RS-13-119, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)

From kanterella
Jump to navigation Jump to search

First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)
ML13241A282
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 08/28/2013
From: Kaegi G
Exelon Generation Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
EA-12-049, RS-13-119
Download: ML13241A282 (108)


Text

7 ti Order No. EA-12-049 RS-13-119 August 28,2013 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Dresden Nuclear Power Station, Units 2 and 3 Renewed Facility Operating License Nos. DPR-19 and DPR-25 NRC Docket Nos. 50-237 and 50-249

Subject:

First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for 8eyond-Design-8asis External Events (Order Number EA-12-049)

References:

1. NRC Order Number EA-12-049, " Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for 8eyond-Design-8asis External Events," dated March 12,2012
2. NRC Interim Staff Guidance JLD-ISG-2012-01, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for 8eyond-Design-8asis External Events," Revision 0, dated August 29,2012
3. NEI 12-06, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide,"

Revision 0, dated August 2012

4. Exelon Generation Company, LLC's Initial Status Report in Response to March 12,2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for 8eyond-Design-8asis External Events (Order Number EA-12-049), dated October 25, 2012
5. Exelon Generation Company, LLC Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for 8eyond-Design-8asis External Events (Order Number EA-12-049), dated February 28,2013 (RS-13-020)

On March 12, 2012, the Nuclear Regulatory Commission ("NRC" or "Commission") issued an order (Reference 1) to Exelon Generation Company, LLC (EGC). Reference 1 was immediately effective and directs EGC to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event. Specific requirements are outlined in of Reference 1.

U.S. Nuclear Regulatory Commission Integrated Plan Report to EA-12-049 August 28,2013 Page 2 Reference 1 required submission of an initial status report 60 days following issuance of the final interim staff guidance (Reference 2) and an overall integrated plan pursuant to Section IV, Condition C. Reference 2 endorses industry guidance document NEI 12-06, Revision 0 (Reference 3) with clarifications and exceptions identified in Reference 2. Reference 4 provided the EGC initial status report regarding mitigation strategies. Reference 5 provided the Dresden Nuclear Power Station, Units 2 and 3 overall integrated plan.

Reference 1 requires submission of a status report at six-month intervals following submittal of the overall integrated plan. Reference 3 provides direction regarding the content of the status reports. The purpose of this letter is to provide the first six-month status report pursuant to Section IV, Condition C.2, of Reference 1, that delineates progress made in implementing the requirements of Reference 1. The enclosed report provides an update of milestone accomplishments since the last status report, including any changes to the compliance method, schedule, or need for relief and the basis, if any.

This letter contains no new regulatory commitments. If you have any questions regarding this report, please contact David P. Helker at 610-765-5525.

I declare under penalty of perjury that the foregoing is true and correct. Executed on the 28th day of August 2013.

Respectfully submitted, Gien~;/:-~

Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC

Enclosure:

1. Dresden Nuclear Power Station, Units 2 and 3 First Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events cc: Director, Office of Nuclear Reactor Regulation NRC Regional Administrator - Region III NRC Senior Resident Inspector - Dresden Nuclear Power Station, Units 2 and 3 NRC Project Manager, NRR - Dresden Nuclear Power Station, Units 2 and 3 Ms. Jessica A. Kratchman, NRR/JLD/PMB, NRC Mr. Robert J. Fretz, Jr, NRR/JLD/PMB, NRC Mr. Robert L. Dennig, NRR/DSS/SCVB, NRC Mr. Eric E. Bowman, NRR/DPR/PGCB, NRC Illinois Emergency Management Agency - Division of Nuclear Safety

Enclosure Dresden Nuclear Power Station, Units 2 and 3 First Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (16 pages)

Enclosure Dresden Nuclear Power Station, Units 2 and 3 First Six Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events 1 Introduction Dresden Nuclear Power Station, Units 2 and 3 (Dresden) developed an Overall Integrated Plan (Reference 1 in Section 8), documenting the diverse and flexible strategies (FLEX), in response to Reference 2. This enclosure provides an update of milestone accomplishments since submittal of the Overall Integrated Plan, including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any.

2 Milestone Accomplishments None 3 Milestone Schedule Status The following provides an update to Attachment 2 of the Overall Integrated Plan. It provides the activity status of each item, and whether the expected completion date has changed. The dates are planning dates subject to change as design and implementation details are developed.

Original Target Activity Status Completion Date

{Include date changes in this column}

Submit 60 Day Status Report Complete Submit Overall Integrated Complete Implementation Plan Contract with RRC Complete Submit 6 month updates August 2013 Update 1 Complete with this submittal February 2014 Update 2 Not Started August 2014 Update 3 Not Started February 2015 Update 4 Not started August 2015 Update 5 Not Started Page 1 of 16

Dresden Nuclear Power Station, Units 2 and 3 First Six Month Status Report for the Implementation of FLEX August 28, 2013 Original Target Activity Status Completion Date

{Include date changes in this column}

February 2016 Update 6 Not Started August 2016 Update 7 Not Started Submit Completion Report Unit 2 Unit 3 Modification Development Oct 2014 Sept 2015 Phase 1 modifications Started Oct 2014 Sept 2015 Phase 2 modifications Started Oct 2014 Sept 2015 Phase 3 modifications Not Started Unit 2 Unit 3 Modification Implementation Nov 2015 Nov 2016 Phase 1 modifications Not Started Nov 2015 Nov 2016 Phase 2 modifications Not started Nov 2015 Nov 2016 Phase 3 modifications Not Started Procedure development Nov 2015 Strategy procedures Not Started Nov 2015 Validate Strategy Procedures Not Started (NEI 12-06, Sect. 11.4.3)

Nov 2015 Maintenance procedures Not Started Jul 2015 Staffing analysis Not Started Nov 2015 Storage Plan and construction Started Nov 2015 FLEX equipment acquisition Started Nov 2015 Training completion Not Started Jul 2015 Regional Response Center Started Operational Nov 2015 Unit 2 Implementation date Not Started Nov 2016 Unit 3 Implementation date Not Started Page 2 of 16

Dresden Nuclear Power Station, Units 2 and 3 First Six Month Status Report for the Implementation of FLEX August 28, 2013 4 Changes to Compliance Method A BWROG review of Reactor Core Isolation Cooling (RCIC) operation with elevated suction temperatures was documented in a GE Task Report (GE Task Report 0000-0143-0382-R0, RCIC System Operation in Prolonged Station Blackout - Feasibility Study, January 2012). The review indicated RCIC could continue to operate up to approximately 230ºF suction temperature. While RCIC and HPCI are similar it could not be determined if the results of the RCIC Study could be applied to HPCI. Therefore, it is now assumed HPCI will fail when Suppression Pool temperature reaches 140ºF. Utilization of this assumption and the MAAP results indicates approximately 2.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> of continuous HPCI operation is available in Phase 1. As a result of the revised assumption, the strategies for FLEX implementation were changed. The changes were large enough that the Original Integrated Plan was modified to describe the changes and the associated impacts. See Attachment 1 for a revised Sequence of Event Timeline. The entire revised FLEX Integrated Plan for Dresden Station (February 2013 FLEX Integrated Plan (REVISED August 28, 2013)) is attached to this enclosure.

5 Need for Relief/Relaxation and Basis for the Relief/Relaxation Dresden Nuclear Power Station expects to comply with the order implementation date and no relief/relaxation is required at this time.

6 Open Items from Overall Integrated Plan and Draft Safety Evaluation The following tables provide a summary of the open items documented in the Overall Integrated Plan or the Draft Safety Evaluation (SE) and the status of each item.

Section Reference Overall Integrated Plan Open Item Status Sequence of Events (page 5-6) The times to complete actions in the Not Started Events Timeline are based on operating judgment, conceptual designs, and current supporting analyses. The final timeline will be time validated once detailed designs are completed and procedures developed.

Page 3 of 16

Dresden Nuclear Power Station, Units 2 and 3 First Six Month Status Report for the Implementation of FLEX August 28, 2013 Section Reference Overall Integrated Plan Open Item Status Sequence of Events (page 5) Analysis of deviations between Exelons Completed. Attachment engineering analyses and the analyses 2 of this Six Month contained in BWROG Document Status Update (Aug NEDC-33771P, GEH Evaluation of 2013)

FLEX Implementation Guidelines and documentation of results on Att. 1B, NSSS Significant Reference Analysis Deviation Table. Planned to be completed and submitted with August 2013 Six Month Update.

Sequence of Events (page 8) Initial evaluations were used to Not Started determine the fuel pool timelines.

Formal calculations will be performed to validate this information during development of the spent fuel pool cooling strategy detailed design.

Deployment Strategy (pages 8-9) Transportation routes will be developed Started from the equipment storage area to the FLEX staging areas. An administrative program will be developed to ensure pathways remain clear or compensatory actions will be implemented to ensure all strategies can be deployed during all modes of operation.

Identification of storage areas and creation of the administrative program are open items.

Programmatic Controls (pages 9- An administrative program for FLEX to Not Started

10) establish responsibilities, and testing &

maintenance requirements will be implemented.

Spent Fuel Pool Cooling Phase 2 Complete an evaluation of the spent fuel Not Started Discussion (page 46) pool area for steam and condensation.

Safety Functions Support Phase 2 Evaluate the habitability conditions for Not Started Discussion (page 57) the Main Control Room and develop a strategy to maintain habitability.

Page 4 of 16

Dresden Nuclear Power Station, Units 2 and 3 First Six Month Status Report for the Implementation of FLEX August 28, 2013 Section Reference Overall Integrated Plan Open Item Status Safety Functions Support Phase 2 Evaluate the habitability conditions for Not Started Discussion (page 57) the Auxiliary Electric Equipment Room (AEER) and develop a strategy to maintain habitability.

Draft Safety Evaluation Open Item Status N/A N/A 7 Potential Draft Safety Evaluation Impacts There are no potential impacts to the Draft Safety Evaluation identified at this time.

8 References The following references support the updates to the Overall Integrated Plan described in this enclosure.

1. Dresden Nuclear Power Stations Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated February 28, 2013 (subsequently revised Aug 28, 2013 - included as Attachment 3 to this enclosure).
2. NRC Order Number EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, dated March 12, 2012.
3. BWROG report NEDC-33771P, Rev. 1, GEH Evaluation of FLEX Implementation Guidelines Rev. 1 9 Attachments
1. Attachment 1, Revised Sequence of Events Timeline.
2. Attachment 2, NSSS Significant Reference Analysis Deviation Table (Attachment 1B of Overall Integrated Plan)
3. Attachment 3, Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013).

Page 5 of 16

Dresden Nuclear Power Station, Units 2 and 3 First Six Month Status Report for the Implementation of FLEX August 28, 2013 Attachment 1 Revised Sequence of Events Timeline Action Elapsed Action Time Remarks / Applicability item Time Constraint Y/N 1 0 Event Starts NA Plant @100% power 0 Reactor scram NA Loss of power to Reactor Protection System results in a reactor scram.

1 1 min Personnel enter DGP 02-03 and DGA 12 N These actions will provide direction for reactor control and options for loss of AC power.

2 1 min Isolation Condenser initiated for N DEOP 100 will direct pressure control (or verified operating if action based on reactor auto initiation occurs) pressure.

3 2 mins Attempt to start EDGs upon N Per FLEX event initial identification of failure to auto start. conditions the EDGs are not available.

4 3 mins Attempt to Start IC Makeup Pump for N There are no fully qualified IC Shell side makeup makeup sources for shell-side makeup.

5 5 mins Personnel dispatched to investigate EDG N Per FLEX event initial failure to start. conditions the EDGs are not available.

6 5 mins HPCI initiated for inventory control and N HPCI suction will auto reactor pressure control (or verified swap to the Torus due to operating if auto initiation occurs). CSTs being assumed lost with the FLEX event (not missile protected).

7 10 mins Attempt to start SBO DG for either Unit N Per FLEX event initial conditions the SBO DGs are not available.

1 Instructions: Provide justification if No or NA is selected in the remark column.

If yes, include technical basis discussion as required by NEI 12-06 section 3.2.1.7 Page 6 of 16

Dresden Nuclear Power Station, Units 2 and 3 First Six Month Status Report for the Implementation of FLEX August 28, 2013 Attachment 1 Revised Sequence of Events Timeline Action Elapsed Action Time Remarks / Applicability item Time Constraint Y/N 1 8 15 mins Personnel dispatched to investigate SBO N Per FLEX event initial DG failure to start. conditions the SBO DGs are not available.

9 15 mins Perform 125 VDC load shedding per N This is an immediate action DGA 13 of DGA 13 to prolong battery availability. Must be completed by 30 minutes after event initiation.

10 20 mins Isolation Condenser secured due to lack Y Per UFSAR, the IC will of shell-side makeup. operate for approximately 20 minutes without shell-side makeup. It is secured to prevent possible damage.

11 30 mins 125 and 250 VDC Load Shed Y DGA 12 Step D.13 Completed (actions identified in DGA identifies that load 03, DGA 12 and DGA 13) shedding to maintain battery availability must be completed if DC chargers are unavailable.

12 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> Control Room crew has assessed SBO N Time is reasonable and plant conditions and declares an approximation based on Extended Loss of AC Power (ELAP) operating crew assessment event. of plant conditions Personnel dispatched to FLEX strategy for supplying make-up water to the Isolation Condenser shell-side.

Personnel dispatched to FLEX strategy for supplying power to the FLEX Makeup Pump and station battery chargers Page 7 of 16

Dresden Nuclear Power Station, Units 2 and 3 First Six Month Status Report for the Implementation of FLEX August 28, 2013 Attachment 1 Revised Sequence of Events Timeline Action Elapsed Action Time Remarks / Applicability item Time Constraint Y/N 1 13 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> Complete actions for Loss of AEER N Perform DOA 5750-1 Ventilation Attachment C Step 6.

Actions can be coordinated with personnel obtaining and staging portable generators, fans, etc.

14 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> Establish natural air flow to HPCI room Y Preliminary GOTHIC by opening doors. analysis indicates opening doors at 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> will result in acceptable room temperature values to support operation of HPCI for at least 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />. HPCI room temperature remains below the isolation point during this time. HPCI operation is assumed for approximately 2.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> in Phase 1.

15 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> Complete actions for loss of Main N DOA 5750-01 actions.

Control Room Ventilation.

16 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> Defeat HPCI high temperature and flow N Ensure HPCI remains isolations available during the event.

17 2.5 FLEX strategy for supplying power to Y When the busses are hours 480 VAC busses and associated Motor energized, power will be Control Centers (MCCs) completed. available to the FLEX Makeup Pump.

This will also supply power to battery chargers.

Preliminary review indicates the batteries will remain available for at least 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> without chargers.

Page 8 of 16

Dresden Nuclear Power Station, Units 2 and 3 First Six Month Status Report for the Implementation of FLEX August 28, 2013 Attachment 1 Revised Sequence of Events Timeline Action Elapsed Action Time Remarks / Applicability item Time Constraint Y/N 1 18 2.5 FLEX pump connected and ready for Y Due to pre-staging of major hours use to support Isolation Condenser shell- components, it is side makeup. reasonable to expect the FLEX pump can be available within this time period.

19 2.5 Isolation Condenser initiated for RPV Y Complete prior to loss of hours pressure control HPCI to ensure RPV heat removal mechanism operating prior to MAAP analysis assumed HPCI loss.

20 2.5 HPCI assumed to fail due to suppression N HPCI may continue to hours pool temperature of 140°F operate above 140°F but it is not relied upon past this point and restoration of the Isolation Condenser will replace the need for HPCI in terms of RPV pressure control.

21 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> Isolate both Reactor Recirculation N Recirc loops are isolated to Loops by closing suction and discharge reduce RPV leakage. The valves sooner this is accomplished the more reactor inventory is conserved.

22 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> Run hoses from CCSW FLEX Standpipe N Establishing a makeup on 545 elevation to the SBLC Tank. source to the tank provides continued availability of a high pressure RPV makeup source.

Page 9 of 16

Dresden Nuclear Power Station, Units 2 and 3 First Six Month Status Report for the Implementation of FLEX August 28, 2013 Attachment 1 Revised Sequence of Events Timeline Action Elapsed Action Time Remarks / Applicability item Time Constraint Y/N 1 23 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> Initiate SBLC as necessary for RPV N Per MAAP analysis after level control. Recirc Loops are isolated and the Isolation Condenser is controlling reactor pressure, RPV leakage will be reduced to approximately 15 gpm at time = 3.0 hours0 days <br />0 hours <br />0 weeks <br />0 months <br />. Makeup from SBLC can be utilized to maintain RPV level above Top of Active Fuel (TAF).

24 10 Personnel dispatched to establish N Further analysis is required hours temporary ventilation to the MCR and to determine if AEER (portable fans and associated supplemental ventilation is generators). needed.

25 12 Makeup to the Spent Fuel Pools using Y EC 371913, Revision 2,:

hours FLEX pump strategy is available. Time-to-Boil Curves.,

identifies a time to boil of 9.54 hours6.25e-4 days <br />0.015 hours <br />8.928571e-5 weeks <br />2.0547e-5 months <br />, and 110.07 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> to the top of active fuel. Therefore completing the equipment line-up for initiating SFP make-up at 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> into the event ensures adequate cooling of the spent fuel is maintained.

26 24 Initial equipment from Regional N NEI 12-06 assumption.

hours Response Center becomes available.

27 24 Makeup to the RPV using FLEX N SBLC is available as a high hours Makeup pump strategy is available. pressure injection source.

Low pressure makeup from FLEX Makeup Pump will not be required before this time.

Page 10 of 16

Dresden Nuclear Power Station, Units 2 and 3 First Six Month Status Report for the Implementation of FLEX August 28, 2013 Attachment 1 Revised Sequence of Events Timeline Action Elapsed Action Time Remarks / Applicability item Time Constraint Y/N 1 28 24-72 Continue to maintain critical functions N None hours of core cooling (via IC and FLEX Pump injection), containment (via hardened vent opening) and SFP cooling (FLEX pump injection to SFP). Utilize initial RRC equipment in spare capacity.

