 April 2013 09:47:00VogtleNRC Region 2W-AP100050.55(e) initial notification for failure to comply with requirements of 10 CFR 50 Appendix B, Criterion VII for procurement of safety-related components associated with AP1000 Nuclear Power Plant construction by CB&I (formerly Shaw Nuclear). This 50.55(e) initial notification addresses a failure to comply by CB&I, an agent of Southern Company for Vogtle 3&4, to meet the requirements of Appendix B, Criterion VII. It is concluded that the QA programmatic issues, as identified by the root cause analysis associated with NRC violation 05200025/2012-004-02, could have produced a defect and this condition is reportable in accordance with 10 CFR 50.55(e)(3)(iii)(C). The root cause of the programmatic procurement problems was that the existing Shaw Nuclear procurement and quality oversight and inspection program did not include a sufficiently strategic, integrated, and graded approach to assure the required quality of material, equipment, and services. This notification closes the interim report submitted on February 4, 2013 by Southern Company. This 50.55(e) initial notification is being submitted pursuant to the requirements of 10 CFR 50.55(e)(3)(iii)(C). The licensee has notified the NRC Resident Inspector.
ENS 485615 December 2012 13:03:00SummerNRC Region 2W-AP1000This is a non-emergency 4-hour informational notification to the NRC in accordance with the reporting requirements of 10 CFR 50.72(b)(2)(xi). On December 5, 2012 at approximately 0810 hours EST, a contract employee within the construction area suffered a non-work related personal medical event. The individual was transported offsite and was pronounced deceased at a local hospital. OSHA was notified at 1134 EST pursuant to the requirements of 29 CFR 1904.39. There was no radioactive contamination involved in this event. South Carolina Electric and Gas Company has not observed any heightened media interest as a result of this event. No other notifications to government agencies are expected. The NRC Resident Inspector has been notified.
ENS 4813626 July 2012 14:27:00VogtleNRC Region 2W-AP1000A non-licensed employee supervisor had a confirmed positive for alcohol during a follow-up fitness for duty test. The employee's unescorted access to the plant has been terminated. Contact the Headquarters Operations Officer for additional details. The licensee notified the NRC Resident Inspector.
ENS 4776523 March 2012 14:33:00VogtleNRC Region 2W-AP1000

On March 9, 2012, Shaw's Vogtle 3&4 Construction Contractor FFD program manager notified SNC (Southern Nuclear Operating Company) FFD program manager of his discovery of anomalies in their random pool while preparing to perform the weekly random pool generation. At that time, approximately 20 people were identified as not being in the pool that had active badges. Corrective actions were implemented to update the pool and provide additional verification of any changes made to the pool. Subsequently discussions with licensing resulted in the conclusion that there was not an indication that there was a programmatic issue and thus was reportable under a 30 day report to the NRC. The NRC was informed of this decision and has been at Vogtle collecting data regarding this event. Since that time, Shaw has been checking past months to determine the extent of condition. On March 22, at 21:01, Shaw notified SNC that the October - December results of personnel who had active badges but was not in the pool was significantly higher than the January through March results, developed earlier. On the basis of this information, SNC has determined that this now rises to the level of a programmatic vulnerability and is subject to a 24-hour report to the NRC. SNC is providing this notification under the provisions of 10 CFR 26.719(b)(4) and 26.417(b)(1) as a discovered vulnerability of the FFD program. The licensee informed the NRC Resident Inspectors.

  • * * UPDATE FROM MAHAN TO HUFFMAN AT 1700 EDT ON 3/26/12 * * *

The licensee noted that this event is also being reported under 10 CFR 26.417(b)(1). R2DO (Haag) has been notified.

ENS 477237 March 2012 16:00:00VogtleNRC Region 2W-AP1000On March 01, 2012, it was discovered that a (Contractor) program manager intentionally failed to implement a procedure change as instructed by management. An initial investigation has determined that interim compensatory actions were in place prior to this pending procedural change. The involved manager's access authorization has been revoked. Southern Nuclear Operating Company, Inc. (SNC) was notified by (the Contractor) of this discovery on March 06, 2012 at 19:00 EST. SNC is providing this notification under the provisions of 10 CFR 26.719(b)(3) as an intentional act that casts doubt on the integrity of the FFD program. At the time of this report, no regulatory barriers for individuals assigned to perform duties that require them to be subject to the FFD program have been breached regarding this event. The licensee notified the NRC Resident Inspector.
ENS 4708722 July 2011 12:18:00VogtleNRC Region 2W-AP1000A contractor supervisor had a confirmed positive for alcohol during a random fitness-for-duty test. The individual's access to the site has been terminated. Contact the Headquarters Operations Officer for additional details. The licensee informed the NRC Resident Inspector.
ENS 4655820 January 2011 15:25:00VogtleNRC Region 2W-AP1000A discovered vulnerability in the Fitness-For-Duty (FFD) program has resulted in contractor personnel being granted unescorted access to Vogtle 3&4 construction site without meeting all the requirements of the FFD Program. Contact the Headquarters Operations Officer for more details. The NRC Resident Inspector has been notified.
ENS 4633514 October 2010 16:55:00VogtleNRC Region 2W-AP1000A non-licensed contract employee supervisor had a confirmed positive for alcohol during a random fitness-for-duty test. The employee's unescorted access to the plant has been terminated. Contact the Headquarters Operations Officer for additional details. The licensee has notified the NRC Resident Inspector.