ML20217N552 | 21 October 1999 | Forwards Operator Licensing Exam Rept 50-331/99-302(OL) for Tests Administered During Wk of 990920.Six Applicants Passed All Sections of Exam & Were Issued Operating Licenses | |
ML20217H892 | 18 October 1999 | Forwards SER Accepting Eight of Licensee Relief Requests, NDE-R001,(Part a & B),NDE-R027,NDE-R028,NDE-R029,NDE-R030, NDE-R032 & NDE-R035,one Request Relief NDE-R036,denied & Relief Request NDE-R034 Unnecessary | |
ML20217F480 | 14 October 1999 | Provides Individual Exam Results for Applicants Who Took Sept 1999 Initial License Exam.Informs That Info Considered Proprietary & That Listed Info,Supplements & Exam Rept Will Be Issued Shortly | |
NG-99-1405, Informs That Util Has Completed Addl Review to Ensure That All Related Requirements for Repair/Replacements Have Been Addressed,Per Util Requesting Approval of Several Inservice Insp Relief Request | 8 October 1999 | Informs That Util Has Completed Addl Review to Ensure That All Related Requirements for Repair/Replacements Have Been Addressed,Per Util Requesting Approval of Several Inservice Insp Relief Request | |
NG-99-1383, Forwards Response to NRC 990930 RAI on TS Change Request TSCR-010 Re Excess Flow Check Valve SRs | 8 October 1999 | Forwards Response to NRC 990930 RAI on TS Change Request TSCR-010 Re Excess Flow Check Valve SRs | Maintenance Rule Program |
ML20217F722 | 7 October 1999 | Forwards Insp Rept 50-331/99-11 on 990820-0930.No Violations Noted | Power change |
ML20212L041 | 5 October 1999 | Informs That Privacy Info Identified in Util Re Duane Arnold Energy Center Emergency Telephone Book,Rev 61 Will Be Withheld from Public Disclosure Pursuant to 10CFR2.790(a)(6) & Section 103(b) of Atomic Energy Act | |
NG-99-1358, Forwards DAEC plant-specific Response to 990927 RAI Re TS Change Request on Excess Flow Check Valve Surveillance requirements.TSTF-334,included | 5 October 1999 | Forwards DAEC plant-specific Response to 990927 RAI Re TS Change Request on Excess Flow Check Valve Surveillance requirements.TSTF-334,included | Incorporated by reference Maintenance Rule Program |
NG-99-1378, Clarifies TS Change Requests for Revised Safety Limit Min Critical Power Ratio.Approval of 990510 & 0716 Application for Amends to License DPR-49 Requested Prior to Scheduled Start of Cycle 17 & Effective Date No Earlier than 991022 | 4 October 1999 | Clarifies TS Change Requests for Revised Safety Limit Min Critical Power Ratio.Approval of 990510 & 0716 Application for Amends to License DPR-49 Requested Prior to Scheduled Start of Cycle 17 & Effective Date No Earlier than 991022 | Minimum Critical Power Ratio |
NG-99-1327, Forwards IST Relief Request VR-24 Re Excess Flow Check Valve Test Frequency,Per 10CFR50.55a(a)(3)(i),for NRC Approval | 4 October 1999 | Forwards IST Relief Request VR-24 Re Excess Flow Check Valve Test Frequency,Per 10CFR50.55a(a)(3)(i),for NRC Approval | |
ML20212J876 | 30 September 1999 | Forwards RAI Re Util 990412 Request to Revise Duane Arnold Energy Ctr TS SR 3.6.1.3.7 to Allow Representative Sample of Reactor Instrumentation Line EFCV to Be Tested Every 24 Months,Instead of Testing Each EFCV Every 24 Months | |
ML20217A933 | 30 September 1999 | Informs That NRC Plan to Conduct Addl Insp by Resident Inspectors Beyond Core Insp Program Over Next 7 Months to Assess Preparation for Implementation of Refuel Outage Activities.Historical Listing of Plant Issues Encl | |
ML20212H212 | 27 September 1999 | Forwards Request for Addl Info Re 990412 Licensee Request to Revise DAEC TS SR 3.6.1.3.7 to Allow Representative Sample of Reactor Instrumentation Line EFCV to Be Tested Every 24 Months,Instead of Testing Each EFCV Every 24 Months | Incorporated by reference |