Page 11 of 16

Dresden Nuclear Power Station, Units 2 and 3 First Six Month Status Report for the Implementation of FLEX August 28, 2013 Attachment 2 NSSS Significant Reference Analysis Deviation Table (Attachment 1B of Overall Integrated Plan)

NEDC 33771 NEDC33771P P Design Item Parameter of Interest Rev 2 Value Page Plant Applied Value Value Gap and Discussion NEDC33771P Rev 1 Section 4.5.1.1 (BWR/2/3. Mark I and EC System Assumptions) and Table 4.5.21 Appendix A are closest to the Dresden Nuclear Power Station and associated response. Differences between the GEH SHEX case and the MAAP analysis of the Dresden strategy are listed below.

Input Parameter Values 1 Core thermal power Proprietary 15 2957 MWT NA The GEH model BWR 2/3 Mark I reference information. plant has lower core thermal power rating.

Refer to report for value.

2 Primary System Leakage Proprietary 15 61 gpm NA The reference plant has 5 Recirculation information. Loops which results in a higher value for Refer to report Recirc Pump seal leakage. Dresden has 2 for value. Recirculation Loops per reactor.

3 Emergency Condenser capacity Proprietary 15 2.52E+108 Btu/hr 2.52E+ The reference plant has 2 Emergency information. 108 Condensers whereas Dresden has 1 Refer to report Btu/hr Isolation Condenser.

for value.

4 Wetwell Free Volume Proprietary 16 110,618 ft3 NA The differences in reference plant information. structural design and minor differences in Refer to report assumed parameter values at time zero for value. should have a negligible effect on the Page 12 of 16

Dresden Nuclear Power Station, Units 2 and 3 First Six Month Status Report for the Implementation of FLEX August 28, 2013 Attachment 2 NEDC 33771 NEDC33771P P Design Item Parameter of Interest Rev 2 Value Page Plant Applied Value Value Gap and Discussion 5 Wetwell airspace temperature Proprietary 16 95°F NA progression of the event after a few hours.

information.

Refer to report for value.

6 Initial Wetwell Pressure Proprietary 16 14.7 psia NA information.

Refer to report for value.

7 Intial Wetwell humidity Proprietary 16 100% NA information.

Refer to report for value.

8 Suppression Pool Volume Proprietary 16 118,630 ft3 NA information.

Refer to report for value.

9 Suppression Pool initial temperature Proprietary 16 95°F NA information.

Refer to report for value.

10 Drywell Free Volume Proprietary 16 158,236 ft3 NA information.

Refer to report for value.

Page 13 of 16

Dresden Nuclear Power Station, Units 2 and 3 First Six Month Status Report for the Implementation of FLEX August 28, 2013 Attachment 2 NEDC 33771 NEDC33771P P Design Item Parameter of Interest Rev 2 Value Page Plant Applied Value Value Gap and Discussion 11 Initial Drywell Temperature Proprietary 16 150°F NA information.

Refer to report for value.

12 Initial Drywell Pressure Proprietary 16 15.7 psia NA information.

Refer to report for value.

13 Initial Drywell Humidity Proprietary 16 50% NA information.

Refer to report for value.

Resultant Parameter Values Maximum Drywell Pressure Proprietary 40 30.3 psia at t0 + 24 62 psig information. hrs Refer to report for value.

Maximum Drywell Temperature Proprietary 40 260°F at t0 + 24 hrs 281°F information.

Refer to report for value.

Page 14 of 16

Dresden Nuclear Power Station, Units 2 and 3 First Six Month Status Report for the Implementation of FLEX August 28, 2013 Attachment 2 NEDC 33771 NEDC33771P P Design Item Parameter of Interest Rev 2 Value Page Plant Applied Value Value Gap and Discussion Maximum Wetwell Pressure Proprietary 40 28.5 psia at t0 + 24 62 psig information. hrs Refer to report for value.

Maximum Wetwell Airspace Proprietary 40 146°F at t0 + 24 hrs 281°F Temperature information.

Refer to report for value.

Maximum Suppression Pool Proprietary 40 140°F at t0 + 24 hrs N/A Temperature information.

Refer to report for value.

Page 15 of 16

Dresden Nuclear Power Station, Units 2 and 3 First Six Month Status Report for the Implementation of FLEX August 28, 2013 Attachment 3 Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

(89 pages)

Page 16 of 16

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

General Integrated Plan Elements BWR Site: Dresden Determine Applicable Input the hazards applicable to the site; seismic, external Extreme External Hazard flood, high winds, snow, ice, cold, high temps.

Describe how NEI 12-06 sections 5 - 9 were applied and Ref: NEI 12-06 section 4.0 -9.0 the basis for why the plant screened out for certain hazards.

JLD-ISG-2012-01 section 1.0 Seismic events, except soil liquefaction; external flooding; severe storms with high winds; snow, ice and extreme cold; and high temperatures) were determined to be applicable Extreme External Hazards for Dresden Nuclear Power Station (DNPS or Dresden) per the guidance of NEI 12-06 and are as follows:

Seismic Hazard Assessment:

Per the Update Final Safety Analysis Report (UFSAR)

(Reference 1, Section 1.2.2.1.5), the seismic criteria for DNPS design criteria is 0.2 g horizontal ground motion with a simultaneous vertical acceleration of 0.133 g.

It is not expected that Dresden roads would be subject to damage caused by liquefaction in a seismic event.

The Dresden UFSAR (Reference 1 Section 2.5.1.1) describes the site geology as a thin (less than 10-foot) mantle of soil, mostly glacial drift, overlying bedrock at the site.

Per the DNPS West ISFSI 10 CFR 72.212 Evaluation Report (Reference 3 Section 2.1.3), DNPS is located in seismic zone 1. Using an empirical technique outlined in the NAVFAC Design Manual (DM-7.3) to evaluate liquefaction potential of soils, for sites in seismic zone 1, a factor of safety in excess of 5 was calculated for the granular deposits encountered in the DNPS East ISFSI soil borings.

With a safety factor of 5 for soil liquefaction the potential for liquefaction is low. Therefore, soil liquefaction will not be considered for assessment within the site boundary.

Per NEI 12-06 (Reference 2, Section 5.2), all sites will consider the seismic hazard. Thus DNPS screens in for an Page 1 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013) assessment for seismic hazard except for liquefaction.

External Flood Hazard Assessment:

The Probable Maximum Flood (PMF), described in the Dresden UFSAR (Reference 1 Section 3.4.1.1), produces a peak flood to elevation 528'-0" at the Dresden site. This is above the grade elevation (517'-0"). The PMF is a precipitation based event. Therefore, time is available to relocate equipment and stage necessary measures to support plant response to rising water levels.

Thus DNPS screens in for an assessment for external flooding.

Extreme Cold Hazard Assessment:

DNPS is located at 88°16'09" W longitude and 41°2323" N latitude. The guidelines provided in NEI 12-06 (Reference 2, Section 8.2.1) include the need to consider extreme snowfall at plant sites above the 35th parallel. DNPS is located above of the 35th parallel and thus the capability to address impedances caused by extreme snowfall with snow removal equipment is required.

DNPS is located within the region characterized by EPRI as ice severity level 5 (Reference 2, Figure 8-2). As such, DNPS is subject to severe icing conditions that could also cause catastrophic destruction to electrical transmission lines.

Thus DNPS screens in for an assessment for ice, snow and extreme cold hazard assessment.

High Wind Hazard Assessment:

DNPS is located at 88°16'09" W longitude and 41°2323" N latitude. Per NEI 12-06 (Reference 2. Figure 7-2) guidance tornado hazards are applicable to Dresden.

Thus DNPS screens in for an assessment for High Wind Hazard.

Extreme High Temperature Hazard Assessment:

The guidelines provided in NEI 12-06 (Reference 2, Section 9.2) include the need to consider high temperature at all plant sites in the lower 48 states. Extreme high temperatures are not expected to impact the utilization of off-site resources or the ability of personnel to implement the required FLEX strategies. Site industrial safety procedures currently address activities with a potential for Page 2 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013) heat stress to prevent adverse impacts on personnel.

Thus DNPS screens in for an assessment for extreme High Temperature.

References

1. Dresden Nuclear Power Station Updated Final Safety Analysis Report, Revision 9
2. Diverse and Flexible Coping Strategies (FLEX)

Implementation Guide, NEI 12-06, Revision 0, August 2012

3. DNPS West ISFSI 10 CFR 72.212 Evaluation Report, Revision 3, November 2011 Key Site assumptions to Provide key assumptions associated with implementation of implement NEI 12-06 FLEX Strategies:

strategies. Flood and seismic re-evaluations pursuant to the 10 CFR 50.54(f) letter of March 12, 2012 are not Ref: NEI 12-06 section 3.2.1 completed and therefore not assumed in this submittal.

As the re-evaluations are completed, appropriate issues will be entered into the corrective action system and addressed on a schedule commensurate with other licensing bases changes.

The FLEX strategies identified in this document were developed using the current DNPS Flooding strategy.

Efforts are in progress to revise the DNPS actions for a flooding event that may impact FLEX strategies.

Information will be provided in a future update if changes to the Dresden FLEX plan are required.

Deployment resources are assumed to begin arriving at hour 6 and fully staffed by 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

Plant initial response is the same as SBO.

No additional single failures of any SSC are assumed (beyond the initial failures that define the Extended Loss of AC Power (ELAP)/Loss of Access to Ultimate Heat Sink (LUHS) scenario in NEI 12-06) (Reference 1).

Primary and secondary storage locations have not been selected. Once locations are finalized implementation routes will be defined.

Storage locations will be chosen in order to support the event timeline.

BWROG EOP Revision EPG/SAG Rev.3, containing items such as guidance to maintain steam driven injection equipment available during emergency Page 3 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013) depressurization, is approved and implemented in time to support compliance date.

DC battery banks are available.

AC and DC distribution systems are available.

Maximum environmental room temperatures for habitability or equipment availability are based on NUMARC 87-00 (Reference 2) guidance if other design basis information or industry guidance is not available.

This plan defines strategies capable of mitigating a simultaneous loss of all alternating current (AC) power and loss of normal access to the ultimate heat sink resulting from a beyond-design-basis event by providing adequate capability to maintain or restore core cooling, containment, and SFP cooling capabilities at all units on a site. Though specific strategies are being developed, due to the inability to anticipate all possible scenarios, the strategies are also diverse and flexible to encompass a wide range of possible conditions. These pre-planned strategies developed to protect the public health and safety will be incorporated into the unit emergency operating procedures in accordance with established EOP change processes, and their impact to the design basis capabilities of the unit evaluated under 10 CFR 50.59. The plant Technical Specifications contain the limiting conditions for normal unit operations to ensure that design safety features are available to respond to a design basis accident and direct the required actions to be taken when the limiting conditions are not met. The result of the beyond-design-basis event may place the plant in a condition where it cannot comply with certain Technical Specifications, and, as such, may warrant invocation of 10 CFR 50.54(x) and/or 10 CFR 73.55(p).

(Reference 3)

References

1. Diverse and Flexible Coping Strategies (FLEX)

Implementation Guide, NEI 12-06, Revision 0, August 2012

2. NUMARC 87-00, Revision 1, Guidelines and Technical Bases for NUMARC Initiatives Addressing Station Blackout at Light Water Reactors
3. Task Interface Agreement (TIA) 2004-04, "Acceptability of Proceduralized Departures from Page 4 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Technical Specifications (TSs) Requirements at the Surry Power Station," (TAC Nos. MC4331 and MC4332)," dated September 12, 2006. (Accession No. ML060590273)

Extent to which the Include a description of any alternatives to the guidance, guidance, JLD-ISG-2012-01 and provide a milestone schedule of planned action.

and NEI 12-06, are being followed. Identify any Full conformance with JLD-ISG-2012-01 and NEI 12-06 is deviations to JLD-ISG-2012- expected with no deviations.

01 and NEI 12-06.

Ref: JLD-ISG-2012-01 NEI 12-06 13.1 Provide a sequence of events Strategies that have a time constraint to be successful and identify any time should be identified with a technical basis and a constraint required for justification provided that the time can reasonably be met success including the (for example, a walk through of deployment).

technical basis for the time constraint. Describe in detail in this section the technical basis for the time constraint identified on the sequence of events timeline Ref: NEI 12-06 section 3.2.1.7 Attachment 1A JLD-ISG-2012-01 section 2.1 See attached sequence of events timeline (Attachment 1A).

Technical Basis Support information, see attached NSSS Significant Reference Analysis Deviation Table (Attachment 1B)

General Technical Basis information BWROG document NEDC-33771P, GEH Evaluation of FLEX Implementation Guidelines has been compared to the Dresden proposed strategies and Modular Accident Analysis Program (MAAP) results. Attachment 1B discusses the differences between the reference BWR 2/3 with Emergency Condenser and Dresden. The results of the BWROG document and Dresden response are consistent. In each case at the end of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> the peak containment values are below their respective design limits with significant margins to the limits.

Therefore, containment venting to remove heat from the containment is not required.

The times to complete actions in the Events Page 5 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Timeline are based on operating judgment, the conceptual designs, and the current supporting analyses. The final timeline will be time validated once detailed designs are completed, procedures are developed, and the results will be provided in a future six (6) month update.

ITEM #10 Secure Isolation Condenser (IC). Per MAAP analysis (Reference 1) the IC will be isolated at 20 minutes due to lack of qualified shell-side makeup water. Securing of the Isolation Condenser would be based on shell-side water level. Depending on initiating conditions and shell-side boil-off the time could be longer than 20 minutes. 20 minutes is utilized in the MAAP assumptions for conservatism.

ITEM #11 DC load shedding must be completed within 30 minutes to maintain battery availability for the maximum time possible.

A preliminary review of battery availability being performed identifies the 125 and 250VDC batteries will operate for at least 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> before dropping to unacceptable voltage levels if deep load shed is performed. Further review and analysis will be performed to support this assumption. The information will be provided in a future update if changes to the Dresden plan are required.

ITEM #14 Establish natural circulation air flow path through the High Pressure Coolant Injection (HPCI) room.

Preliminary GOTHIC analysis indicates opening doors at 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> will result in acceptable room temperature values to support operation of HPCI for at least 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />. The GOTHIC analysis indicates the temperature is approximately 155ºF after 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> which is below the lowest Group 4 Isolation Point of 162ºF specified in DIS 2300-07 (Reference 2)

ITEM#17 MAAP analysis (Reference 1, DR_FLEX_CASE9) indicates that initiation of the IC at approximately the 2.5 hour5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> point will result in RPV water level being maintained above top of active fuel (TAF) for greater than 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br />.

FLEX strategy for supplying power to 480 VAC busses and associated Motor Control Centers (MCCs) must be Page 6 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013) completed to power the FLEX Makeup Pumps for IC Shell-side makeup. Due to pre-staging of major components, it is reasonable to expect the FLEX Makeup pump can be energized within this time period.

ITEM#18 MAAP analysis (Reference 1, DR_FLEX_CASE9) indicates that initiation of the IC at approximately the 2.5 hour5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> point will result in RPV water level being maintained above top of active fuel (TAF) for greater than 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br />.

Due to pre-staging of major components, it is reasonable to expect the FLEX Makeup pump can be FLEX pump connected and ready for use to support Isolation Condenser shell-side makeup within this time period.

ITEM#19 MAAP analysis (Reference 1, DR_FLEX_CASE9) indicates that initiation of the IC at approximately the 2.5 hour5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> point will result in RPV water level being maintained above top of active fuel (TAF) for greater than 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br />.

A BWROG review of Reactor Core Isolation Cooling (RCIC) operation with elevated suction temperatures was documented in a GE Task Report (Reference 3). The review indicated RCIC could continue to operate up to approximately 230ºF suction temperature. While RCIC and HPCI are similar it could not be determined if the results of the RCIC Study could be applied to HPCI. Therefore, it is assumed HPCI will fail when Suppression Pool temperature reaches 140ºF. Utilization of this assumption and the MAAP results indicates approximately 2.4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> of HPCI operation is available in Phase 1.

ITEM #25 Spent Fuel Pool (SFP) make-up is not a time constraint with the initial condition of Mode 1 @ 100% power, since the worst case fuel pool heat load conditions only exist during a refueling outage. Under non-outage conditions, the maximum SFP heat load is 14.912 MBtu/hr. Loss of SFP cooling with this heat load and an initial SFP temperature of 150 degrees F results in a time to boil of 9.54 hours6.25e-4 days <br />0.015 hours <br />8.928571e-5 weeks <br />2.0547e-5 months <br />, and 110.07 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> to the top of active fuel. Therefore completing the equipment line-up for initiating SFP make-up at 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> into the event ensures adequate cooling of the spent fuel is maintained.

Page 7 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

The worst case SFP heat load during an outage is 39.688 MBtu/hr. Loss of SFP cooling with this heat load and an initial SFP temperature of 150 degrees F results in a time to boil of 3.58 hours6.712963e-4 days <br />0.0161 hours <br />9.589947e-5 weeks <br />2.2069e-5 months <br />, and 41.36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> to the top of active fuel.

With the entire core being located in the SFP, manpower resources normally allocated to core cooling along with the Operations outage shift manpower can be allocated to aligning SFP make-up which ensures the system alignment can be established prior to the point at which SFP conditions become challenged. Therefore completing the equipment line-up for initiating SFP make-up at 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> into the event ensures adequate cooling of the spent fuel is maintained.

Initial calculations were used to determine the fuel pool timelines (Reference 5). Formal calculations will be performed to validate this information during development of the spent fuel pool cooling strategy detailed design, and will be provided in a future six (6) month update.

References

1. DR-MISC-043 Revision 1, MAAP Analysis to Support FLEX Initial Strategy.
2. DIS 2300-07, Rev 20, HIGH PRESSURE COOLANT INJECTION AREA TEMPERATURE SWITCH CALIBRATION.
3. GE Task Report 0000-0143-0382-R0, RCIC System Operation in Prolonged Station Blackout -

Feasibility Study, January 2012

4. DEOP 200-1, Primary Containment Control, Revision 10
5. EC 371913, Revision 2,: Time-to-Boil Curves Identify how strategies will Describe how the strategies will be deployed in all modes.

be deployed in all modes.

Deployment of FLEX is expected for all modes of Ref: NEI 12-06 section 13.1.6 operation. Transportation routes will be developed from the equipment storage area to the FLEX staging areas. An administrative program will be developed to ensure pathways remain clear or compensatory actions will be implemented to ensure all strategies can be deployed during all modes of operation. This administrative program will also ensure the strategies can be implemented in all modes by maintaining the portable FLEX equipment available to be deployed during all modes.

