RA-17-0046, Transmittal of Duke Energy Carolinas (DEC) Physical Security Plan Revision 25 and Duke Energy Progress (DEP) Physical Security Plan Revision 11

From kanterella
Jump to navigation Jump to search
Transmittal of Duke Energy Carolinas (DEC) Physical Security Plan Revision 25 and Duke Energy Progress (DEP) Physical Security Plan Revision 11
ML17293A032
Person / Time
Site: Oconee, Mcguire, Catawba, Harris, Brunswick, Robinson, McGuire, 07200006, 07200040, 07200003, 07200060  Duke energy icon.png
Issue date: 10/17/2017
From: Nolan M
Duke Energy Carolinas
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation
References
RA-17-0046
Download: ML17293A032 (8)


Text

M. *Christopher Nolan 526 South Church Street SAFEGUARDS INFORMATION

  • Charlotte, NC 28202 When separated, this page is decontroiled.

Mailing Address:

Mail Code. EC2ZF IP. 0. Box 1006 Charlotte, NC 28201-1006 704-382-7426 10 CFR 50.'4 10 CFR 50.54(p) 10 CFR 72.44(e) 10 CFR 72.186(bj..

Serial: RA-17-0046 October 17, 2017 U.S. Nuclear Regulatory Attn: Document Control Desk Washington, DC 20555-0001 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS .. 1AND2 DOCKET NOS. 50-325 AND 50-324 /RENEWED LICENSE NOS. DPR-71 AND DPR~62 BRUNSWICK INDEPENDENT SPENT FUEL STORAGE INSTALLATION DOCKET NO. 72-6 CATAWBA NUCLEAR STATION, UNITS 1AND2 DOCKET NOS. 50-413 AND 50-414 /,RENEWED LICENSE NOS. NPF-35 AND NPF-52 CATAWBA NUCLEAR STATION INDEPENDENT SPENT FUEL STORAGE INSTALLATION DOCKET NO. 72-45 H.B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2

.DOCKET NO. 50-261 I RENEWED LICENSE NO. DPR-23

.H.B. ROBINSON INDEPE~DENT SPENT FUEL STORAGE INSTALLATION DOCKET NO. 72-3 I LICENSE NO. SNM-2502

  • H.B. ROBINSON INDEPENDENT SPENT FUEL STORAGE INSTALLATION DOCKET NO. 72-60 MCGUIRE NUCLEAR STATION, UNITS 1 AND 2 DOCKET NOS: 50-369 AND 50-370 I RENEWED LICENSE NOS. NPF-9 AND NPF-17 MCGUIRE NUCLEAR STATION INDEPENDENT SPENT FUEL STORAGE INSTALLATION DOCKET NO. 72-38 SoDI OCONEE NUCLEAR STATION, UNIT NOS ..1, 2 AND 3 DOCKET NOS .. 50-269,*50-270 AND 50-287 / RENEWED LICENSE NOS. DPR-38, DPR-47 ~;JJ55Z(p AND DPR-55 SAFEGUARDS INFORMATION . ;JJJ155
if~~

When separated, this page is decontrolled.

SAFEGUARDS INFORMATION When separated, this page is decontrolled.

U.S. Nuclear Regulatory Commission RA-17-0046 Page 2 of 6 OCONEE NUCLEAR STATION INDEPENDENT SPENT FUEL STORAGE INSTALLATION

  • DOCKET NO. 72-04/ LICENSE NO. SNM-2503 OCONEE NUCLEAR STATION INDEPENDENT SPENT FUEL STORAGE INSTALLATION DOCKET NO. 72-40 SHEARON HARRIS NUCLEAR POWER PLANT, UNIT NO. 1 DOCKET NO. 50-400 I RENEWED LICENSE NO. NPF-63 SubjeGt: TRANSMITTAL OF DUKE ENERGY CAROLINAS (DEC) PHYSICAL SECURITY PLAN REVISION 25 AND DUKE ENERGY PROGRESS (DEP)

PHYSICAL SECURITY PLAN REVISION 11 In accordance with 10 CFR 50.4(b)(4)(iii), 10 CFR 50.54(p)(2) and 10 CFR 72.44(e), Duke Energy provides notification that Brunswick' Steam Electric Plant, Units 1 and 2, Catawba Nuclear Station, Units 1 and 2, H. B. Robinson Steam Electric Plant Unit 2, McGuire Nuclear Station, Units 1 and 2, Oconee Nuclear Station, Units 1, 2 and 3 and Shearon Harris Nuclear Power Plant, Unit 1, Physical Security Plans, Security Training and Qualification Plan, Safeguards Contingency Plan and Independent Spent Fuel Storage Installation Security

  • Programs have been revised. The effective date of implementation for Revisions 25 and .11, respectively, were August 31, 2017.

This letter includes three enclosures which contain Safeguards Information as defined in 10 CFR 73.2 and must be protected from unauthorized disclosure in accordance With 10 CFR 73.21. Enclosure 1 contains a summary 'description of the Physical Security Plan revision changes. Enelosure 2 contains a copy of Duke Energy Carolinas - Catawba, McGuire and Oconee Nuclear Plants Physical Security Plan and Independent Spent Fuel Storage Installation Security Program and the Duke Energy Progress - Brunswick, Harris and Robinson Nuclear Plants Physical Security Plan, Security Training and Qualification Plan, Safeguards Contingency Pfan and Independent Spent Fuel Storage Installation Security Program.

Enclosure 3 contains the 10 CFR 50.Q4(p) Evaluations.