ML20212H215 | 22 September 1999 | Forwards Amend 228 to License DPR-49 & Safety Evaluation. Amend Revises DAEC TS SR 3.4.3.1, Safety/Relief Valves & Safety Valves | |
NG-99-1262, Forwards License Renewal Application for G Thullen,License SOP 30232-2.Thullen Has Completed Requalification Program for Daec.Encls Withheld,Per 10CFR2.790(a)(6) | 20 September 1999 | Forwards License Renewal Application for G Thullen,License SOP 30232-2.Thullen Has Completed Requalification Program for Daec.Encls Withheld,Per 10CFR2.790(a)(6) | |
NG-99-1214, Forwards Voluntary Info Requested in Response to NRC Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Exams, Re Estimated Number of Operator Licensing Exams & Applicants for Years 2000 Through 2003 | 15 September 1999 | Forwards Voluntary Info Requested in Response to NRC Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Exams, Re Estimated Number of Operator Licensing Exams & Applicants for Years 2000 Through 2003 | |
NG-99-1278, Forwards Corrected TS Page 3.3-52 Re TS Change Request TSCR-003,removing Requirements for Hpcis & Rcics Isolation Manual Initiation Instrumentation.Page Indicates Deletion of Condition G as Well as or G from Condition H | 15 September 1999 | Forwards Corrected TS Page 3.3-52 Re TS Change Request TSCR-003,removing Requirements for Hpcis & Rcics Isolation Manual Initiation Instrumentation.Page Indicates Deletion of Condition G as Well as or G from Condition H | |
ML20212A871 | 14 September 1999 | Informs That 990716 Application Which Submitted Affidavit & Attachment Re Addl Info Re Cycle Specific SLMCPR for Plant Cycle 17, June 1999,marked Proprietary,Will Be Withheld from Public Disclosure,Per 10CFR2.790(b)(5) | |
NG-99-1249, Requests Exemption from Certain Requirements Applicable to ECCS Evaluation Models Performed IAW App K to 10CFR50 for DAEC | 10 September 1999 | Requests Exemption from Certain Requirements Applicable to ECCS Evaluation Models Performed IAW App K to 10CFR50 for DAEC | Probabilistic Risk Assessment Incorporated by reference Exemption Request |
NG-99-1252, Informs That There Is No Longer Need for Any Waiver Associated with Senior Operator License Application for MR Pettengill Due to Completion of All Five Manipulations | 9 September 1999 | Informs That There Is No Longer Need for Any Waiver Associated with Senior Operator License Application for MR Pettengill Due to Completion of All Five Manipulations | |
NG-99-1192, Forwards marked-up Copies of Affected Tables & Ref Matl Which Supports Changes Re DAEC Reactor Vessel Integrity Database (Rvid),As Requested in GL 92-01,rev 1,suppl 1, Reactor Vessel Structural Integrity | 8 September 1999 | Forwards marked-up Copies of Affected Tables & Ref Matl Which Supports Changes Re DAEC Reactor Vessel Integrity Database (Rvid),As Requested in GL 92-01,rev 1,suppl 1, Reactor Vessel Structural Integrity | |
ML20211M562 | 2 September 1999 | Forwards Insp Rept 50-331/99-08 on 990712-16 & 0810-12.No Violations Noted.Insp Consisted of Review of Source Term Reduction & Integration of ALARA Into Work Planning & Execution,Calibration & Maint | |
NG-99-1216, Requests Waiver to Allow MR Pettengill to Participate in Upcoming Senior Operator Examination on 990920.Util Intends to Ensure That Pettengill Completes All Five Required Manipulations as Soon as Possible | 1 September 1999 | Requests Waiver to Allow MR Pettengill to Participate in Upcoming Senior Operator Examination on 990920.Util Intends to Ensure That Pettengill Completes All Five Required Manipulations as Soon as Possible | |