Page 8 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Identification of storage and creation of the administrative program are open items. Closure of these items will be documented in a six (6) month update.

Provide a milestone The dates specifically required by the order are obligated or schedule. This schedule committed dates. Other dates are planned dates subject to should include: change. Updates will be provided in the periodic (six Modifications timeline month) status reports.

o Phase 1 See attached milestone schedule Attachment 2 Modifications o Phase 2 Exelon Generation Company, LLC (Exelon) fully expects to Modifications meet the site implementation/compliance dates provided in o Phase 3 Order EA-12-049 with no exceptions. Any changes or Modifications additions to the planned interim milestone dates will be Procedure guidance provided in a future six (6) month update.

development complete o Strategies o Maintenance Storage plan (reasonable protection)

Staffing analysis completion FLEX equipment acquisition timeline Training completion for the strategies Regional Response Centers operational Ref: NEI 12-06 section 13.1 Identify how the Provide a description of the programmatic controls programmatic controls will equipment protection, storage and deployment and be met. equipment quality. See section 11 in NEI 12-06. Storage of equipment, 11.3, will be documented in later sections of this Ref: NEI 12-06 section 11 template and need not be included in this section.

JLD-ISG-2012-01 section 6.0 See section 6.0 of JLD-ISG-2012-01.

DNPS will implement an administrative program for FLEX to establish responsibilities, and testing & maintenance requirements. A plant system designation will be assigned to FLEX equipment which requires configuration controls Page 9 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013) associated with systems. This will establish responsibilities, maintenance and testing requirements for all components associated with FLEX. Unique identification numbers will be assigned to all components added to the FLEX plant system. Equipment associated with these strategies will be procured as commercial equipment with design, storage, maintenance, testing, and configuration control as outlined in JLD-ISG-2012-01 section 6 and NEI 12-06 section 11.

Installed structures, systems and components pursuant to 10CFR50.63(a) will continue to meet the augmented quality guidelines of Regulatory Guide 1.155, Station Blackout.

Standard industry PMs will be developed to establish maintenance and testing frequencies based on type of equipment and will be within EPRI guidelines. Testing procedures will be developed based on the industry PM templates and Exelon standards.

Describe training plan List training plans for affected organizations or describe the plan for training development Training materials for FLEX will be developed for all station staff involved in implementing FLEX strategies. For accredited training programs, the Systematic Approach to Training, SAT, will be used to determine training needs. For other station staff, a training overview will be developed per change management plan.

Describe Regional Response DNPS has contractual agreements in place with the Center plan Strategic Alliance for FLEX Emergency Response (SAFER).

The industry will establish two (2) Regional Response Centers (RRC) to support utilities during beyond design basis events. Each RRC will hold five (5) sets of equipment, four (4) of which will be able to be fully deployed when requested, the fifth set will have equipment in a maintenance cycle. Equipment will be moved from an RRC to a local Assemble Area, established by the SAFER team and the utility. Communications will be established between the affected nuclear site and the SAFER team and required equipment moved to the site as needed. First arriving equipment, as established during development of the nuclear sites playbook, will be delivered to the site within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> from the initial request.

Page 10 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Notes:

Exelon Generation Company, LLC (Exelon) has not finalized the engineering designs for compliance with NRC Order EA-12-049. Detailed designs based on the current conceptual designs will be developed to determine the final plan and associated mitigating strategies. Analysis will be performed to validate that the plant modifications, selected equipment, and identified mitigating strategy can satisfy the safety function requirements of NEI 12-06. Once these designs and mitigating strategies have been fully developed, Exelon will update the integrated plan for DNPS during a scheduled six (6) month update. This update will include any changes to the initial designs as submitted in the February 28, 2013 Integrated plan (as revised Aug 28, 2013).

Page 11 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Core Cooling Determine Baseline coping capability with installed coping1 modifications not including FLEX modifications, utilizing methods described in Table 3-1 of NEI 12-06:

RCIC/HPCI/IC Depressurize RPV for injection with portable injection source Sustained water source BWR Installed Equipment Phase 1:

Provide a general description of the coping strategies using installed equipment including modifications that are proposed to maintain core cooling. Identify methods (RCIC/HPCI/IC)and strategy(ies) utilized to achieve this coping time.

Power Operation, Startup, and Hot Shutdown Reactor Level Control Initial reactor water level control would be accomplished using the HPCI System which is independent of all AC power. Normal suction source for HPCI is the Condensate Storage Tanks (CST). Operation of the HPCI Turbine will result in a heat input to the Torus. There is no current method to remove heat from the Torus when AC power is not available. The CSTs are qualified for all criteria with the exception of tornado/high winds. If the CSTs are unavailable, HPCI suction can be transferred to the Torus (suppression pool).

With continuous HPCI operation MAAP analysis (Reference 1) indicates suppression pool temperature reaches 140ºF approximately 2.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> after event initiation. The Dresden UFSAR (Reference 2, Section 6.3.2.3) identifies continued operation of HPCI above a suppression pool temperature of 140°F is not permitted based on lube oil heat exchanger performance and pump net positive suction head. Utilization of this assumption and the MAAP results indicates 2.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> of HPCI operation is available in Phase 1.

With regards to DC power, HPCI would remain a viable source as long as 250VDC power is available. After 250VDC battery depletion, HPCI is assumed to be not available as essential support motors (such as Gland Seal Leak-off (GSLO) Drain Pump and the GSLO Condenser Exhauster) lose power. A preliminary review identifies the 250VDC batteries will operate for at least 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> before dropping to unacceptable voltage levels if deep load shed is performed.

Therefore, 250VDC availability is not limiting to HPCI operation in Phase 1 when compared to pump suction temperatures from the Suppression Pool.

Pressure Control As described in the Dresden UFSAR (Reference 2, Section 5.4.6.), the Isolation Condenser (IC) 1 Coping modifications consist of modifications installed to increase initial coping time, i.e. generators to preserve vital instruments or increase operating time on battery powered equipment.

Page 12 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013) provides RPV pressure control in the event that the reactor becomes isolated from the turbine and 6

the main condenser. The IC was designed for a cooling rate of 252.5 x 10 Btu/hr and is capable of operation without AC electrical power and operates by natural circulation. Steam flow from the reactor condenses in the tubes of the heat exchanger and returns by gravity to the reactor in a closed loop. The differential water head, created when the steam is condensed, serves as the driving force. Shell side water is boiled and vented to atmosphere outside the Reactor Building.

Makeup water for the IC shell side is normally supplied from the clean demineralized water storage tank via one of two diesel driven isolation condenser makeup water pumps. Per the UFSAR (Reference 2, Section 5.4.6.3), the Isolation Condenser will operate approximately 20 minutes without initiation of shell-side makeup. In Phase 1 there are no shell side makeup sources that meet requirements for FLEX qualification. Therefore, the Isolation Condenser will be secured based on shell-side water level to prevent possible damage from operation with inadequate shell-side level.

Operation of the HPCI System removes heat from the RPV. This heat removal will be used to maintain RPV pressure after the Isolation Condenser is secured. As previously mentioned, operation of the HPCI turbine will result in a heat input to the Torus.

After HPCI is lost, the Target Rock Safety Relief Valve (SRV) and/or Electromatic Relief Valves (ERV) will operate to control RPV pressure. The Target Rock Safety Relief Valve and ERVs release steam from the RPV to the Suppression Pool under the water. This results in a loss of RPV inventory and a heat addition to the Suppression Pool.

Overall Response The MAAP (Reference 1) was utilized to evaluate overall response of installed systems per the system utilization described above. With continuous HPCI operation MAAP analysis indicates suppression pool temperature reaches 140ºF approximately 2.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> after event initiation.

MAAP case DR_FLEX_CASE8 (Reference 1) most closely resembles the expected Phase 1 system response. Following the loss of HPCI as an injection source due to suppression pool temperature exceeding 140 ºF and assuming the Isolation Condenser is unavailable without a shell side make up source; water level in the RPV reaches the top of active fuel approximately 4.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> after event initiation. The reactor water inventory loss is due to operation of the Target Rock Safety Relief Valve for reactor pressure control after HPCI operation ceases and assumed leakage sources. Primary Containment pressure reaches design pressure approximately 8-9 hours after the event.

Based on the above information, the coping time for Dresden Station using installed equipment is approximately 4.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> when core uncovery occurs.

Additionally MAAP analysis (Reference 1, DR_FLEX_CASE8) identified the Heat Capacity Temperature Limit (HCTL) is reached approximately 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> into the event and the Pressure Suppression Pressure is reached approximately 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> into the event. Based on this information and current Dresden Emergency Operating Procedures (Reference 3) RPV emergency depressurization will not be required before HPCI is assumed to fail.. Once the IC is placed back in service at approximately 2.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> into the event, it is expected the reactor will be cooled and Page 13 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013) depressurized with the use of the IC.

Cold Shutdown and Refueling When in Cold Shutdown and Refueling, many variables exist which impact the ability to cool the core. In the event of an ELAP during these Modes, installed plant systems cannot be relied upon to cool the core, thus transition to Phase 2 will begin immediately. All efforts will be made to expeditiously provide core cooling and minimize heat-up and re-pressurization. Exelon has a program in place (References 4 and 5) to determine the time to boil for all conditions during shutdown periods. This time will be used to determine the time required to complete transition to Phase 2.

To accommodate the activities of vessel disassembly and refueling, water levels in the reactor vessel and the reactor cavity are often changed. The most limiting condition is the case in which the reactor head is removed and water level in the vessel is at or below the reactor vessel flange. If an ELAP/LUHS occurs during this condition then (depending on the time after shutdown) boiling in the core may occur quite rapidly.

Deploying and implementation of a FLEX Makeup pump to supply injection flow must commence as soon as possible from the initiation of the event. This should be plausible because more personnel are on site during outages to provide the necessary resources. Strategies for makeup water include utilization of a FLEX Makeup pump to take suction from the UHS as described in the Phase 2 Core Cooling section.

Guidance will be provided to ensure that sufficient area is available for deployment without interference from outage equipment during refueling outages.

References:

1. DR-MISC-043 Revision 1, MAAP Analysis to Support FLEX Initial Strategy.
2. Dresden Nuclear Power Station Updated Final Safety Analysis Report, Revision 9
3. DEOP 200-1, Primary Containment Control, Revision 10
4. OU-AA-103, Shutdown Safety Management Program
5. EC 371913, Revision 2,: Time-to-Boil Curves Details:

Provide a brief Confirm that procedure/guidance exists or will be developed to description of Procedures support implementation

/ Strategies / Guidelines Dresden Station will utilize the industry developed guidance from the Owners Groups, EPRI and NEI Task team to develop site specific procedures or guidelines to address the criteria in NEI 12-

06. These procedures and/or guidelines will support the existing symptom based command and control strategies in the current EOPs.

At the initiation of the event personnel will enter DGA 12, Partial or Complete Loss of AC Power, and Emergency Operating Page 14 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Procedures (EOPs). DGA-12 provides direction for SBO events and will direct Operations personnel to perform DC Load shedding to extend battery availability. Personnel will utilize High Pressure Coolant Injection (HPCI) and Isolation Condenser (IC) for initial reactor pressure and level control as described above.

Procedures exist to operate installed plant equipment such as HPCI and the IC. Direction is provided for actions such as DC Load Shedding in station procedures.

Identify modifications List modifications There are no modifications required to support Phase 1 response.

Key Reactor Parameters List instrumentation credited for this coping evaluation.

RPV Level Instrument Power supply LI 2-640-29A(B) ESS (via Digital FWLC). 250VDC supply LI 3-640-29A(B) ESS (via Digital FWLC) 250VDC supply LI 2-263-59A(B) N/A, Local instruments, no power required LI 3-263-59A(B) N/A, Local instruments, no power required LI 2-263-151A(B) N/A, Local instruments, no power required LI 3-263-151A(B) N/A, Local instruments, no power required RPV Pressure Instrument Power supply PI 2-263-156 125VDC 2A1 PI 3-263-156 125VDC 3A1 PI 2-263-60A(B) N/A, Local instruments, no power required PI 3-263-60A(B) N/A, Local instruments, no power required PI 2-263-139A(B) N/A, Local instruments, no power required PI 3-263-139A(B) N/A, Local instruments, no power required Isolation Condenser Shell-side Level Instrument Power supply 2-1301-644 N/A, Local sight-glass, no power required 3-1301-644 N/A, Local sight-glass, no power required DNPS evaluation of the FLEX strategy may identify additional parameters that are needed in order to support key actions identified in the plant procedures/guidance or to indicate imminent or actual core damage (NEI 12-06 Rev. 0, Section 3.2.1.10) and any differences will be communicated in a future six (6) month update following identification.

Page 15 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Notes:

Exelon Generation Company, LLC (Exelon) has not finalized the engineering designs for compliance with NRC Order EA-12-049. Detailed designs based on the current conceptual designs will be developed to determine the final plan and associated mitigating strategies. Analysis will be performed to validate that the plant modifications, selected equipment, and identified mitigating strategy can satisfy the safety function requirements of NEI 12-06. Once these designs and mitigating strategies have been fully developed, Exelon will update the integrated plan for DNPS during a scheduled six (6) month update. This update will include any changes to the initial designs as submitted in the February 28, 2013 Integrated plan (as revised Aug 28, 2013).

Page 16 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Core Cooling BWR Portable Equipment Phase 2:

Provide a general description of the coping strategies using on-site portable equipment including modifications that are proposed to maintain core cooling. Identify methods (RCIC/HPCI/IC)and strategy(ies) utilized to achieve this coping time.

Dresden-specific inputs and the MAAP 4.0.5 computer code are used to calculate plant response to several scenarios to analyze this event as documented in DR-MISC-043 Revision 1 (Reference 1). Case DR_FLEX_CASE9 best represents the postulated conditions where the assumed RPV leakage is 61 gpm with no RPV makeup after HPCI operation ceases.

Station personnel will line-up pre-staged equipment to supply shell-side makeup to the Isolation Condenser (IC) and re-energize the 125V and 250VDC Battery Chargers. If the IC is placed in service prior to HPCI being secured, the core will remain covered for at least 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> without makeup. The only inventory losses during this time will be the assumed 61 gpm leakage.

Personnel will also line-up RPV inventory makeup sources supplied by FLEX equipment.

RPV Pressure Control Dresden will utilize pre-staged equipment to provide shell-side makeup to the IC prior to the loss of HPCI as an RPV Pressure Control mechanism. Utilization of the IC as the RPV Pressure Control mechanism will eliminate the need for SRV/ERV operation and the subsequent RPV inventory loss/Suppression Pool heat addition.

Shell-side makeup to the IC will be established using a proposed pre-staged AC powered FLEX Makeup Pump. The pump suction will be from the Ultimate Heat Sink (UHS) utilizing existing Containment Closed Service Water (CCSW) suction piping. Pump discharge will be directed through a temporary connection to existing Containment Closed Service Water (CCSW) pump discharge piping and then into the Reactor Building. New standpipes will be installed on the CCSW piping to establish valve stations in the Reactor Building. Hoses will be routed from the standpipe valve stations to the following locations, either of which will supply shell-side makeup water to both Isolation Condensers. Therefore, only 1 FLEX Makeup Pump is required to meet the strategy needs for both Units.

1. Primary Strategy The first proposed strategy is associated with the currently installed IC Makeup Pump discharge line. New taps will be installed on the 8 combined discharge piping of the IC Makeup Pumps in the Reactor Building. The taps will include a check valve, gate valve, and quick hose connection to connect to pipe line 2/3-43218-8. Taps will be located on 517 elevation (preferred) and 545 (available during flood conditions) elevations. The primary source will be the Unit 2 FLEX Makeup Pump.

Page 17 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Core Cooling BWR Portable Equipment Phase 2:

2. Alternate Strategy The alternate strategy will be to use the Unit 3 FLEX Makeup Pump and associated CCSW standpipe to supply shell-side makeup water to both Isolation Condensers.

Connection of a FLEX Makeup pump via a hose to one of the proposed hose connections on the combined IC Makeup Pump discharge piping (on the 517 elevation, or on the 545 elevation in the Reactor Building) allows water from the UHS to be supplied directly to the IC shells with minimal impact on the staffing requirements at Dresden.

These modifications are in diverse locations, and the connection points and piping are qualified for the five Beyond Design Basis External Events (BDBEEs) that must be considered for implementation of FLEX. The proposed FLEX Makeup Pumps will be capable of operating under water and therefore will be available during a flooding event. Additionally, these modifications are designed to supply both the Unit 2 IC and the Unit 3 IC simultaneously. The Pump motors will be powered from 480 VAC Motor Control Centers (MCCs) that are capable of being powered by the FLEX Diesel Generators described in the Safety Function Support - Phase 2 section of this submittal.

RPV Makeup The Phase 1 injection method to the RPV is HPCI, whose primary water source is the Contaminated Condensate Storage Tank (CST). However, when the CST is unavailable, HPCI switches suction to the suppression pool. Eventually, increased suppression pool temperature renders the suppression pool unavailable as a HPCI suction source. Additionally, reactor pressure (i.e. decay heat) may become insufficient to drive the HPCI turbine. Therefore, an alternate makeup water source is required.

The alternate makeup water source for direct RPV injection involves proposed pre-staged AC powered FLEX Makeup Pumps. The pump suction will be from the Ultimate Heat Sink (UHS) utilizing existing Containment Closed Service Water (CCSW) suction piping. Pump discharge will be directed through a temporary connection to existing Containment Closed Service Water (CCSW) pump discharge piping and then into the Reactor Building. New standpipes will be installed on the CCSW piping to establish valve stations in the Reactor Building. Due to the proposed location of the standpipes and the capacity of the proposed pumps, 1 FLEX Makeup Pump is capable of supplying makeup to both Units. Hoses will be routed from the standpipe valve stations to one of two proposed locations.

1. Primary Strategy Unit 2 A new check valve, gate valve, and quick hose connection will be installed on the flanged connection between MO 2-1501-28A and MO 2-1501-27A. A hose would Page 18 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Core Cooling BWR Portable Equipment Phase 2:

then be utilized to connect at this location from the CCSW Standpipe on the 517 elevation. Water would flow from the FLEX pump discharge, into the CCSW Standpipe manifold valve, through the hose between the new connections and into the LPCI System. Installed valves in the system would then be manually operated, if necessary, to direct water into the reactor vessel.