SAFEGUARDS INFORMATION When separated, this page is decontrolled.

SAFEGUARDS INFORMATION When separated, this page is decontrolled.

U.S. Nuclear Regulatory Commission RA-17-0046 Page 3 of 6 This document contains no new regulatory commitments. Please refer any questions regarding this submittal to Mr. Art Zaremba at 98"0-373-2062.

Sincerely, M. Christopher Nolan Director - Nuclear Regulatory Affairs

Enclosures:

1. Summary Description of Changes [SAFEGUARDS INFORMATION]
2. Copy of Duke Energy Carolinas - Catawba, McGuire and .Oconee Plants Physical Security Plan and Independent Spent Fuel Storage Installation Security Program (composite) and the Duke Energy Progress - Brunswick, Harris and Robinson Nuclear Plants Physical Security Plan, Security Training and Qualification Plan, Safeguards Contingency Plan and Independent Spent Fuel Storage Installation Security Program

[SAFEGUARDS INFORMATiON]

3. 10 CFR 50.54(p) Evaluations SAFEGUARDS INFORMATION When separated, this page is decontrolled.

SAFEGUARDS INFORMATION When separated, this page is decontrolled.

U.S. Nuclear Regulatory Commission RA-17-0046 4of6

  • xc: (w/ Enclosures) [SAFEGUARDS INFORMATION]

C. Haney, Regional Administrator U.S. Nuclear Regulatory Commission - Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, GA 30303-1257 xc: (w/o Enclosures)

AL. Hon, Project Manager (BSEP)

U. S. Nuclear Regulatory Commission One White Flint North, Mail Stop 8 G9A 11555 Rockville Pike

  • Rockville, MD 20852-2738 J.D. Austin, Project Manager (CNS)

U. S. Nuclear Regulator)i Commission One White Flint North 11555.Rockville Pike Rockville, MD 20852.:2738 M.C. Barillas, Project Manager (SHNPP)

U. S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738 G.A Hutto, Project Manager (MNS)

U. S. Nuclear Regulatory Commission One White Flint North 11555 Rockvifle Pike Rockville, MD 20852-2738 AL. Klett, Senior Project Manager (ONS)

U. S. Nuclear Regulatory Commission One White Flint North, Mail Stop 8 G9A 11555 Rockville Pike

!Rockville, MD 20852-2738 D.J. Galvin, Project Manager (HBRSEP, Unit 2)

U. S. Nuclear Regulatory Commission One White Flint North, Mail Stop 8 G9A 11555 Rockville Pike Rockville, MD 20852-2738 SAFEGUARDS INFORMATION When separated, this page is decontrolled.

SAFEGUARDS INFORMATION When separated, this page is decontrolled.

U.S. Nuclear Regulatory Commission RA-17-0046 .

5 of 6 xc: (w/o enclosures, continued)

G. Smith NRC Senior Resident Inspector Brunswick Steam Electric Plant, Unit Nos. 1 and 2 J.D. Austin NRC Senior Resident Inspector Catawba Nuclear Station G.R. Eatmon NRC Senior Resident Inspector H.B. Robinson Steam Electric Plant, Unit No. 2 G.A. Hutto NRC Senior Resident Inspector McGuire Nuclear Station E.L. Crowe NRC Senior Resident lnspecfor Oconee Nuclear Station

  • Mark Riches NRC Senior Resident Inspector Shearon Harris Nuclear Power Plant, Unit 1 SAFEGUARDS INFORMATION When separated, this page is decontrolled.

SAFEGUARDS INFORMATiON.

When separated, this page is decontrolled.

U.S. Nuclear Regulatory Commission RA-17-0046 Page 6of6 bxc: (w/out enclosures):

Lee Grzeck Bill Murray (For BSEP Licensing/Nuclear Records)

C.A. *Fletcher NCMPA PMPA NCEMC CNS Master File 801.01 - CN04DM T. S. Lowery (For CNS Licensing/Nuclear Records).

B.K. Jones J.N. Robertson Christine Magner (For SHNPP Licensing/Nuclear Records)

C.J. Thomas MNS Master File 801.01 - MG02DM P.T. Howell (For MNS Licensing/Nuclear Records)

D.M. Hubbard C.J. Wasik Michele Shealy (For ONS Licensing/Nuclear Records)

I I

. I

  • G. Sherman T. Pila Heidi Walters (For HBRSEP Licensing/Nuclear Records)

. M.C. Nolan A.H. Zaremba .

,E.T. O'Neil T.W. King T.J. Wadsworth A. Young ELL File: (Corporate)

SAFEGUARDS INFORMATION When separated, this page is decontrolled.

SAFEGUARDS INFORMATION When separated, this page is decontrolled.

U.S. Nuclear Regulatory Commission RA-17-0046 Enclosure 1 Summary Description of Changes SAFEGUARDS INFORMATION When separated, this page is decontrolled.

  • SAFEGUARDS INFORMATION When separated, this page is decontrolled.

U.S. Nuclear Regulatory Commission

. RA-17-0046 Enclosure 2 Copy of Duke Energy Carolinas - Catawba, McGuire and Oconee Plants Physical Security Plan and Independent Spent Fuel Storage Installation Security Program (composite) and the Duke Energy Progress - Brunswick, Harris and Robinson Nuclear Plants Physical Security Plan, Security Training and Qualiffcation Plan, Safeguards*

Contingency Plan and Independent Spent Fuel Storage Installation Security Program SAFEGUARDS INFORMATION When separated, this page is decontrolled.