NG-99-1182, Forwards Certified License Applications IAW Provisions of Examiner Standard (ES)-201 for SA Arebaugh,Sd Bahnsen,Jd Kalamaja,Ja Miell,Bd Musel & MR Pettengill.Encls to Ltr Withheld Per 10CFR2.790(a)(6) | 31 August 1999 | Forwards Certified License Applications IAW Provisions of Examiner Standard (ES)-201 for SA Arebaugh,Sd Bahnsen,Jd Kalamaja,Ja Miell,Bd Musel & MR Pettengill.Encls to Ltr Withheld Per 10CFR2.790(a)(6) | |
ML20211M581 | 31 August 1999 | Forwards Proprietary Version of Rev 61 to DAEC Emergency Telephone Book. Proprietary Encl Withheld | |
NG-99-1205, Forwards FFD Rept of Program Performance Info for DAEC During Six Month Period from 990101-0630 | 30 August 1999 | Forwards FFD Rept of Program Performance Info for DAEC During Six Month Period from 990101-0630 | Fitness for Duty |
ML20211F783 | 26 August 1999 | Forwards Insp Rept 50-331/99-09 on 990708-0819.Violation Re Failure to Log Entry Into TS Limiting Condition for Operation When Power Lost to Drywell Sump Pump Level Switches,Noted & Being Treated as NCV | Downpower |
ML20210V123 | 17 August 1999 | Forwards Insp Rept 50-331/99-10 on 990802-06.No Violations Noted.Insp Examined Activities Conducted Under Emergency Preparedness Program | |
ML20211A873 | 16 August 1999 | Ack Receipt of 990212 & 0402 Ltrs,Which Transmitted Changes Identified as Revs 39 & 40 to DAEC Security Plan,Submitted Under Provisions of 10CFR50.54(p).NRC Review Comments for Subject Plans,Encl | |
NG-99-1146, Forwards Validated Exam Matls for Initial License Exam to Be Administered at Facility,Wk of 990920,IAW Guidelines in NUREG-1021,Rev 8,dtd April 1999 | 16 August 1999 | Forwards Validated Exam Matls for Initial License Exam to Be Administered at Facility,Wk of 990920,IAW Guidelines in NUREG-1021,Rev 8,dtd April 1999 | Half scram Stroke time Time to boil Squib Locked High Radiation Area B.5.b Double blade guide Job Performance Measure Operability Determination |
NG-99-1126, Submits Rept Re Changes in Calculated Peak Cladding Temp for Daec,Iaw 10CFR50.46(a)(3)(ii),guidance in NRC Info Notice 97-015 & Suppl 1.Rept Covers Period from Last Annual Rept Through June 1999 | 13 August 1999 | Submits Rept Re Changes in Calculated Peak Cladding Temp for Daec,Iaw 10CFR50.46(a)(3)(ii),guidance in NRC Info Notice 97-015 & Suppl 1.Rept Covers Period from Last Annual Rept Through June 1999 | |
NG-99-1050, Informs That Recommendation in BWRVIP-18,incorrectly Interpreted During RFO 15 & 25% of Creviced Welds Examined. All of Inspected Creviced Welds Were Found to Be Acceptable | 28 July 1999 | Informs That Recommendation in BWRVIP-18,incorrectly Interpreted During RFO 15 & 25% of Creviced Welds Examined. All of Inspected Creviced Welds Were Found to Be Acceptable | |
ML20210L831 | 27 July 1999 | Forwards Insp Rept 50-331/99-05 on 990601-0701.Violations Noted.Insp Included Assessment & Evaluation of Engineering Support,Design Change & Mod Activities Including 10CFR50.59 Safety Evaluations,Applicability Reviews & C/As | Temporary Modification |
ML20210E978 | 26 July 1999 | Informs That Info Submitted by Ltr (Nep 99-0067), Ies Utilities,Inc,Will Be Withheld from Public Disclosure, Per 10CFR2.790(a)(6) | |
ML20210E143 | 22 July 1999 | Provides Summary of 990715 Meeting with Alliant Utilities & Duane Arnold Energy Ctr Mgt Re Recent Plant Performance Review Issued by NRC for Duane Arnold Energy Ctr.Associated Meeting Summary & Alliant Utilities Meeting Handout Encl | Temporary Modification Systematic Assessment of Licensee Performance |