Unit 3 A new check valve, gate valve, and quick hose connection will be installed on the flanged connection between MO 3-1501-28B and MO 3-1501-27B. A hose would then be utilized to connect at this location from the CCSW Standpipe on the 517 elevation. Water would flow from the FLEX pump discharge, into the CCSW Standpipe manifold valve, through the hose between the new connections and into the LPCI System. Installed valves in the system would then be manually operated, if necessary, to direct water into the reactor vessel.

2. Alternate Strategy The second proposed strategy is associated with a similar flow path for the upper drywell spray headers on the 545 elevation and the LPCI system.

Unit 2 A new check valve, gate valve, and quick hose connection will be installed on the flanged connection between MO 2-1501-28B and MO 2-1501-27B. A hose would then be utilized to connect at this location from the CCSW Standpipe on the 545 elevation. Water would flow from the FLEX pump discharge, into the CCSW Standpipe manifold valve, through the hose between the new connections and into the LPCI System at the upper drywell spray header. Installed valves in the system would then be manually operated, if necessary, to direct water into the reactor vessel.

Unit 3 A new check valve, gate valve, and quick hose connection will be installed on the flanged connection between MO 3-1501-28A and MO 3-1501-27A. A hose would then be utilized to connect at this location from the CCSW Standpipe on the 545 elevation. Water would flow from the FLEX pump discharge, into the CCSW Standpipe manifold valve, through the hose between the new connections and into the LPCI System at the upper drywell spray header. Installed valves in the system would then be manually operated, if necessary, to direct water into the reactor vessel.

These modifications are in diverse locations, and the connection points and piping will be qualified for the five Beyond Design Basis External Events (BDBEEs) that must be considered for implementation of FLEX. The proposed FLEX Makeup Pumps will be capable of operating under water and therefore will be available during a flooding event. Additionally, these modifications are designed to supply both the Unit 2 and the Unit 3 RPV Makeup needs Page 19 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Core Cooling BWR Portable Equipment Phase 2:

simultaneously from one FLEX Makeup Pump. The Pump motors will be powered from 480 VAC Motor Control Centers (MCCs) that are capable of being powered by the FLEX Diesel Generators described in the Safety Function Support - Phase 2 section of this submittal.

Two additional actions will be available to limit RPV inventory reduction when a FLEX Diesel Generator is started and 480 V Busses/MCCs are energized.

The first action will involve isolation of the Reactor Recirculation Loops. The loop isolation valves are AC powered and can be closed when power is available. This will eliminate the Recirculation Pump Seal Leakage (36 gpm total of the assumed RPV leakage). DR-MISC-043 Revision 1 (Reference 1) Case DR_FLEX_CASE11 is similar to Case DR_FLEX_CASE9 but it simulates the plant response of isolating the Recirculation Loops at 3.0 hours0 days <br />0 hours <br />0 weeks <br />0 months <br />. The time to core uncovery increases from 16.8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> to 37.3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />. It is important to note these times in DR-MISC-043 Revision 1 (Reference 1) Case DR_FLEX_CASE11are based on conditions with no RPV makeup source. If RPV makeup is available core uncovery does not occur.

The second action is the availability of energizing Standby Liquid Control (SBLC) pumps in non-flood initiating events. Each pump can supply 40 gpm at a discharge pressure of up to 1250 psig. The SBLC Storage Tank would then be used as an RPV makeup source. Utilization of SBLC as a high pressure injection source will further lengthen the time to core uncovery in DR-MISC-043 Revision 1 (Reference 1) Case DR_FLEX_CASE11. High pressure injection will not be required in a flood scenario because the plant is shutdown and depressurized prior to the flood reaching the 517 elevation. Under flood conditions, the FLEX Makeup Pump will be the RPV injection source.

It is expected that continued use of the Isolation Condenser for RPV heat removal/pressure control, with a FLEX Makeup pump available for injection into the RPV, will provide long-term core cooling without the need for offsite equipment.

References:

1. DR-MISC-043 Revision 1, MAAP Analysis to Support FLEX Initial Strategy.

Details:

Provide a brief Confirm that procedure/guidance exists or will be developed to description of Procedures support implementation

/ Strategies / Guidelines Dresden Station will utilize the industry developed guidance from the Owners Groups, EPRI and NEI Task team to develop site specific procedures or guidelines to address the criteria in NEI 12-06. These procedures and/or guidelines will support the existing symptom based command and control strategies in the current EOPs.

Page 20 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Core Cooling BWR Portable Equipment Phase 2:

Identify modifications List modifications

1. Installation of new piping and associated connections, valve and flanges, and new connection points in the existing IC shell-side makeup line to allow for the connection of a pre-staged FLEX Makeup pump to provide a path from one Unit for IC shell-side makeup.

(see Attachment 3 Figures 1 and 2)

2. Installation of new piping and associated connections, valve and flanges, to allow for the connection of a pre-staged FLEX Makeup pump to provide a path from the opposite Unit for IC shell-side makeup. This will provide another source of shell-side makeup. (see Attachment 3 Figures 1 and 2)
3. Installation of new connection points associated with the LPCI Lower Drywell Spray piping to provide RPV makeup using a pre-staged FLEX Makeup pump. (see Attachment 3 Figures 1 and 3)
4. Installation of new connection points associated with the LPCI Upper Drywell Spray piping to provide RPV makeup using a pre-staged FLEX Makeup pump. (see Attachment 3 Figures 1 and 3)

Key Reactor Parameters List instrumentation credited or recovered for this coping evaluation.

RPV Level Instrument Power supply LI 2-640-29A(B) ESS (via Digital FWLC). 250VDC supply LI 3-640-29A(B) ESS (via Digital FWLC) 250VDC supply LI 2-263-59A(B) N/A, Local instruments, no power required LI 3-263-59A(B) N/A, Local instruments, no power required LI 2-263-151A(B) N/A, Local instruments, no power required LI 3-263-151A(B) N/A, Local instruments, no power required Page 21 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Core Cooling BWR Portable Equipment Phase 2:

RPV Pressure Instrument Power supply PI 2-263-156 125VDC 2A1 PI 3-263-156 125VDC 3A1 PI 2-263-60A(B) N/A, Local instruments, no power required PI 3-263-60A(B) N/A, Local instruments, no power required PI 2-263-139A(B) N/A, Local instruments, no power required PI 3-263-139A(B) N/A, Local instruments, no power required Isolation Condenser Shell-side Level Instrument Power supply 2-1301-644 N/A, Local sight-glass, no power required 3-1301-644 N/A, Local sight-glass, no power required 2-1340-2 Instrument Bus (Available for all events except flooding above 517 elevation) 3-1340-2 Instrument Bus (Available for all events except flooding above 517 elevation)

DNPS evaluation of the FLEX strategy may identify additional parameters that are needed in order to support key actions identified in the plant procedures/guidance or to indicate imminent or actual core damage (NEI 12-06 Rev. 0, Section 3.2.1.10) and any differences will be communicated in a future six (6) month update following identification.

Storage / Protection of Equipment :

Describe storage / protection plan or schedule to determine storage requirements Seismic List how equipment is protected or schedule to protect Structures to provide protection of FLEX equipment will be constructed to meet the requirements of NEI 12-06 Section 11.

Schedule to construct permanent building is contained in Attachment 2, and will satisfy the site compliance date.

Temporary locations will be used until building construction completion. Procedures and programs will be developed to Page 22 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Core Cooling BWR Portable Equipment Phase 2:

address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the external hazards applicable to DNPS.

Pre-staged Phase 2 equipment and associated connections will be located in robust structures. The FLEX Generators will be located in a robust structure above the Unit 2 HRSS Building.

The FLEX Makeup Pumps will be located in the Turbine Building below grade level. The connections for electrical and mechanical functions will be in the robust structure above Unit 2 HRSS, the Reactor Building or the Turbine Building.

Flooding List how equipment is protected or schedule to protect Note: if stored below current flood level, then ensure procedures exist to move equipment prior to exceeding flood level Structures to provide protection of FLEX equipment will be constructed to meet the requirements of NEI 12-06 Section 11.

Schedule to construct permanent building is contained in Attachment 2, and will satisfy the site compliance date.

Temporary locations will be used until building construction completion. Procedures and programs will be developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the external hazards applicable to DNPS.

FLEX equipment can be stored below flood level at DNPS since sufficient warning time is available to relocate and/or deploy the equipment. Plant procedures/guidance will be developed to address the needed actions. FLEX equipment will be relocated to a position that is protected from the flood, either by barriers or by elevation, prior to the arrival of the potentially damaging flood levels. Both electrical and at least one mechanical FLEX connection locations will be above the flood plain. At least one fuel oil storage tank will be protected from flood conditions.

Pre-staged Phase 2 equipment will be located in areas above the flood level (such as FLEX Generator) or capable of operating submerged (FLEX Makeup Pump). During flood preparations the appropriate connections and equipment set-up will be completed such that actions to support core cooling will be completed before the flood level reaches 517 elevation.

Severe Storms with High List how equipment is protected or schedule to protect Winds Page 23 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Core Cooling BWR Portable Equipment Phase 2:

Structures to provide protection of FLEX equipment will be constructed to meet the requirements of NEI 12-06 Section 11.

Schedule to construct permanent building is contained in Attachment 2, and will satisfy the site compliance date.

Temporary locations will be used until building construction completion. Procedures and programs will be developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the external hazards applicable to DNPS.

Pre-staged Phase 2 equipment and associated connections will be located in robust structures. The FLEX Generators will be located in a robust structure above the Unit 2 HRSS Building.

The FLEX Makeup Pumps will be located in the Turbine Building below grade level. The connections for electrical and mechanical functions will be in the robust structure above Unit 2 HRSS, the Reactor Building or the Turbine Building.

Snow, Ice, and Extreme List how equipment is protected or schedule to protect Cold Structures to provide protection of FLEX equipment will be constructed to meet the requirements of NEI 12-06 Section 11.

Schedule to construct permanent building is contained in Attachment 2, and will satisfy the site compliance date.

Temporary locations will be used until building construction completion. Procedures and programs will be developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the external hazards applicable to DNPS.

Pre-staged Phase 2 equipment and associated connections will be located in robust structures. The FLEX Generators will be located in a robust structure above the Unit 2 HRSS Building.

The FLEX Makeup Pumps will be located in the Turbine Building below grade level. The connections for electrical and mechanical functions will be in the robust structure above Unit 2 HRSS, the Reactor Building or the Turbine Building.

High Temperatures List how equipment is protected or schedule to protect Structures to provide protection of FLEX equipment will be constructed to meet the requirements of NEI 12-06 Section 11.

Schedule to construct permanent building is contained in Attachment 2, and will satisfy the site compliance date.

Page 24 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Core Cooling BWR Portable Equipment Phase 2:

Temporary locations will be used until building construction completion. Procedures and programs will be developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the external hazards applicable to DNPS.

Pre-staged Phase 2 equipment and associated connections will be located in robust structures. The FLEX Generators will be located in a robust structure above the Unit 2 HRSS Building.

The FLEX Makeup Pumps will be located in the Turbine Building below grade level. The connections for electrical and mechanical functions will be in the robust structure above Unit 2 HRSS, the Reactor Building or the Turbine Building.

Deployment Conceptual Modification (Attachment 3 contains Conceptual Sketches)

Strategy Modifications Protection of connections Identify Strategy including how Identify modifications Identify how the the equipment will be deployed connection is protected to the point of use.

For the primary and alternate Deployment to use the FLEX FLEX pump piping strategy (for IC shell-side pumps for IC Makeup will connections will be makeup), FLEX pumps will be consist of connecting the protected in the area of pre-staged on each unit in the discharge piping as well as the the existing CCSW area of the CCSW pumps. The electrical power supply for the pumps located in a lower FLEX Pumps will take suction 480 VAC motor (provided by elevation of the Turbine from the UHS source available FLEX portable generator building.

at the CCSW pumps and will through existing 480 VAC be connected to the discharge buses). Necessary Electrical connections for of a CCSW pump on each unit. modifications for deployment the FLEX 480 VAC The CCSW discharge piping include: generator are will be modified by the Pre-stage 480 VAC FLEX conceptually planned to installation of a standpipe in the pumps near the CCSW be located in a structure Reactor Building with valve Pumps above the Unit 2 High manifolds which will provide Install suction and Radiation Sampling connection points for hoses to discharge piping for pre- System (HRSS) Building the IC Makeup system. staged FLEX pumps to and in the Reactor allow timely connection Building. Both locations Install electrical supply to are robust against the pre-staged FLEX pumps to designated FLEX allow timely connection initiating conditions.

Page 25 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Core Cooling BWR Portable Equipment Phase 2:

Preliminary review indicates all connections to support the Primary strategy will be inside the current Station power block and therefore inside robust structures. To provide response during flood conditions, appropriate components will be capable of operating submerged and connections above the flood level will be available.

FLEX piping, valves, and connections (electrical &

fluid) will meet NEI 12-06 Rev.0 protection requirements.

For the primary and alternate Deployment to use the FLEX FLEX pump piping strategy (for RPV makeup), pumps for RPV Makeup will connections will be FLEX pumps will be pre-staged consist of connecting the protected in the area of on each unit in the area of the discharge piping as well as the the existing CCSW CCSW pumps. The FLEX electrical power supply for the pumps located in a lower Pumps will take suction from 480 VAC motor (provided by elevation of the Turbine the UHS source available at the FLEX portable generator building.

CCSW pumps and will be through existing 480 VAC connected to the discharge of a buses). Necessary Electrical connections for CCSW pump on each unit. The modifications for deployment the FLEX 480 VAC CCSW discharge piping will be include: generator are modified by the installation of a Pre-stage 480 VAC FLEX conceptually planned to standpipe in the Reactor pumps near the CCSW be located in a structure Building with valve manifolds Pumps above the Unit 2 High which will be connected via Install suction and Radiation Sampling hoses to either DW Spray Line. discharge piping for pre- System (HRSS) Building Installed LPCI Piping will then staged FLEX pumps to and in the Reactor be utilized to transport the allow timely connection Building. Both locations water into the RPV. Install electrical supply to are robust against the Page 26 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Core Cooling BWR Portable Equipment Phase 2:

pre-staged FLEX pumps to designated FLEX allow timely connection initiating conditions.

Preliminary review indicates all connections to support the Primary strategy will be inside the current Station power block and therefore inside robust structures. To provide response during flood conditions, appropriate components will be capable of operating submerged and connections above the flood level will be available.

FLEX piping, valves, and connections (electrical &

fluid) will meet NEI 12-06 Rev.0 protection requirements.

Notes:

Exelon Generation Company, LLC (Exelon) has not finalized the engineering designs for compliance with NRC Order EA-12-049. Detailed designs based on the current conceptual designs will be developed to determine the final plan and associated mitigating strategies. Analysis will be performed to validate that the plant modifications, selected equipment, and identified mitigating strategy can satisfy the safety function requirements of NEI 12-06. Once these designs and mitigating strategies have been fully developed, Exelon will update the integrated plan for DNPS during a scheduled six (6) month update. This update will include any changes to the initial designs as submitted in the February 28, 2013 Integrated plan (as revised Aug 28, 2013).

Page 27 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Core Cooling BWR Portable Equipment Phase 3:

Provide a general description of the coping strategies using phase 3 equipment including modifications that are proposed to maintain core cooling. Identify methods (RCIC/HPCI/IC) and strategy(ies) utilized to achieve this coping time.

Phase 1 and 2 strategy will provide sufficient capability that no additional Phase 3 strategies are required.

In the event additional equipment is needed portable pumps and generators can utilize the connection points installed in Phase 2 modifications to provide the necessary flow and pressure as outlined in Phase 2 response for RPV Pressure Control and RPV Makeup.

Details:

Provide a brief Confirm that procedure/guidance exists or will be developed to description of Procedures support implementation

/ Strategies / Guidelines DNPS will use the industry developed guidance from the Owners Groups, EPRI and NEI Task team to develop site specific procedures or guidelines to address the criteria in NEI 12-06. These procedures and/or guidelines will support the existing symptom based command and control strategies in the current EOPs.

Identify modifications List modifications None.

Key Reactor Parameters List instrumentation credited or recovered for this coping evaluation.

RPV Level Instrument Power supply LI 2-640-29A(B) ESS (via Digital FWLC). 250VDC supply LI 3-640-29A(B) ESS (via Digital FWLC) 250VDC supply LI 2-263-59A(B) N/A, Local instruments, no power required LI 3-263-59A(B) N/A, Local instruments, no power required LI 2-263-151A(B) N/A, Local instruments, no power required LI 3-263-151A(B) N/A, Local instruments, no power required Page 28 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Core Cooling BWR Portable Equipment Phase 3:

RPV Pressure Instrument Power supply PI 2-263-156 125VDC 2A1 PI 3-263-156 125VDC 3A1 PI 2-263-60A(B) N/A, Local instruments, no power required PI 3-263-60A(B) N/A, Local instruments, no power required PI 2-263-139A(B) N/A, Local instruments, no power required PI 3-263-139A(B) N/A, Local instruments, no power required Isolation Condenser Shell-side Level Instrument Power supply 2-1301-644 N/A, Local sight-glass, no power required 3-1301-644 N/A, Local sight-glass, no power required 2-1340-2 Instrument Bus (Available for all events except flooding above 517 elevation) 3-1340-2 Instrument Bus (Available for all events except flooding above 517 elevation)

DNPS evaluation of the FLEX strategy may identify additional parameters that are needed in order to support key actions identified in the plant procedures/guidance or to indicate imminent or actual core damage (NEI 12-06 Rev. 0, Section 3.2.1.10) and any differences will be communicated in a future six (6) month update following identification.

Deployment Conceptual Modification (Attachment 3 contains Conceptual Sketches)

Strategy Modifications Protection of connections Identify Strategy including how Identify modifications Identify how the the equipment will be deployed connection is protected to the point of use.

None None None Page 29 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Core Cooling BWR Portable Equipment Phase 3:

Notes:

Exelon Generation Company, LLC (Exelon) has not finalized the engineering designs for compliance with NRC Order EA-12-049. Detailed designs based on the current conceptual designs will be developed to determine the final plan and associated mitigating strategies. Analysis will be performed to validate that the plant modifications, selected equipment, and identified mitigating strategy can satisfy the safety function requirements of NEI 12-06. Once these designs and mitigating strategies have been fully developed, Exelon will update the integrated plan for DNPS during a scheduled six (6) month update. This update will include any changes to the initial designs as submitted in the February 28, 2013 Integrated plan (as revised Aug 28, 2013).

Page 30 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Containment Determine Baseline coping capability with installed coping2 modifications not including FLEX modifications, utilizing methods described in Table 3-1 of NEI 12-06:

Containment Venting or Alternate Heat Removal Hydrogen Igniters (Mark III containments only)

BWR Installed Equipment Phase 1:

Provide a general description of the coping strategies using installed equipment including modifications that are proposed to maintain containment. Identify methods (containment vent or alternative / Hydrogen Igniters) and strategy(ies) utilized to achieve this coping time.

At the initiation of the event personnel will enter DGA 12, Partial or Complete Loss of AC Power, and Emergency Operating Procedures (EOPs). Reactor water level and pressure control would be accomplished using the HPCI System which is independent of all AC power. Operation of the HPCI Turbine will result in a heat input to the Torus. There is no current method to remove heat from the Torus without AC power. HPCI will remain a viable system as long as Suppression Pool temperature is less than or equal to 140°F and 250VDC power is available.

Once the IC has been re-initiated, the HPCI system can be secured. The IC removes decay heat with no loss of inventory from the reactor coolant system (although there still may be some leakage from the assumed RPV leakage into the Drywell), and with no addition of heat to the suppression pool. As long as the shell side of the IC is replenished (phase 2) with sufficient water, the IC will remove adequate decay heat to maintain core cooling. MAAP analysis (Reference 1, DR_FLEX_CASE11) performed identified drywell pressure would be approximately 20 psig at 2.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> from the start of the event, at which time, IC would be re-initiated and HPCI secured.

During Phase 1, containment integrity is maintained by normal design features of the containment, such as the containment isolation valves. In accordance with NEI 12-06 (Reference 2 Section 3.2.1.11), the containment is assumed to be isolated following the event.

BWROG document NEDC-33771P, GEH Evaluation of FLEX Implementation Guidelines has been compared to the Dresden proposed strategies and Modular Accident Analysis Program (MAAP) results. The results of the BWROG document and Dresden response are consistent. In each case at the end of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> the peak containment values are below their respective design limits with significant margins to the limits. Therefore, containment venting to remove heat from the containment is not required. Reliable Hardened Vent System (RHVS) will be available for use to vent containment if necessary. Procedures (References 3, 4 and 5) provide the required directions to accomplish this task. Monitoring of containment (drywell) pressure and temperature will be available via normal plant instrumentation.

2 Coping modifications consist of modifications installed to increase initial coping time, i.e. generators to preserve vital instruments or increase operating time on battery powered equipment.

Page 31 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

References:

1. DR-MISC-043 Revision 1, MAAP Analysis to Support FLEX Initial Strategy.
2. Diverse and Flexible Coping Strategies (FLEX) Implementation Guide, NEI 12-06, Revision 0, August 2012
3. DEOP 0200-01, Primary Containment Control
4. DOA 1600-09, Emergency Containment Venting
5. DEOP 500-4, Containment Venting Details:

Provide a brief Confirm that procedure/guidance exists or will be developed to description of Procedures support implementation

/ Strategies / Guidelines Dresden Station will utilize the industry developed guidance from the Owners Groups, EPRI and NEI Task team to develop site specific procedures or guidelines to address the criteria in NEI 12-06. These procedures and/or guidelines will support the existing symptom based command and control strategies in the current EOPs.

Identify modifications List modifications None Key Containment List instrumentation credited for this coping evaluation.

Parameters Containment Pressure Instrument Power supply PI 2-1640-5 ESS (250VDC supply)

PI 3-1640-5 ESS (250VDC supply)

PR/FR 2-8540-2/4 ESS (250VDC supply)

PR/FR 3-8540-2/4 ESS (250VDC supply)

Suppression Pool Level Instrument Power supply LI 2-1602-3 125VDC 2B1 LI 3-1602-3 125VDC 3B1 Local Sight glass N/A, Local instruments, no power required Suppression Pool Temperature There are no instruments that meet the NEI 12-06 requirements. Temperature will be taken locally at the torus using surface pyrometer.

Page 32 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

DNPS evaluation of the FLEX strategy may identify additional parameters that are needed in order to support key actions identified in the plant procedures/guidance or to indicate imminent or actual core damage (NEI 12-06 Rev. 0, Section 3.2.1.10) and any differences will be communicated in a future six (6) month update following identification.

Notes:

Exelon Generation Company, LLC (Exelon) has not finalized the engineering designs for compliance with NRC Order EA-12-049. Detailed designs based on the current conceptual designs will be developed to determine the final plan and associated mitigating strategies. Analysis will be performed to validate that the plant modifications, selected equipment, and identified mitigating strategy can satisfy the safety function requirements of NEI 12-06. Once these designs and mitigating strategies have been fully developed, Exelon will update the integrated plan for DNPS during a scheduled six (6) month update. This update will include any changes to the initial designs as submitted in the February 28, 2013 Integrated plan (as revised Aug 28, 2013).

Page 33 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Containment BWR Portable Equipment Phase 2:

Provide a general description of the coping strategies using on-site portable equipment including modifications that are proposed to maintain containment. Identify methods (containment vent or alternative / Hydrogen Igniters)and strategy(ies) utilized to achieve this coping time.

Dresden will utilize pre-staged equipment to provide shell-side makeup to the IC prior to the loss of HPCI. Utilization of the IC as the RPV Pressure Control mechanism will eliminate the need for ERV operation and the subsequent heat addition to the containment.

Shell-side makeup to the IC will be established using a proposed pre-staged AC powered FLEX Makeup Pump. The pump suction will be from the Ultimate Heat Sink (UHS) utilizing existing Containment Closed Service Water (CCSW) suction piping. Pump discharge will be directed through a temporary connection to existing Containment Closed Service Water (CCSW) pump discharge piping and then into the Reactor Building. New standpipes will be installed on the CCSW piping to establish valve stations in the Reactor Building. Hoses will be routed from the standpipe valve stations to the following locations, either of which will supply shell-side makeup water to both Isolation Condensers. Therefore, only 1 FLEX Makeup Pump is required to meet the strategy needs for both Units.

1. Primary Strategy The first proposed strategy is associated with the currently installed IC Makeup Pump discharge line. New taps will be installed on the 8 combined discharge piping of the IC Makeup Pumps in the Reactor Building. The taps will include a check valve, gate valve, and quick hose connection to connect to pipe line 2/3-43218-8. Taps will be located on 517 elevation (preferred) and 545 (available during flood conditions) elevations. The primary source will be the Unit 2 FLEX Makeup Pump. This strategy will supply shell-side makeup water to both Isolation Condensers.
2. Alternate Strategy The alternate strategy will be to use the Unit 3 FLEX Makeup Pump and associated CCSW standpipe to supply shell-side makeup water to both Isolation Condensers.

Connection of a FLEX pump via a hose to one of the proposed quick hose connections on the combined IC Makeup Pump combined discharge piping (on the 517 elevation or the 545 elevation in the Reactor Building) allows water from the UHS to be supplied directly to the IC shells with minimal impact on the staffing requirements at Dresden.

These modifications are in diverse locations, and the connection points and piping are qualified for the five Beyond Design Basis External Events (BDBEEs) that must be considered for implementation of FLEX. The proposed FLEX Makeup Pumps will be capable of operating under water and therefore will be available during a flooding event. Additionally, these modifications are designed to supply both the Unit 2 IC and the Unit 3 IC simultaneously. The Pump motors will be powered from 480 VAC Motor Control Centers (MCCs) that are capable of being powered by the FLEX Diesel Generators described in the Page 34 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Containment BWR Portable Equipment Phase 2:

Safety Function Support - Phase 2 section of this submittal.

MAAP analysis (Reference 1, DR_FLEX_CASE11) trends indicate that Drywell Pressure will stabilize below 40 psig and remain there if reactor water level remains above the top of active fuel and the IC remains available. Phase 2 of containment integrity is maintained throughout the duration of the event.

References

1. DR-MISC-043 Revision 1, MAAP Analysis to Support FLEX Initial Strategy.

Details:

Provide a brief Confirm that procedure/guidance exists or will be developed to description of Procedures support implementation

/ Strategies / Guidelines Dresden Station will utilize the industry developed guidance from the Owners Groups, EPRI and NEI Task team to develop site specific procedures or guidelines to address the criteria in NEI 12-06. These procedures and/or guidelines will support the existing symptom based command and control strategies in the current EOPs.

Identify modifications List modifications

1. Installation of new piping and associated connections, valve and flanges, and new connection points in the existing IC shell-side makeup line to allow for the connection of a pre-staged FLEX Makeup pump to provide a path from one Unit for IC shell-side makeup.

(see Attachment 3 Figures 1 and 2)

2. Installation of new piping and associated connections, valve and flanges, to allow for the connection of a pre-staged FLEX Makeup pump to provide a path from the opposite Unit for IC shell-side makeup. This will provide another source of shell-side makeup. (see Attachment 3 Figures 1 and 2)

Key Containment List instrumentation credited or recovered for this coping Parameters evaluation.

Page 35 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Containment BWR Portable Equipment Phase 2:

Containment Pressure Instrument Power supply PI 2-1640-5 ESS (250VDC supply)

PI 3-1640-5 ESS (250VDC supply)

PR/FR 2-8540-2/4 ESS (250VDC supply)

PR/FR 3-8540-2/4 ESS (250VDC supply)

Suppression Pool Level Instrument Power supply LI 2-1602-3 125VDC 2B1 LI 3-1602-3 125VDC 3B1 Local Sight glass N/A, Local instrument, no power required Suppression Pool Temperature Instrument Power supply TIRS2(3)-1640-200A(B) Instrument Bus There are no instruments that meet the NEI 12-06 requirements for flood conditions. Temperature will be taken locally at the torus using surface pyrometer.

Isolation Condenser Shell-side Level Instrument Power supply 2-1301-644 N/A, Local sight-glass, no power required 3-1301-644 N/A, Local sight-glass, no power required 2-1340-2 Instrument Bus (Available for all events except flooding above 517 elevation) 3-1340-2 Instrument Bus (Available for all events except flooding above 517 elevation)

DNPS evaluation of the FLEX strategy may identify additional parameters that are needed in order to support key actions identified in the plant procedures/guidance or to indicate imminent or actual core damage (NEI 12-06 Rev. 0, Section 3.2.1.10) and any differences will be communicated in a future six (6) month update following identification.

Page 36 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Containment BWR Portable Equipment Phase 2:

Storage / Protection of Equipment :

Describe storage / protection plan or schedule to determine storage requirements Seismic List how equipment is protected or schedule to protect Structures to provide protection of FLEX equipment will be constructed to meet the requirements of NEI 12-06 Section 11.

Schedule to construct permanent building is contained in Attachment 2, and will satisfy the site compliance date.

Temporary locations will be used until building construction completion. Procedures and programs will be developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the external hazards applicable to DNPS.

Pre-staged Phase 2 equipment and associated connections will be located in robust structures. The FLEX Generators will be located in a robust structure above the Unit 2 HRSS Building.

The FLEX Makeup Pumps will be located in the Turbine Building below grade level. The connections for electrical and mechanical functions will be in the robust structure above Unit 2 HRSS, the Reactor Building or the Turbine Building.

Flooding List how equipment is protected or schedule to protect Note: if stored below current flood level, then ensure procedures exist to move equipment prior to exceeding flood level. Structures to provide protection of FLEX equipment will be constructed to meet the requirements of NEI 12-06 Section 11.

Schedule to construct permanent building is contained in Attachment 2, and will satisfy the site compliance date.

Temporary locations will be used until building construction completion. Procedures and programs will be developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the external hazards applicable to DNPS.

FLEX equipment can be stored below flood level at DNPS since sufficient warning time is available to relocate and/or deploy the equipment. Plant procedures/guidance will be developed to address the needed actions. FLEX equipment will be relocated to a position that is protected from the flood, either by barriers or by elevation, prior to the arrival of the potentially damaging flood levels. Both electrical and at least one mechanical FLEX connection locations will be above the flood plain. At least one fuel oil storage tank will be protected from Page 37 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Containment BWR Portable Equipment Phase 2:

flood conditions.

Pre-staged Phase 2 equipment will be located in areas above the flood level (such as FLEX Generator) or capable of operating submerged (FLEX Makeup Pump). During flood preparations the appropriate connections and equipment set-up will be completed such that actions to support core cooling will be completed before the flood level reaches 517 elevation.

Severe Storms with High List how equipment is protected or schedule to protect Winds Structures to provide protection of FLEX equipment will be constructed to meet the requirements of NEI 12-06 Section 11.

Schedule to construct permanent building is contained in Attachment 2, and will satisfy the site compliance date.

Temporary locations will be used until building construction completion. Procedures and programs will be developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the external hazards applicable to DNPS.

Pre-staged Phase 2 equipment and associated connections will be located in robust structures. The FLEX Generators will be located in a robust structure above the Unit 2 HRSS Building.

The FLEX Makeup Pumps will be located in the Turbine Building below grade level. The connections for electrical and mechanical functions will be in the robust structure above Unit 2 HRSS, the Reactor Building or the Turbine Building.

Snow, Ice, and Extreme List how equipment is protected or schedule to protect Cold Structures to provide protection of FLEX equipment will be constructed to meet the requirements of NEI 12-06 Section 11.

Schedule to construct permanent building is contained in Attachment 2, and will satisfy the site compliance date.

Temporary locations will be used until building construction completion. Procedures and programs will be developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the external hazards applicable to DNPS.

Pre-staged Phase 2 equipment and associated connections will be located in robust structures. The FLEX Generators will be Page 38 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Containment BWR Portable Equipment Phase 2:

located in a robust structure above the Unit 2 HRSS Building.

The FLEX Makeup Pumps will be located in the Turbine Building below grade level. The connections for electrical and mechanical functions will be in the robust structure above Unit 2 HRSS, the Reactor Building or the Turbine Building.

High Temperatures List how equipment is protected or schedule to protect Structures to provide protection of FLEX equipment will be constructed to meet the requirements of NEI 12-06 Section 11.

Schedule to construct permanent building is contained in Attachment 2, and will satisfy the site compliance date.

Temporary locations will be used until building construction completion. Procedures and programs will be developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the external hazards applicable to DNPS.

Pre-staged Phase 2 equipment and associated connections will be located in robust structures. The FLEX Generators will be located in a robust structure above the Unit 2 HRSS Building.

The FLEX Makeup Pumps will be located in the Turbine Building below grade level. The connections for electrical and mechanical functions will be in the robust structure above Unit 2 HRSS, the Reactor Building or the Turbine Building.

Deployment Conceptual Design (Attachment 3 contains Conceptual Sketches)

Strategy Modifications Protection of connections Identify Strategy including how Identify modifications Identify how the the equipment will be deployed connection is protected to the point of use.

For the primary and alternate Deployment to use the FLEX FLEX pump piping strategy (for IC shell-side pumps for IC Makeup will connections will be makeup), FLEX pumps will be consist of connecting the protected in the area of pre-staged on each unit in the discharge piping as well as the the existing CCSW area of the CCSW pumps. The electrical power supply for the pumps located in a lower FLEX Pumps will take suction 480 VAC motor (provided by elevation of the Turbine from the UHS source available FLEX portable generator building.

at the CCSW pumps and will through existing 480 VAC be connected to the discharge buses). Necessary Electrical connections for Page 39 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Containment BWR Portable Equipment Phase 2:

of a CCSW pump on each unit. modifications for deployment the FLEX 480 VAC The CCSW discharge piping include: generator are will be modified by the Pre-stage 480 VAC conceptually planned to installation of a standpipe in the FLEX pumps near the be located in a structure Reactor Building with valve CCSW Pumps above the Unit 2 High manifolds which will be Install suction and Radiation Sampling connected to the IC Makeup discharge piping for System (HRSS) Building system. pre-staged FLEX pumps and in the Reactor to allow timely Building. Both locations connection are robust against the Install electrical supply designated FLEX to pre-staged FLEX initiating conditions.

pumps to allow timely connection Preliminary review indicates all connections to support the Primary strategy will be inside the current Station power block and therefore inside robust structures. To provide response during flood conditions, appropriate components will be capable of operating submerged and connections above the flood level will be available.

FLEX piping, valves, and connections (electrical &

fluid) will meet NEI 12-06 Rev.0 protection requirements.

Notes:

Exelon Generation Company, LLC (Exelon) has not finalized the engineering designs for compliance with NRC Order EA-12-049. Detailed designs based on the current conceptual designs will be developed to determine the final plan and associated mitigating strategies. Analysis will be performed to validate that the plant modifications, selected equipment, and identified mitigating strategy can satisfy the safety function requirements of Page 40 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Containment BWR Portable Equipment Phase 2:

NEI 12-06. Once these designs and mitigating strategies have been fully developed, Exelon will update the integrated plan for DNPS during a scheduled six (6) month update. This update will include any changes to the initial designs as submitted in the February 28, 2013 Integrated plan (as revised Aug 28, 2013).

Page 41 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Containment BWR Portable Equipment Phase 3:

Provide a general description of the coping strategies using phase 3 equipment including modifications that are proposed to maintain containment. Identify methods (containment vent or alternative /

Hydrogen Igniters) and strategy(ies) utilized to achieve this coping time.

Phase 1 and 2 strategy will provide sufficient capability that no additional Phase 3 strategies are required.

In the event additional equipment is needed portable pumps and generators can utilize the connection points installed in Phase 2 modifications to provide the necessary flow and pressure as outlined in Phase 2 response.

Details:

Provide a brief Confirm that procedure/guidance exists or will be developed to description of Procedures support implementation

/ Strategies / Guidelines DNPS will use the industry developed guidance from the Owners Groups, EPRI and NEI Task team to develop site specific procedures or guidelines to address the criteria in NEI 12-06. These procedures and/or guidelines will support the existing symptom based command and control strategies in the current EOPs.