NG-99-0993, Submits Amend to Commitment Contained in Util 990623 Response to NRC RAI Re Third ten-year Interval ISI Relief Requests.Licensee Now Commits to Meeting Code Requirement of Asme,Section XI,1989 Edition,Paragragh IWB/IWC-2420(a) | 21 July 1999 | Submits Amend to Commitment Contained in Util 990623 Response to NRC RAI Re Third ten-year Interval ISI Relief Requests.Licensee Now Commits to Meeting Code Requirement of Asme,Section XI,1989 Edition,Paragragh IWB/IWC-2420(a) | |
ML20210B716 | 20 July 1999 | Forwards Audit Rept on Y2K Contingency Planning Program at Duane Arnold Energy Center Conducted on 990615-16 as follow-up to NRC GL 98-01 | |
ML20210B527 | 16 July 1999 | Forwards Insp Rept 50-331/99-07 on 990526-0707.Two Violations Being Treated as Noncited Violations | |
NG-99-0989, Provides Estimate of Number of Licensing Requests That Will Be Submitted in FY00 & 01,in Response to Administrative Ltr 99-02, Operating Reactor Licensing Action Estimates | 16 July 1999 | Provides Estimate of Number of Licensing Requests That Will Be Submitted in FY00 & 01,in Response to Administrative Ltr 99-02, Operating Reactor Licensing Action Estimates | |
ML20209E840 | 13 July 1999 | Discusses Completion of NRC GL 97-04, Assurance of Sufficient Net Positive Suction Head for Emergency Core Cooling & Containment Heat Removal Pumps for Plant | |
NG-99-0990, Forwards License Renewal Applications for Ta Zimmerman SOP 30772 & Ba Westcot SOP 30771.Encls Withheld,Per 10CFR2.790 | 13 July 1999 | Forwards License Renewal Applications for Ta Zimmerman SOP 30772 & Ba Westcot SOP 30771.Encls Withheld,Per 10CFR2.790 | |
ML20209G499 | 12 July 1999 | Forwards Insp Rept 50-331/98-05 on 990622-24.No Violations Noted | Nondestructive Examination |
ML20207H674 | 6 July 1999 | Forwards Operating Licensing Exam Rept 50-331/99-301(OL) on 990525.Staff Administered Written Exam to One Reactor Operator Applicant Previously Demonstrating Unsatisfactory Results During Jul 1998 Exam | |
NG-99-0928, Forwards Response to NRC 980902 Comments Re Design Basis NPSH Analyses as Requested by GL 97-04 | 1 July 1999 | Forwards Response to NRC 980902 Comments Re Design Basis NPSH Analyses as Requested by GL 97-04 | |
NG-99-0859, Responds to NRC Request for Info Re Y2K Readiness at Nuclear Power Plants,Per GL 98-01.Y2K Readiness Disclosure for Plant Encl | 25 June 1999 | Responds to NRC Request for Info Re Y2K Readiness at Nuclear Power Plants,Per GL 98-01.Y2K Readiness Disclosure for Plant Encl | Backfit |
ML20212J452 | 25 June 1999 | Discusses Closure of TAC MA1188 Re Response to RAI to GL 92-01,rev 1,suppl 1, Reactor Vessel Structural Integrity | |
NG-99-0880, Informs That Util Commits to Repeating Newly Established Sequence of Component Exams During Successive Insp Intervals for NDE-R035,in Response to NRC Re Inservice Insp Relief Requests | 23 June 1999 | Informs That Util Commits to Repeating Newly Established Sequence of Component Exams During Successive Insp Intervals for NDE-R035,in Response to NRC Re Inservice Insp Relief Requests | |
ML20196F953 | 21 June 1999 | Forwards Proprietary Rev 60 to Duane Arnold Energy Center Emergency Telephone Book.Proprietary Info Withheld | |
ML20196A143 | 18 June 1999 | Confirms Discussion Between Members of Staffs to Have Meeting on 990715 at Training Ctr at Duane Arnold Energy Ctr to Discuss Results of Plant Performance Review Process | |
ML20212J054 | 17 June 1999 | Responds to Requesting That NRC Staff ...Allow BWR Plants Identified to Defer Weld Overlay Exams Until March 2001 or Until Completion of NRC Staff Review & Approval of Proposed Generic Rept,Whichever Comes First | Weld Overlay |