Identify modifications List modifications None Key Containment List instrumentation credited or recovered for this coping Parameters evaluation.

DNPS evaluation of the FLEX strategy may identify additional parameters that are needed in order to support key actions identified in the plant procedures/guidance or to indicate imminent or actual core damage (NEI 12-06 Rev. 0, Section 3.2.1.10) and any differences will be communicated in a future six (6) month update following identification.

Deployment Conceptual Design (Attachment 3 contains Conceptual Sketches)

Strategy Modifications Protection of connections Identify Strategy including how Identify modifications Identify how the the equipment will be deployed connection is protected to the point of use.

Page 42 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Containment BWR Portable Equipment Phase 3:

None None None Notes:

Exelon Generation Company, LLC (Exelon) has not finalized the engineering designs for compliance with NRC Order EA-12-049. Detailed designs based on the current conceptual designs will be developed to determine the final plan and associated mitigating strategies. Analysis will be performed to validate that the plant modifications, selected equipment, and identified mitigating strategy can satisfy the safety function requirements of NEI 12-06. Once these designs and mitigating strategies have been fully developed, Exelon will update the integrated plan for DNPS during a scheduled six (6) month update. This update will include any changes to the initial designs as submitted in the February 28, 2013 Integrated plan (as revised Aug 28, 2013).

Page 43 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Spent Fuel Pool Cooling Determine Baseline coping capability with installed coping3 modifications not including FLEX modifications, utilizing methods described in Table 3-1 of NEI 12-06:

Makeup with Portable Injection Source BWR Installed Equipment Phase 1:

Provide a general description of the coping strategies using installed equipment including modifications that are proposed to maintain spent fuel pool cooling. Identify methods (makeup with portable injection source)and strategy(ies) utilized to achieve this coping time There are no phase 1 actions required at this time that need to be addressed.

The spent fuel pool has been designed to withstand the anticipated earthquake loadings as a Class I structure. Each unit has its own spent fuel pool measuring 33 ft x 41 ft. Each pool is a reinforced concrete structure, completely lined with seam-welded stainless steel plates welded to reinforcing members (channels, I beams, etc.) embedded in concrete. The normal depth of water in the spent fuel pool is 37 feet, 9 inches and the depth of water in the transfer canal during refueling is 22 feet, 9 inches. (Reference 1, Section 9.1.2.2.3)

EC 371913 (Reference 2) was revised to incorporate a review of Spent Fuel Pool response to an ELAP. At initial conditions, the spent fuel pool is at 19 ft above the top of active fuel (minimum level per Tech Spec). The loss of all AC Power Sources causes a loss of forced circulation and heat removal.

Spent Fuel Pool (SFP) make-up is not a time constraint with the initial condition of Mode 1 @ 100% power, since the worst case fuel pool heat load conditions only exist during a refueling outage. Under non-outage conditions, the maximum SFP heat load is 14.912 MBtu/hr. Loss of SFP cooling with this heat load and an initial SFP temperature of 150 degrees F results in a time to boil of 9.54 hours6.25e-4 days <br />0.015 hours <br />8.928571e-5 weeks <br />2.0547e-5 months <br />, and 110.07 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> to the top of active fuel.

Therefore completing the equipment line-up for initiating SFP make-up at 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> into the event ensures adequate cooling of the spent fuel is maintained.

The worst case SFP heat load during an outage is 39.688 MBtu/hr. Loss of SFP cooling with this heat load and an initial SFP temperature of 150 degrees F results in a time to boil of 3.58 hours6.712963e-4 days <br />0.0161 hours <br />9.589947e-5 weeks <br />2.2069e-5 months <br />, and 41.36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> to the top of active fuel. With the entire core being located in the SFP, manpower resources normally allocated to core cooling along with the Operations outage shift manpower can be allocated to aligning SFP make-up which ensures the system alignment can be established prior to the point at which SFP conditions become challenged. Therefore completing the equipment line-up for initiating SFP make-up at 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> into the event ensures adequate cooling of the spent fuel is maintained.

3 Coping modifications consist of modifications installed to increase initial coping time, i.e. generators to preserve vital instruments or increase operating time on battery powered equipment.

Page 44 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Evaluation of the spent fuel pool area for steam and condensation has not yet been performed.

The results of this evaluation and the vent path strategy, if needed, will be provided in a future six (6) month update.

References:

1. Dresden Nuclear Power Station Updated Final Safety Analysis Report, Revision 9
2. EC 371913, Revision 2,: Time-to-Boil Curves Details:

Provide a brief The station procedure to respond to a loss of cooling in the description of Procedures spent fuel pool is DOA 1900-01 Loss of Fuel Pool Cooling.

/ Strategies / Guidelines Furthermore, time-to-boil curves are contained in Attachments O and P of OP-DR-104-1001 Shutdown Risk Management Contingency Plans, which were prepared in accordance with OP-AA-108-117-1001 Spent Fuel Storage Pools Heat-Up Rate with Loss of Normal Cooling. Inputs and assumptions are identified in EC EVAL 371913, Rev.02 Time-to-Boil Curves Dresden Station will utilize the industry developed guidance from the Owners Groups, EPRI and NEI Task team to develop site specific procedures or guidelines to address the criteria in NEI 12-06. These procedures and/or guidelines will support the existing symptom based command and control strategies in the current EOPs.

Identify any equipment N/A modifications Key SFP Parameter Spent Fuel Pool Level Instrumentation will be installed in accordance with NRC Order EA 12-051.

DNPS evaluation of the FLEX strategy may identify additional parameters that are needed in order to support key actions identified in the plant procedures/guidance or to indicate imminent or actual core damage (NEI 12-06 Rev. 0, Section 3.2.1.10) and any differences will be communicated in a future six (6) month update following identification.

Notes:

Exelon Generation Company, LLC (Exelon) has not finalized the engineering designs for compliance with NRC Order EA-12-049. Detailed designs based on the current conceptual designs will be developed to determine the final plan and associated mitigating strategies. Analysis will be performed to validate that the plant modifications, selected equipment, and identified mitigating strategy can satisfy the safety function requirements of NEI 12-06. Once these designs and mitigating strategies have been fully developed, Exelon will update the integrated plan for DNPS during a scheduled six (6) month update. This update will include any changes to the initial designs as submitted in the February 28, 2013 Integrated plan (as revised Aug 28, 2013).

Page 45 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Spent Fuel Pool Cooling BWR Portable Equipment Phase 2:

Provide a general description of the coping strategies using on-site portable equipment including modifications that are proposed to maintain spent fuel pool cooling. Identify methods (makeup with portable injection source) and strategy(ies) utilized to achieve this coping time.

Dresden Nuclear Power Station (DNPS) personnel will line-up a proposed pre-staged AC powered FLEX Makeup Pump to supply water to the spent fuel pool (SFP). The pump suction will be from the Ultimate Heat Sink (UHS) utilizing existing Containment Closed Service Water (CCSW) suction piping. Pump discharge will be directed through a temporary connection to existing Containment Closed Service Water (CCSW) pump discharge piping and then into the Reactor Building. New standpipes will be installed on the CCSW piping to establish valve stations in the Reactor Building. Hoses will be routed from the standpipe valve stations to a proposed modification on the SFP cooling discharge header. Due to the proposed location of the standpipes and the capacity of the proposed pumps, 1 FLEX Makeup Pump is capable of supplying makeup to both Units Spent Fuel Pools. The modification of the SFP cooling discharge header will consist of connecting into the Shutdown Cooling (SDC) piping to the SFP return. A new manual valve and check valve along with appropriate piping will be installed for this strategy. Opening installed manual valve 2(3)-1901-64 then provides a flow path into the fuel pool. Starting the Flex Pump and throttling a manual valve at the standpipe connection being used (517 or 545 elevation) will control makeup flow into the spent fuel pool without accessing the refueling floor.

Additionally spray cooling of the fuel pool via portable monitor nozzles and makeup directly to the fuel pool using hoses on the refuel floor is available per 50.54 (hh)(2) requirements.

Given the initial conditions of the FLEX event, this strategy will be required to utilize the pump suction lift mode with a water source such as a cooling canal or the UHS instead of a flooded suction from the fire header. DOP 0010-14 provides direction for use of the B.5.b pump using suction lift from a source other than the fire header. EC 371626 (Reference 1) identifies the B.5.b pump is capable of providing the required flows to each fuel pool when operating in the suction lift mode.

Evaluation of the spent fuel pool area for steam and condensation has not yet been performed.

The results of this evaluation and the vent path strategy will be provided in a future six (6) month update.

References:

1. EC 371626, Validation of Hydraulic Capabilities of B5B Pump Schedule:

Provide a brief Confirm that procedure/guidance exists or will be developed to description of Procedures support implementation

/ Strategies / Guidelines Page 46 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Spent Fuel Pool Cooling BWR Portable Equipment Phase 2:

Dresden Station will utilize the industry developed guidance from the Owners Groups, EPRI and NEI Task team to develop site specific procedures or guidelines to address the criteria in NEI 12-06. These procedures and/or guidelines will support the existing symptom based command and control strategies in the current EOPs.

Identify modifications List modifications

1. Installation of new piping and associated connections, valve and flanges, and new connection points in the existing Spent Fuel Pool Cooling Return Line from Shutdown Cooling to allow for the connection of a pre-staged FLEX Makeup pump to provide a path for Spent Fuel Pool makeup. (see Attachment 3 Figures 1 and 5).

Spent Fuel Pool Level Instrumentation will be installed in accordance with NRC Order EA 12-051.

Key SFP Parameter Spent Fuel Pool Level Instrumentation will be installed in accordance with NRC Order EA 12-051.

DNPS evaluation of the FLEX strategy may identify additional parameters that are needed in order to support key actions identified in the plant procedures/guidance or to indicate imminent or actual core damage (NEI 12-06 Rev. 0, Section 3.2.1.10) and any differences will be communicated in a future six (6) month update following identification.

Storage / Protection of Equipment :

Describe storage / protection plan or schedule to determine storage requirements Seismic List how equipment is protected or schedule to protect Structures to provide protection of FLEX equipment will be constructed to meet the requirements of NEI 12-06 Section 11.

Schedule to construct permanent building is contained in Attachment 2, and will satisfy the site compliance date.

Temporary locations will be used until building construction completion. Procedures and programs will be developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the external hazards applicable to DNPS.

Page 47 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Spent Fuel Pool Cooling BWR Portable Equipment Phase 2:

Pre-staged Phase 2 equipment and associated connections will be located in robust structures. The FLEX Generators will be located in a robust structure above the Unit 2 HRSS Building.

The FLEX Makeup Pumps will be located in the Turbine Building below grade level. The connections for electrical and mechanical functions will be in the robust structure above Unit 2 HRSS, the Reactor Building or the Turbine Building.

Flooding List how equipment is protected or schedule to protect Note: if stored below current flood level, then ensure procedures exist to move equipment prior to exceeding flood level. Structures to provide protection of FLEX equipment will be constructed to meet the requirements of NEI 12-06 Section 11.

Schedule to construct permanent building is contained in Attachment 2, and will satisfy the site compliance date.

Temporary locations will be used until building construction completion. Procedures and programs will be developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the external hazards applicable to DNPS.

FLEX equipment can be stored below flood level at DNPS since sufficient warning time is available to relocate and/or deploy the equipment. Plant procedures/guidance will be developed to address the needed actions. FLEX equipment will be relocated to a position that is protected from the flood, either by barriers or by elevation, prior to the arrival of the potentially damaging flood levels. At least one mechanical FLEX connection location for Spent Fuel Pool Makeup will be above the flood plain. At least one fuel oil storage tank will be protected from flood conditions.

Pre-staged Phase 2 equipment will be located in areas above the flood level (such as FLEX Generator) or capable of operating submerged (FLEX Makeup Pump). During flood preparations the appropriate connections and equipment set-up will be completed such that actions to support core cooling will be completed before the flood level reaches 517 elevation.

Severe Storms with High List how equipment is protected or schedule to protect Winds Structures to provide protection of FLEX equipment will be constructed to meet the requirements of NEI 12-06 Section 11.

Page 48 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Spent Fuel Pool Cooling BWR Portable Equipment Phase 2:

Schedule to construct permanent building is contained in Attachment 2, and will satisfy the site compliance date.

Temporary locations will be used until building construction completion. Procedures and programs will be developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the external hazards applicable to DNPS.

Pre-staged Phase 2 equipment and associated connections will be located in robust structures. The FLEX Generators will be located in a robust structure above the Unit 2 HRSS Building.

The FLEX Makeup Pumps will be located in the Turbine Building below grade level. The connections for electrical and mechanical functions will be in the robust structure above Unit 2 HRSS, the Reactor Building or the Turbine Building.

Snow, Ice, and Extreme List how equipment is protected or schedule to protect Cold Structures to provide protection of FLEX equipment will be constructed to meet the requirements of NEI 12-06 Section 11.

Schedule to construct permanent building is contained in Attachment 2, and will satisfy the site compliance date.

Temporary locations will be used until building construction completion. Procedures and programs will be developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the external hazards applicable to DNPS.

Pre-staged Phase 2 equipment and associated connections will be located in robust structures. The FLEX Generators will be located in a robust structure above the Unit 2 HRSS Building.

The FLEX Makeup Pumps will be located in the Turbine Building below grade level. The connections for electrical and mechanical functions will be in the robust structure above Unit 2 HRSS, the Reactor Building or the Turbine Building.

High Temperatures List how equipment is protected or schedule to protect Structures to provide protection of FLEX equipment will be constructed to meet the requirements of NEI 12-06 Section 11.

Schedule to construct permanent building is contained in Attachment 2, and will satisfy the site compliance date.

Page 49 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Spent Fuel Pool Cooling BWR Portable Equipment Phase 2:

Temporary locations will be used until building construction completion. Procedures and programs will be developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the external hazards applicable to DNPS.

Pre-staged Phase 2 equipment and associated connections will be located in robust structures. The FLEX Generators will be located in a robust structure above the Unit 2 HRSS Building.

The FLEX Makeup Pumps will be located in the Turbine Building below grade level. The connections for electrical and mechanical functions will be in the robust structure above Unit 2 HRSS, the Reactor Building or the Turbine Building.

Deployment Conceptual Design (Attachment 3 contains Conceptual Sketches)

Strategy Modifications Protection of connections Identify Strategy including how Identify modifications Identify how the the equipment will be deployed connection is protected to the point of use.

For the primary Spent Fuel Deployment to use the FLEX FLEX pump piping Pool makeup strategy, FLEX pumps for Spent Fuel Pool connections will be pumps will be pre-staged on makeup will consist of protected in the area of each unit in the area of the connecting the discharge piping the existing CCSW CCSW pumps. The FLEX as well as the electrical power pumps located in a lower Pumps will take suction from supply for the 480 VAC motor elevation of the Turbine the UHS source available at the (provided by FLEX portable building.

CCSW pumps and will be generator through existing 480 connected to the discharge of a VAC buses). Necessary Electrical connections for CCSW pump on each unit. The modifications for deployment the FLEX 480 VAC CCSW discharge piping will be include: generator are modified by the installation of a Pre-stage 480 VAC FLEX conceptually planned to standpipe in the Reactor pumps near the CCSW be located in a structure Building with valve manifolds Pumps above the Unit 2 High which will be connected via Install suction and Radiation Sampling hoses to the existing Spent Fuel discharge piping for pre- System (HRSS) Building Pool Cooling Return Line from staged FLEX pumps to and in the Reactor Shutdown Cooling. allow timely connection Building. Both locations Install electrical supply to are robust against the pre-staged FLEX pumps to designated FLEX allow timely connection initiating conditions.

Page 50 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Spent Fuel Pool Cooling BWR Portable Equipment Phase 2:

Preliminary review indicates all connections to support the Primary strategy will be inside the current Station power block and therefore inside robust structures. To provide response during flood conditions, appropriate components will be capable of operating submerged and connections above the flood level will be available.

FLEX piping, valves, and connections (electrical &

fluid) will meet NEI 12-06 Rev.0 protection requirements.

Notes:

Exelon Generation Company, LLC (Exelon) has not finalized the engineering designs for compliance with NRC Order EA-12-049. Detailed designs based on the current conceptual designs will be developed to determine the final plan and associated mitigating strategies. Analysis will be performed to validate that the plant modifications, selected equipment, and identified mitigating strategy can satisfy the safety function requirements of NEI 12-06. Once these designs and mitigating strategies have been fully developed, Exelon will update the integrated plan for DNPS during a scheduled six (6) month update. This update will include any changes to the initial designs as submitted in the February 28, 2013 Integrated plan (as revised Aug 28, 2013).

Page 51 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Spent Fuel Pool Cooling BWR Portable Equipment Phase 3:

Provide a general description of the coping strategies using phase 3 equipment including modifications that are proposed to maintain spent fuel pool cooling. Identify methods (makeup with portable injection source)and strategy(ies) utilized to achieve this coping time.

Phase 1 and 2 strategy will provide sufficient capability that no additional Phase 3 strategies are required.

In the event additional equipment is needed portable pumps can utilize the connection points installed in Phase 2 modifications to provide the necessary flow and pressure as outlined in Phase 2 response.

Schedule:

Provide a brief Confirm that procedure/guidance exists or will be developed to description of Procedures support implementation

/ Strategies / Guidelines DNPS will use the industry developed guidance from the Owners Groups, EPRI and NEI Task team to develop site specific procedures or guidelines to address the criteria in NEI 12-06. These procedures and/or guidelines will support the existing symptom based command and control strategies in the current EOPs.

Identify modifications List modifications None Key SFP Parameter DNPS evaluation of the FLEX strategy may identify additional parameters that are needed in order to support key actions identified in the plant procedures/guidance or to indicate imminent or actual core damage (NEI 12-06 Rev. 0, Section 3.2.1.10) and any differences will be communicated in a future six (6) month update following identification.

Deployment Conceptual Design (Attachment 3 contains Conceptual Sketches)

Strategy Modifications Protection of connections Identify Strategy including how Identify modifications Identify how the the equipment will be deployed connection is protected to the point of use.

Page 52 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Maintain Spent Fuel Pool Cooling BWR Portable Equipment Phase 3:

None None None Notes:

Exelon Generation Company, LLC (Exelon) has not finalized the engineering designs for compliance with NRC Order EA-12-049. Detailed designs based on the current conceptual designs will be developed to determine the final plan and associated mitigating strategies. Analysis will be performed to validate that the plant modifications, selected equipment, and identified mitigating strategy can satisfy the safety function requirements of NEI 12-06. Once these designs and mitigating strategies have been fully developed, Exelon will update the integrated plan for DNPS during a scheduled six (6) month update. This update will include any changes to the initial designs as submitted in the February 28, 2013 Integrated plan (as revised Aug 28, 2013).

Page 53 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Safety Functions Support Determine Baseline coping capability with installed coping4 modifications not including FLEX modifications.

BWR Installed Equipment Phase 1 Provide a general description of the coping strategies using installed equipment including station modifications that are proposed to maintain and/or support safety functions. Identify methods and strategy(ies) utilized to achieve coping times.

HPCI Room Habitability Preliminary GOTHIC analysis indicates opening doors at 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> will result in acceptable room temperature values to support operation of HPCI for at least 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />. The GOTHIC analysis indicates the temperature is approximately 155ºF after 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> which is below the lowest Group 4 Isolation Point of 162ºF specified in DIS 2300-07 (Reference 1)

Main Control Room Habitability In the event of an ELAP event Main Control Room Habitability will be maintained using the guidance of DOA 5750-1 (Reference 2, Attachment A). The actions entail opening multiple doors inside and outside the Main Control Room to establish an air flow path through the room. The applicable actions are initiated after Main Control Room temperature exceeds 95°F and are expected to maintain temperature less than 120°F during Phase 1.

Battery Room Ventilation It is expected that the rise in temperature in the Safety Related Battery Rooms due to the loss of ventilation will not adversely affect the functionality of the batteries (Reference 3).

References:

1. DIS 2300-07, Rev 20, HIGH PRESSURE COOLANT INJECTION AREA TEMPERATURE SWITCH CALIBRATION.
2. DOA 5750-01, Ventilation System Failure, (Revision 58)
3. EC 350067, The effects of elevated temperatures on the Unit 3 Station Batteries.

4 Coping modifications consist of modifications installed to increase initial coping time, i.e. generators to preserve vital instruments or increase operating time on battery powered equipment.

Page 54 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Details:

Provide a brief Confirm that procedure/guidance exists or will be developed to description of support implementation.

Procedures / Strategies /

Guidelines Dresden Station will utilize the industry developed guidance from the Owners Groups, EPRI and NEI Task team to develop site specific procedures or guidelines to address the criteria in NEI 12-06. These procedures and/or guidelines will support the existing symptom based command and control strategies in the current EOPs.

Identify modifications List modifications and describe how they support coping time.

None Key Parameters List instrumentation credited for this coping evaluation phase.

DNPS evaluation of the FLEX strategy may identify additional parameters that are needed in order to support key actions identified in the plant procedures/guidance or to indicate imminent or actual core damage (NEI 12-06 Rev. 0, Section 3.2.1.10) and any differences will be communicated in a future six (6) month update following identification.

Notes:

Exelon Generation Company, LLC (Exelon) has not finalized the engineering designs for compliance with NRC Order EA-12-049. Detailed designs based on the current conceptual designs will be developed to determine the final plan and associated mitigating strategies. Analysis will be performed to validate that the plant modifications, selected equipment, and identified mitigating strategy can satisfy the safety function requirements of NEI 12-06. Once these designs and mitigating strategies have been fully developed, Exelon will update the integrated plan for DNPS during a scheduled six (6) month update. This update will include any changes to the initial designs as submitted in the February 28, 2013 Integrated plan (as revised Aug 28, 2013).

Page 55 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Safety Functions Support BWR Portable Equipment Phase 2 Provide a general description of the coping strategies using on-site portable equipment including station modifications that are proposed to maintain and/or support safety functions. Identify methods and strategy(ies) utilized to achieve coping times.

Electrical System Support and DC Battery availability The 480VAC power distribution system provides power to the 120VAC Essential Safety Systems (ESS) buses at Dresden. The ESS buses provide power to critical loads for achieving and maintaining safe shutdown, such as battery chargers and instrument panels. The 480VAC power distribution system also consists of Non-ESS buses, which provide power to the Auxiliary Electrical Equipment Room (AEER) and Battery Room HVAC systems. Upon an ELAP, these services would be lost. If power cannot be restored, the ability of the plant to achieve and maintain safe shutdown during a BDBEE would be severely compromised.

The following modifications are being proposed to connect a pre-staged generator to provide power to critical loads. Only one pre-staged generator will be required to supply all current FLEX related loads for both units simultaneously.

1. Primary strategy Install a seismically qualified, disconnect panel in the vicinity of Bus 28 for unit 2 and Bus 38 for unit 3. Note: all future bus references will be stated as unit 2 then (unit 3),

example is Bus 28 (38). One side of the disconnect panel will be connected to Bus 28 (38). The other side of the disconnect panel will have an installed cable to a connection point in the area in which the pre-staged diesel generators will be located.

This end of the cable will terminate in a panel with a quick connection mechanism, which will be standard to coordinate with the connections supplied by the Regional Response Centers (RRCs). During a FLEX event, an operator will plug cables with quick connectors from the pre-staged diesel generator output into the panel. Closing the disconnect switch and starting the pre-staged diesel generator will power bus 28 (38). Once this is completed, closing the installed cross-tie breakers will allow Bus 28 (38) to supply power to Bus 29 (39).. See Appendix 3 Figure 4 for a conceptual drawing of this modification.

2. Alternate strategy Install a second seismically qualified, disconnect panel in the vicinity of Bus 29 (39).

One side of the disconnect panel will be connected to Bus 29 (39). The other side of the disconnect panel will have an installed cable to a connection point in the area in which the pre-staged diesel generators will be located. This end of the cable will terminate in a panel with a quick connection mechanism, which will be standard to coordinate with the connections supplied by the Regional Response Centers (RRCs).

During a FLEX event, an operator will plug cables with quick connectors from the pre-Page 56 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Safety Functions Support BWR Portable Equipment Phase 2 staged diesel generator output into the panel. Closing the disconnect switch and starting the pre-staged diesel generator will power bus 29 (39). Once this is completed, closing the installed cross-tie breakers will allow Bus 29 (39) to supply power to Bus 28 (38). See Appendix 3 Figure 4 for a conceptual drawing of this modification.

The proposed modifications will resolve the problem of supplying power to the Unit critical loads by providing operators with easy connections to facilitate use of a pre-staged diesel generator. Supplying power to the critical loads will meet the requirements of NEI 12-06 for restoring 480VAC power. No additional modifications are required to supply power to the 480VAC power distribution system.

Fuel Oil Supply to Portable Equipment Fuel oil to FLEX Generators will be supplied by the quantity of fuel in the tanks located on the skids of the portable equipment. A modification has been proposed to allow transfer of fuel oil from the 2/3 Emergency Diesel Generator (EDG) main fuel oil storage tank to the area of the proposed FLEX Diesel Generators. See Appendix 3 Figure 6 for a conceptual drawing of this modification.

If onsite diesel fuel reserves are needed to operate temporary equipment, the primary locations to obtain diesel fuel would be to pump fuel directly from the seismically qualified underground fuel oil storage tanks. A FLEX Truck is available with fuel storage tanks. Fuel oil can be pumped to these tanks and then transported to portable equipment locations.

Main Control Room Habitability Exelon Generation Company, LLC (Exelon) intends on maintaining the Operational command and control function within the Main Control Room. Habitability conditions will be evaluated and a strategy will be developed to maintain Main Control Room habitability. The strategy will be submitted in a future six (6) month update.

Auxiliary Equipment Electric Room (AEER) and Battery Room Ventilation Current DNPS procedures provide direction for loss of ventilation in various areas. Further evaluation will be conducted to determine if actions such as staging portable fans are required for long term ELAP. Any differences will be communicated in a future six (6) month update following identification.

Details:

Provide a brief Confirm that procedure/guidance exists or will be developed to description of Procedures support implementation with a description of the procedure /

/ Strategies / Guidelines strategy / guideline.

Page 57 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Safety Functions Support BWR Portable Equipment Phase 2 Dresden Station will utilize the industry developed guidance from the Owners Groups, EPRI and NEI Task team to develop site specific procedures or guidelines to address the criteria in NEI 12-06. These procedures and/or guidelines will support the existing symptom based command and control strategies in the current EOPs.

Identify modifications List modifications necessary for phase 2

1. Installation of a pre-staged FLEX Diesel Generator and associated quick connect capability to supply 480 VAC power to panels located near the ESS Busses.
2. Disconnect panel installation near Bus 28 (38) with associated cabling to provide for connection of a pre-staged or portable AC generator (see Attachment 3 Figure 4)
3. Disconnect panel installation near Bus 29 (39) with associated cabling to provide for connection of a pre-staged or portable AC generator (see Attachment 3 Figure 4)
4. Installation of connection capability and associated temporary hoses from the 2/3 EDG Main Fuel Oil Storage Tank to the area near the pre-staged FLEX Diesel Generators. A pre-staged pump would be connected at the new connection points. The pre-staged pump will be powered from a source capable of being energized by the FLEX Diesel Generator.

Key Parameters List instrumentation credited or recovered for this coping evaluation.

DNPS evaluation of the FLEX strategy may identify additional parameters that are needed in order to support key actions identified in the plant procedures/guidance or to indicate imminent or actual core damage (NEI 12-06 Rev. 0, Section 3.2.1.10) and any differences will be communicated in a future six (6) month update following identification.

Storage / Protection of Equipment :

Describe storage / protection plan or schedule to determine storage requirements Page 58 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Safety Functions Support BWR Portable Equipment Phase 2 Seismic List how equipment is protected or schedule to protect Structures to provide protection of FLEX equipment will be constructed to meet the requirements of NEI 12-06 Section

11. Schedule to construct permanent building is contained in Attachment 2, and will satisfy the site compliance date.

Temporary locations will be used until building construction completion. Procedures and programs will be developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the external hazards applicable to DNPS.

Pre-staged Phase 2 equipment and associated connections will be located in robust structures. The FLEX Generators will be located in a robust structure above the Unit 2 HRSS Building. The connections for electrical functions will be in the robust structure above Unit 2 HRSS, the Reactor Building or the Turbine Building.

Flooding List how equipment is protected or schedule to protect Note: if stored below current flood level, then ensure procedures exist to move equipment prior to exceeding flood level. Structures to provide protection of FLEX equipment will be constructed to meet the requirements of NEI 12-06 Section

11. Schedule to construct permanent building is contained in Attachment 2, and will satisfy the site compliance date.

Temporary locations will be used until building construction completion. Procedures and programs will be developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the external hazards applicable to DNPS.

FLEX equipment can be stored below flood level at DNPS since sufficient warning time is available to relocate and/or deploy the equipment. Plant procedures/guidance will be developed to address the needed actions. FLEX equipment will be relocated to a position that is protected from the flood, either by barriers or by elevation, prior to the arrival of the potentially damaging flood levels. Both electrical and at least one mechanical FLEX connection locations will be above the flood plain. At least one fuel oil storage tank will be protected from flood conditions.

Page 59 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Safety Functions Support BWR Portable Equipment Phase 2 The FLEX Generators will be located above the maximum flood level in a robust structure over the Unit 2 HRSS Building. The connections for electrical functions will be in the robust structure above Unit 2 HRSS, the Reactor Building or the Turbine Building at elevations higher than maximum flood level. During flood preparations the appropriate connections and equipment set-up will be completed such that support actions for the Safety Functions will be completed before the flood level reaches 517 elevation.

Severe Storms with High List how equipment is protected or schedule to protect Winds Structures to provide protection of FLEX equipment will be constructed to meet the requirements of NEI 12-06 Section

11. Schedule to construct permanent building is contained in Attachment 2, and will satisfy the site compliance date.

Temporary locations will be used until building construction completion. Procedures and programs will be developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the external hazards applicable to DNPS.

Pre-staged Phase 2 equipment and associated connections will be located in robust structures. The FLEX Generators will be located in a robust structure above the Unit 2 HRSS Building. The connections for electrical functions will be in the robust structure above Unit 2 HRSS, the Reactor Building or the Turbine Building.

Snow, Ice, and Extreme Cold List how equipment is protected or schedule to protect Structures to provide protection of FLEX equipment will be constructed to meet the requirements of NEI 12-06 Section

11. Schedule to construct permanent building is contained in Attachment 2, and will satisfy the site compliance date.

Temporary locations will be used until building construction completion. Procedures and programs will be developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the external hazards applicable to DNPS.

Pre-staged Phase 2 equipment and associated connections Page 60 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Safety Functions Support BWR Portable Equipment Phase 2 will be located in robust structures. The FLEX Generators will be located in a robust structure above the Unit 2 HRSS Building. The connections for electrical functions will be in the robust structure above Unit 2 HRSS, the Reactor Building or the Turbine Building.

High Temperatures List how equipment is protected or schedule to protect Structures to provide protection of FLEX equipment will be constructed to meet the requirements of NEI 12-06 Section

11. Schedule to construct permanent building is contained in Attachment 2, and will satisfy the site compliance date.

Temporary locations will be used until building construction completion. Procedures and programs will be developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the external hazards applicable to DNPS.

Pre-staged Phase 2 equipment and associated connections will be located in robust structures. The FLEX Generators will be located in a robust structure above the Unit 2 HRSS Building. The connections for electrical functions will be in the robust structure above Unit 2 HRSS, the Reactor Building or the Turbine Building.

Deployment Conceptual Design (Attachment 3 contains Conceptual Sketches)

Strategy Modifications Protection of connections Identify Strategy including how Identify modifications Identify how the the equipment will be deployed connection is protected to the point of use.

Cables from a a pre-staged Electrical power will be Electrical connections for diesel powered generator supplied by a pre-staged FLEX the FLEX 480 VAC located above the U2 HRSS Diesel Generator through generator are Building will be connected to existing 480 VAC buses. conceptually planned to quick connect panel. Output Necessary modifications for be located in a structure cabling from the panel will deployment include: above the Unit 2 High enter the Reactor Building. Install quick connection Radiation Sampling Station personnel will start the capability, associated System (HRSS) Building diesel generator to supply 480 panels and cabling. and in the Reactor VAC power to the ESS Busses Disconnect panels will be Building. Both locations Page 61 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Safety Functions Support BWR Portable Equipment Phase 2 in the Reactor Building. installed at busses 28, 29, are robust against the 38 and 39 to support designated FLEX separation between FLEX initiating conditions.

cabling and permanent plant equipment. Preliminary review indicates all connections to support the Primary strategies will be inside the current Station power block and therefore inside robust structures. To provide response during flood conditions, the connections and associated equipment will be above the maximum flood level.

FLEX piping, valves, and connections (electrical &

fluid) will meet NEI 12-06 Rev.0 protection requirements.

Fuel oil will be transferred Piping modifications will be The connections and from the 2/3 EDG Main Fuel made to the 2/3 EDG Fuel Oil proposed hose routings Oil Storage Tank to support Transfer System to allow are conceptually planned FLEX Diesel Generator connection of a pre-staged to be located in a structure operation. pump and hoses. The hoses above the Unit 2 High will transport fuel oil to the Radiation Sampling FLEX Diesel Generator area System (HRSS) Building, for transfer to the skid mounted in the 2/3 EDG Room and tanks on the diesels. in the Reactor Building which are robust locations.

To provide response during flood conditions, appropriate components will be capable of operating submerged.

Page 62 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Safety Functions Support BWR Portable Equipment Phase 2 Notes:

Exelon Generation Company, LLC (Exelon) has not finalized the engineering designs for compliance with NRC Order EA-12-049. Detailed designs based on the current conceptual designs will be developed to determine the final plan and associated mitigating strategies. Analysis will be performed to validate that the plant modifications, selected equipment, and identified mitigating strategy can satisfy the safety function requirements of NEI 12-06. Once these designs and mitigating strategies have been fully developed, Exelon will update the integrated plan for DNPS during a scheduled six (6) month update. This update will include any changes to the initial designs as submitted in the February 28, 2013 Integrated plan (as revised Aug 28, 2013).

Page 63 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Safety Functions Support BWR Portable Equipment Phase 3 Provide a general description of the coping strategies using phase 3 equipment including modifications that are proposed to maintain and/or support safety functions. Identify methods and strategy(ies) utilized to achieve coping times.

Phase 1 and 2 strategy will provide sufficient capability that no additional Phase 3 strategies are required.

In the event additional equipment is needed portable pumps and generators can utilize the connection points installed in Phase 2 modifications to provide the necessary flow and pressure as outlined in Phase 2 response.

Details:

Provide a brief Confirm that procedure/guidance exists or will be developed to description of Procedures support implementation with a description of the procedure /

/ Strategies / Guidelines strategy / guideline.

DNPS will use the industry developed guidance from the Owners Groups, EPRI and NEI Task team to develop site specific procedures or guidelines to address the criteria in NEI 12-06. These procedures and/or guidelines will support the existing symptom based command and control strategies in the current EOPs.

Identify modifications List modifications necessary for phase 3 None Key Parameters List instrumentation credited or recovered for this coping evaluation.

DNPS evaluation of the FLEX strategy may identify additional parameters that are needed in order to support key actions identified in the plant procedures/guidance or to indicate imminent or actual core damage (NEI 12-06 Rev. 0, Section 3.2.1.10) and any differences will be communicated in a future six (6) month update following identification.

Page 64 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Safety Functions Support BWR Portable Equipment Phase 3 Deployment Conceptual Design (Attachment 3 contains Conceptual Sketches)

Strategy Modifications Protection of connections Identify Strategy including how Identify modifications Identify how the the equipment will be deployed connection is protected to the point of use.

None None None Notes:

Exelon Generation Company, LLC (Exelon) has not finalized the engineering designs for compliance with NRC Order EA-12-049. Detailed designs based on the current conceptual designs will be developed to determine the final plan and associated mitigating strategies. Analysis will be performed to validate that the plant modifications, selected equipment, and identified mitigating strategy can satisfy the safety function requirements of NEI 12-06. Once these designs and mitigating strategies have been fully developed, Exelon will update the integrated plan for DNPS during a scheduled six (6) month update. This update will include any changes to the initial designs as submitted in the February 28, 2013 Integrated plan (as revised Aug 28, 2013).

Page 65 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

BWR Portable Equipment Phase 2 Use and (potential / flexibility) diverse uses Performance Criteria Maintenance List portable Core Containment SFP Instrumentation Accessibility Maintenance / PM equipment requirements Two (2) low X X X Minimum 975 gpm Equipment pressure maintenance and high testing will be capacity performed in submersible accordance with the electrically industry templates, driven as outlined in JLD-pumps ISG-2012-01, Section 6 and NEI 12-06, Section 11.

Two (2) 480 X X X X X Minimum 550 kW Equipment VAC Diesel maintenance and powered testing will be Generators performed in accordance with the industry templates, as outlined in JLD-ISG-2012-01, Section 6 and NEI 12-06, Section 11.

Page 66 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

BWR Portable Equipment Phase 2 Use and (potential / flexibility) diverse uses Performance Criteria Maintenance List portable Core Containment SFP Instrumentation Accessibility Maintenance / PM equipment requirements Heavy Duty X Similar to F-750 with Equipment truck on-board fuel tanks for maintenance and refueling portable testing will be equipment. Used to performed in transport portable accordance with the equipment and clear industry templates, debris as outlined in JLD-ISG-2012-01, Section 6 and NEI 12-06, Section 11.

Six (6) X 42 120V, 2 speed fan Equipment Industrial 13,300 CFM ON HIGH maintenance and blowers AND 9,500 CFM ON testing will be LOW performed in accordance with the industry templates, as outlined in JLD-ISG-2012-01, Section 6 and NEI 12-06, Section 11.

Page 67 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

BWR Portable Equipment Phase 2 Use and (potential / flexibility) diverse uses Performance Criteria Maintenance List portable Core Containment SFP Instrumentation Accessibility Maintenance / PM equipment requirements Ten (10) X 120V Equipment Portable 5200 cfm maintenance and fans with testing will be flexible performed in ducting accordance with the industry templates, as outlined in JLD-ISG-2012-01, Section 6 and NEI 12-06, Section 11.

Ten (10) X 50 Feet long, Equipment light strings maintenance and testing will be performed in accordance with the industry templates, as outlined in JLD-ISG-2012-01, Section 6 and NEI 12-06, Section 11.

Page 68 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

BWR Portable Equipment Phase 2 Use and (potential / flexibility) diverse uses Performance Criteria Maintenance List portable Core Containment SFP Instrumentation Accessibility Maintenance / PM equipment requirements Ten (10) free X General usage Equipment standing maintenance and Flood Lights testing will be with tripod performed in base accordance with the industry templates, as outlined in JLD-ISG-2012-01, Section 6 and NEI 12-06, Section 11.

Six (6) X 5.5 kW Equipment 120/240V maintenance and Portable AC testing will be Generators performed in accordance with the industry templates, as outlined in JLD-ISG-2012-01, Section 6 and NEI 12-06, Section 11.

Page 69 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

BWR Portable Equipment Phase 2 Use and (potential / flexibility) diverse uses Performance Criteria Maintenance List portable Core Containment SFP Instrumentation Accessibility Maintenance / PM equipment requirements Three (3) X General usage Equipment Dewatering maintenance and pumps - testing will be diesel driven performed in accordance with the industry templates, as outlined in JLD-ISG-2012-01, Section 6 and NEI 12-06, Section 11.

Page 70 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

BWR Portable Equipment Phase 3 Use and (potential / flexibility) diverse uses Performance Criteria Notes List portable Core Containment SFP Instrumentation Accessibility equipment Note: The RRC equipment has not been procured at the time of this submittal. Once the SAFER committee determines the equipment specifications for bid, updates will be made as necessary to this table. The Phase 3 portable equipment table will be updated once all of the equipment has been procured and placed in inventory.

Medium X X X X X 2 MW output at Generator must be Voltage 4160VAC, three phase common Diesel commercially Generator available.

Must run on diesel fuel.

Low Voltage X X X X X 500 kW output at Generator must be Diesel 480VAC, three phase common Generator commercially available.

Must run on diesel fuel.

Low Pressure X X X 300 psi shutoff head, Pump 2500 gpm max flow Low Pressure X X 500 psi shutoff head, Pump 500 gpm max flow Low Pressure X 110 psi shutoff head, Pump 400 gpm max flow submersible Page 71 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

BWR Portable Equipment Phase 3 Use and (potential / flexibility) diverse uses Performance Criteria Notes List portable Core Containment SFP Instrumentation Accessibility equipment Low Pressure X X 150 psi shutoff head, Pump 5000 gpm max flow Air X 120 psi minimum Compressor pressure, 2000 scfm Page 72 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Phase 3 Response Equipment/Commodities Item Notes Radiation Protection Equipment The RRC will not stock this type of equipment but this equipment will be requested Survey instruments from site to site and utility to utility on an as required basis.

Dosimetry Off-site monitoring/sampling Commodities The RRC will not stock these commodities but they will be requested from site to Food site and utility to utility on an as required basis.

Potable water Fuel Requirements 300 - 500 gallon bladders that can be delivered by air Heavy Equipment TBD during site specific playbook development Transportation equipment Redundant phase 2 equipment to be located at RRC Debris clearing equipment Page 73 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Attachment 1A Sequence of Events Timeline (insert site specific time line to support submittal)

Action Elapsed Action Time Remarks / Applicability item Time Constraint Y/N 5 0 Event Starts NA Plant @100% power 0 Reactor scram NA Loss of power to Reactor Protection System results in a reactor scram.

1 1 min Personnel enter DGP 02-03 and N These actions will DGA 12 provide direction for reactor control and options for loss of AC power.

2 1 min Isolation Condenser initiated for N DEOP 100 will direct pressure control (or verified action based on operating if auto initiation occurs) reactor pressure.

3 2 mins Attempt to start EDGs upon N Per FLEX event initial identification of failure to auto start. conditions the EDGs are not available.

4 3 mins Attempt to Start IC Makeup Pump N There are no fully for IC Shell side makeup qualified makeup sources for shell-side makeup.

5 5 mins Personnel dispatched to investigate N Per FLEX event initial EDG failure to start. conditions the EDGs are not available.

6 5 mins HPCI initiated for inventory control N HPCI suction will and reactor pressure control (or auto swap to the Torus verified operating if auto initiation due to CSTs being occurs). assumed lost with the FLEX event (not missile protected).

7 10 Attempt to start SBO DG for either N Per FLEX event initial mins Unit conditions the SBO DGs are not available.

5 Instructions: Provide justification if No or NA is selected in the remark column.

If yes, include technical basis discussion as requires by NEI 12-06 section 3.2.1.7 Page 74 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Attachment 1A Sequence of Events Timeline (insert site specific time line to support submittal)

Action Elapsed Action Time Remarks / Applicability item Time Constraint Y/N 5 8 15 Personnel dispatched to investigate N Per FLEX event initial mins SBO DG failure to start. conditions the SBO DGs are not available.

9 15 Perform 125 VDC load shedding per N This is an immediate mins DGA 13 action of DGA 13 to prolong battery availability. Must be completed by 30 minutes after event initiation.

10 20 Isolation Condenser secured due to Y Per UFSAR, the IC mins lack of shell-side makeup. will operate for approximately 20 minutes without shell-side makeup. It is secured to prevent possible damage.

11 30 125 and 250 VDC Load Shed Y DGA 12 Step D.13 mins Completed (actions identified in identifies that load DGA 03, DGA 12 and DGA 13) shedding to maintain battery availability must be completed if DC chargers are unavailable.

12 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> Control Room crew has assessed N Time is reasonable SBO and plant conditions and approximation based declares an Extended Loss of AC on operating crew Power (ELAP) event. assessment of plant Personnel dispatched to FLEX conditions strategy for supplying make-up water to the Isolation Condenser shell-side.

Personnel dispatched to FLEX strategy for supplying power to the FLEX Makeup Pump and station battery chargers.

Page 75 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Attachment 1A Sequence of Events Timeline (insert site specific time line to support submittal)

Action Elapsed Action Time Remarks / Applicability item Time Constraint Y/N 5 13 2 Complete actions for Loss of AEER N Perform DOA 5750-1 hours Ventilation Attachment C Step 6.

Actions can be coordinated with personnel obtaining and staging portable generators, fans, etc.

14 2 Establish natural air flow to HPCI Y Preliminary GOTHIC hours room by opening doors. analysis indicates opening doors at 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> will result in acceptable room temperature values to support operation of HPCI for at least 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />. HPCI room temperature remains below the isolation point during this time.

HPCI operation is assumed for approximately 2.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> in Phase 1.

15 2 Complete actions for loss of Main N DOA 5750-01 actions.

hours Control Room Ventilation.

16 2 Defeat HPCI high temperature and N Ensure HPCI remains hours flow isolations available during the event.

Page 76 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Attachment 1A Sequence of Events Timeline (insert site specific time line to support submittal)

Action Elapsed Action Time Remarks / Applicability item Time Constraint Y/N 5 17 2.5 FLEX strategy for supplying power Y When the busses are hours to 480 VAC busses and associated energized, power will Motor Control Centers (MCCs) be available to the completed. FLEX Makeup Pump.

This will also supply power to battery chargers. Preliminary review indicates the batteries will remain available for at least 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> without chargers.

18 2.5 FLEX pump connected and ready for Y Due to pre-staging of hours use to support Isolation Condenser major components, it shell-side makeup. is reasonable to expect the FLEX pump can be available within this time period.

19 2.5 Isolation Condenser initiated for Y Complete prior to loss hours RPV pressure control of HPCI to ensure RPV heat removal mechanism operating prior to MAAP analysis assumed HPCI loss.

20 2.5 HPCI assumed to fail due to N HPCI may continue to hours suppression pool temperature of operate above 140°F 140°F but it is not relied upon past this point and restoration of the Isolation Condenser will replace the need for HPCI in terms of RPV pressure control.

Page 77 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Attachment 1A Sequence of Events Timeline (insert site specific time line to support submittal)

Action Elapsed Action Time Remarks / Applicability item Time Constraint Y/N 5 21 3 Isolate both Reactor Recirculation N Recirc loops are hours Loops by closing suction and isolated to reduce discharge valves RPV leakage. The sooner this is accomplished the more reactor inventory is conserved.

22 4 Run hoses from CCSW FLEX N Establishing a makeup hours Standpipe on 545 elevation to the source to the tank SBLC Tank. provides continued availability of a high pressure RPV makeup source.

23 4 Initiate SBLC as necessary for RPV N Per MAAP analysis hours level control. after Recirc Loops are isolated and the Isolation Condenser is controlling reactor pressure, RPV leakage will be reduced to approximately 15 gpm at time = 3.0 hours0 days <br />0 hours <br />0 weeks <br />0 months <br />.

Makeup from SBLC can be utilized to maintain RPV level above Top of Active Fuel (TAF).

24 10 Personnel dispatched to establish N Further analysis is hours temporary ventilation to the MCR required to determine and AEER (portable fans and if supplemental associated generators). ventilation is needed.

Page 78 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Attachment 1A Sequence of Events Timeline (insert site specific time line to support submittal)

Action Elapsed Action Time Remarks / Applicability item Time Constraint Y/N 5 25 12 Makeup to the Spent Fuel Pools Y EC 371913, Revision hours using FLEX pump strategy is 2,: Time-to-Boil available. Curves., identifies a time to boil of 9.54 hours6.25e-4 days <br />0.015 hours <br />8.928571e-5 weeks <br />2.0547e-5 months <br />, and 110.07 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> to the top of active fuel. Therefore completing the equipment line-up for initiating SFP make-up at 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> into the event ensures adequate cooling of the spent fuel is maintained.

26 24 Initial equipment from Regional N NEI 12-06 hours Response Center becomes available. assumption.

27 24 Makeup to the RPV using FLEX N SBLC is available as a hours Makeup pump strategy is available. high pressure injection source. Low pressure makeup from FLEX Makeup Pump will not be required before this time.

28 24-72 Continue to maintain critical N None hours functions of core cooling (via IC and FLEX Pump injection), containment (via hardened vent opening) and SFP cooling (FLEX pump injection to SFP). Utilize initial RRC equipment in spare capacity.

Page 79 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Attachment 1B NSSS Significant Reference Analysis Deviation Table NEDC 33771 NEDC33771P P Design Item Parameter of Interest Rev 2 Value Page Plant Applied Value Value Gap and Discussion NEDC33771P Rev 1 Section 4.5.1.1 (BWR/2/3. Mark I and EC System Assumptions) and Table 4.5.21 Appendix A are closest to the Dresden Nuclear Power Station and associated response. Differences between the GEH SHEX case and the MAAP analysis of the Dresden strategy are listed below.

Input Parameter Values 1 Core thermal power Proprietary 15 2957 MWT NA The GEH model BWR 2/3 Mark I reference information. plant has lower core thermal power rating.

Refer to report for value.

2 Primary System Leakage Proprietary 15 61 gpm NA The reference plant has 5 Recirculation information. Loops which results in a higher value for Refer to report Recirc Pump seal leakage. Dresden has 2 for value. Recirculation Loops per reactor.

8 3 Emergency Condenser capacity Proprietary 15 2.52E+10 Btu/hr 2.52E+ The reference plant has 2 Emergency information. 108 Condensers whereas Dresden has 1 Refer to report Btu/hr Isolation Condenser.

for value.

4 Wetwell Free Volume Proprietary 16 110,618 ft3 NA The differences in reference plant information. structural design and minor differences in Refer to report assumed parameter values at time zero for value. should have a negligible effect on the 5 Wetwell airspace temperature Proprietary 16 95°F NA progression of the event after a few hours.

information.

Refer to report for value.

6 Initial Wetwell Pressure Proprietary 16 14.7 psia NA information.

Refer to report for value.

Page 80 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

NEDC 33771 NEDC33771P P Design Item Parameter of Interest Rev 2 Value Page Plant Applied Value Value Gap and Discussion 7 Intial Wetwell humidity Proprietary 16 100% NA information.

Refer to report for value.

8 Suppression Pool Volume Proprietary 16 118,630 ft3 NA information.

Refer to report for value.

9 Suppression Pool initial temperature Proprietary 16 95°F NA information.

Refer to report for value.

10 Drywell Free Volume Proprietary 16 158,236 ft3 NA information.

Refer to report for value.

11 Initial Drywell Temperature Proprietary 16 150°F NA information.

Refer to report for value.

12 Initial Drywell Pressure Proprietary 16 15.7 psia NA information.

Refer to report for value.

13 Initial Drywell Humidity Proprietary 16 50% NA information.

Refer to report for value.

Page 81 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

NEDC 33771 NEDC33771P P Design Item Parameter of Interest Rev 2 Value Page Plant Applied Value Value Gap and Discussion Resultant Parameter Values Maximum Drywell Pressure Proprietary 40 30.3 psia at t0 + 24 62 psig information. hrs Refer to report for value.

Maximum Drywell Temperature Proprietary 40 260°F at t0 + 24 hrs 281°F information.

Refer to report for value.

Maximum Wetwell Pressure Proprietary 40 28.5 psia at t0 + 24 62 psig information. hrs Refer to report for value.

Maximum Wetwell Airspace Proprietary 40 146°F at t0 + 24 hrs 281°F Temperature information.

Refer to report for value.

Maximum Suppression Pool Proprietary 40 140°F at t0 + 24 hrs N/A Temperature information.

Refer to report for value.

Page 82 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation Strategies Integrated Plan (REVISED August 28, 2013)

Attachment 2 Milestone Schedule Site: Dresden Original Target Activity Status Completion Date {Include date changes in this column}

Submit 60 Day Status Report Complete Submit Overall Integrated Complete Implementation Plan Contract with RRC Complete Recurring action, Submit 6 month updates Ongoing Aug and Feb Unit 2 Unit 3 Modification Development Oct 2014 Sept 2015 Phase 1 modifications Note 1 Oct 2014 Sept 2015 Phase 2 modifications Note 1 Oct 2014 Sept 2015 Phase 3 modifications Note 1 Unit 2 Unit 3 Modification Implementation Nov 2015 Nov 2016 Phase 1 modifications Note 1 Nov 2015 Nov 2016 Phase 2 modifications Note 1 Nov 2015 Nov 2016 Phase 3 modifications Note 1 Procedure development Nov 2015 Strategy procedures Note 1 Nov 2015 Validate Strategy Procedures Note 1 (NEI 1206, Sect. 11.4.3)

Nov 2015 Maintenance procedures Note 1 Jul 2015 Staffing analysis Note 1 Nov 2015 Storage Plan and construction Note 1 Nov 2015 FLEX equipment acquisition Note 1 Nov 2015 Training completion Note 1 Jul 2015 Regional Response Center (will be a standard date from Operational RRC)

Nov 2015 Unit 2 Implementation date Note 1 Nov 2016 Unit 3 Implementation date Note 1 Note(s):

1. Exelon will update the status of ongoing and future milestones in the Integrated Plan for DNPS during a scheduled six (6) month update. This update will include any changes to the milestone schedule as submitted in the February 28, 2013 Integrated plan (as revised Aug 28, 2013).

Page 83 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation strategies Integrated Plan (REVISED August 28, 2013)

Attachment 3 Conceptual Sketches Figure 1 - FLEX Makeup Pump Page 84 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation strategies Integrated Plan (REVISED August 28, 2013)

Attachment 3 Conceptual Sketches Figure 2 - Isolation Condenser Shell-side Makeup Page 85 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation strategies Integrated Plan (REVISED August 28, 2013)

Attachment 3 Conceptual Sketches Figure 3 - RPV Makeup Page 86 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation strategies Integrated Plan (REVISED August 28, 2013)

Attachment 3 Conceptual Sketches Figure 4 - Connection of external power source to 480 VAC Distribution Page 87 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation strategies Integrated Plan (REVISED August 28, 2013)

Attachment 3 Conceptual Sketches Figure 5 - Spent Fuel Pool Makeup Page 88 of 89

Dresden Nuclear Power Station, Units 2 and 3 Mitigation strategies Integrated Plan (REVISED August 28, 2013)

Attachment 3 Conceptual Sketches Figure 6 - FLEX Fuel Oil Transfer Page 89 of 89